7750 N LOUISE AVE 91406
Certificate Information: 7750 N LOUISE AVE 91406
- Application / Permit
- 20014-20000-05252
- Plan Check / Job No.
- B20VN15413
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR INT/EXT REMODEL W/ IRR 27'3"X8'11" ADDN @ FRONT, 29'7"X16'9" ADDN @ REAR W/ NEW ATT 47'3"X15' TRELLIS & 2'X29'11" ADDN @ SIDE. AND ALL NEW ROOF FRAMING. <NFPA-13D FIRE SPRINKLER SYSTEM THRU-OUT>
- Permit Issued
- Issued on 10/8/2021
- Issuing Office
- Current Status
- CofO Issued on 8/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/30/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/23/2020 | HAYATO TSUCHIYA |
| Corrections Issued | 12/26/2020 | HAYATO TSUCHIYA |
| Quality Review Completed | 12/31/2020 | STEVEN KIM |
| Applicant returned to address corrections | 2/26/2021 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 3/4/2021 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 4/11/2021 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 5/10/2021 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 9/14/2021 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 9/24/2021 | HAYATO TSUCHIYA |
| Plan Check Approved | 9/28/2021 | HAYATO TSUCHIYA |
| Building Plans Picked Up | 9/28/2021 | APPLICANT |
| Issued | 10/8/2021 | APPLICANT |
| CofO in Progress | 7/31/2024 | RAUL OLAGI |
| CofO Issued | 8/12/2024 | DANIEL ORRANTE |
| Permit Finaled | 8/12/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/5/2021 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 1/5/2021 | JOHN TRIANTAFYLLOS |
| Low Impact Development | Cleared | 8/25/2021 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 8/26/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Wood Construction | 12/3/2021 | Conditional Approval | MICHAEL TEMPLE |
| Excavation/Setback/Form/Re-Bar | 12/7/2021 | Not Ready for Inspection | RAUL OLAGI |
| Pre-Inspection | 12/7/2021 | Approved | RAUL OLAGI |
| Footing/Foundation/Slab | 12/16/2021 | Not Ready for Inspection | RAUL OLAGI |
| Footing/Foundation/Slab | 1/7/2022 | Not Ready for Inspection | MICHAEL TEMPLE |
| Footing/Foundation/Slab | 2/2/2022 | Corrections Issued | RAUL OLAGI |
| Excavation/Setback/Form/Re-Bar | 2/7/2022 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 2/23/2022 | Partial Approval | RAUL OLAGI |
| Wood Frame | 2/23/2022 | Partial Approval | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 3/1/2022 | Approved | RAUL OLAGI |
| Deputy Wood Construction | 5/27/2022 | Conditional Approval | RAUL OLAGI |
| BUILDING-Rough-Frame | 5/31/2022 | Corrections Issued | RAUL OLAGI |
| Deputy Drilled-In Anchors | 5/31/2022 | Conditional Approval | RAUL OLAGI |
| ELECTRICAL-Rough | 5/31/2022 | Approved | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 5/31/2022 | Approved | RAUL OLAGI |
| HVAC-Rough | 5/31/2022 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 5/31/2022 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 6/22/2022 | Approved | ALAN MORELOS |
| Green Building Rough | 6/22/2022 | Approved | ALAN MORELOS |
| Interior/Exterior Lathing | 6/22/2022 | Partial Approval | ALAN MORELOS |
| Drywall Nailing | 6/27/2022 | Not Ready for Inspection | ALAN MORELOS |
| Insulation | 6/27/2022 | Approved | ALAN MORELOS |
| Drywall Nailing | 6/30/2022 | Approved | ALAN MORELOS |
| Interior/Exterior Lathing | 6/30/2022 | Approved | ALAN MORELOS |
| ELECTRICAL-Final | 9/2/2022 | No Access for Inspection | RAUL OLAGI |
| Gas Test | 9/2/2022 | No Access for Inspection | RAUL OLAGI |
| HVAC-Final | 9/2/2022 | No Access for Inspection | RAUL OLAGI |
| PLUMBING-Final | 9/2/2022 | No Access for Inspection | RAUL OLAGI |
| ELECTRICAL-Final | 9/15/2022 | Corrections Issued | RAUL OLAGI |
| Final | 9/15/2022 | Corrections Issued | RAUL OLAGI |
| Footing/Foundation/Slab | 9/15/2022 | Approved | RAUL OLAGI |
| Green Building Final | 9/15/2022 | Approved | RAUL OLAGI |
| HVAC-Final | 9/15/2022 | Approved | RAUL OLAGI |
| PLUMBING-Final | 9/15/2022 | Approved | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 9/15/2022 | SGSOV Approved | RAUL OLAGI |
| Smoke Detectors | 9/15/2022 | Approved | RAUL OLAGI |
| ELECTRICAL-Final | 9/20/2022 | Approved | RAUL OLAGI |
| Final | 9/20/2022 | Corrections Issued | RAUL OLAGI |
| Final | 7/30/2024 | OK to Issue CofO | RAUL OLAGI |