13724 W TERRA BELLA ST 91331
Certificate Information: 13724 W TERRA BELLA ST 91331
- Application / Permit
- 20014-20000-05263
- Plan Check / Job No.
- B20VN15438
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT 18' X 20'-1" (E) DETACHED GARAGE AND ADD 23'-11.5" X 26'-6" TO CREATE INTO (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d) AND ADD 4' X 6' FOR (N) COVERED PORCH. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 2/19/2021
- Issuing Office
- Current Status
- CofO Issued on 7/17/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/30/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/11/2020 | RAPHAEL ROSAS |
| Corrections Issued | 12/12/2020 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 2/9/2021 | RAPHAEL ROSAS |
| Issued | 2/19/2021 | APPLICANT |
| CofO in Progress | 6/22/2021 | ARTHUR SARGSYAN |
| CofO in Progress | 6/22/2021 | ARTHUR SARGSYAN |
| CofO Issued | 7/17/2021 | MICHAEL SMITH |
| Permit Finaled | 7/17/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 12/23/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 12/28/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 12/28/2020 | JOHN TRIANTAFYLLOS |
| Low Impact Development | Cleared | 1/27/2021 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 1/28/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| METHANE-Barrier | 2/23/2021 | Approved | MICHEL ABAJAN |
| METHANE-Subgrade | 2/23/2021 | Approved | MICHEL ABAJAN |
| Sewer | 2/23/2021 | Approved | MICHEL ABAJAN |
| Footing/Foundation/Slab | 2/26/2021 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/8/2021 | Partial Approval | MICHEL ABAJAN |
| Service/Power Release | 3/10/2021 | Partial Inspection | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 3/22/2021 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 3/22/2021 | Approved | MICHEL ABAJAN |
| Green Building Rough | 3/22/2021 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 3/22/2021 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 3/22/2021 | Approved | MICHEL ABAJAN |
| METHANE-Rough | 3/22/2021 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 3/22/2021 | Approved | MICHEL ABAJAN |
| Insulation | 3/25/2021 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 3/31/2021 | Approved | MICHEL ABAJAN |
| Final | 5/14/2021 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 5/14/2021 | Not Ready for Inspection | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 5/14/2021 | SGSOV Approved | MICHEL ABAJAN |
| Smoke Detectors | 5/14/2021 | Approved | MICHEL ABAJAN |
| Final | 6/21/2021 | OK to Issue CofO | ARTHUR SARGSYAN |
| Green Building Final | 6/21/2021 | Approved | ARTHUR SARGSYAN |