145 1/2 E 98TH ST 90003
Certificate Information: 145 1/2 E 98TH ST 90003
- Application / Permit
- 20014-20000-05249
- Plan Check / Job No.
- B20VN15401
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- REMOVE EX DET (23'4"X12'2") GARAGE EXCEPT 2' OF EX EXT WALL AND CONSTRUCT (45'X25') ACCESSORY DWELLING UNIT PER ORD #186,481 W/ ADDITION & (5'X11'8") TRELLIS OVER FRONT PORCH. ALL WORK PER ENGR.
- Permit Issued
- Issued on 9/30/2021
- Issuing Office
- Current Status
- CofO Issued on 6/28/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/30/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/11/2020 | HAYATO TSUCHIYA |
| Corrections Issued | 12/12/2020 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 4/6/2021 | PETER MOSESIAN |
| Applicant returned to address corrections | 6/18/2021 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 6/24/2021 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 7/28/2021 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 8/16/2021 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 9/10/2021 | HAYATO TSUCHIYA |
| Plan Check Approved | 9/18/2021 | HAYATO TSUCHIYA |
| Building Plans Picked Up | 9/20/2021 | APPLICANT |
| Issued | 9/30/2021 | APPLICANT |
| CofO in Progress | 5/24/2022 | ALIZAH MAYAGOITIA |
| Permit Finaled | 6/28/2022 | DEROLD HAUFF |
| CofO Issued | 6/28/2022 | DEROLD HAUFF |
| Permit Finaled | 6/28/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/30/2020 | JEANIE LAM |
| Permit | Cleared | 12/30/2020 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 12/31/2020 | JEANIE LAM |
| Sewer availability | Cleared | 12/31/2020 | JEANIE LAM |
| Hydrant and Access approval | Cleared | 1/25/2021 | KURT CORRAL |
| Low Impact Development | Cleared | 5/12/2021 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 5/14/2021 | ROSA SILVA |
Contact Information
| Contractor | Polymath Development Group Inc; Lic. No.: 1069728-B | 7341 AMESTOY AVENUE VAN NUYS, CA 91406 |
| Engineer | Crook,, Barrett Cameron; Lic. No.: C57196 | 2036 CREEK RD KITTY HAWK, NC 27949 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/6/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| Footing/Foundation/Slab | 10/6/2021 | Corrections Issued | EUGENE CASSIDY |
| Underground Mechanical | 10/6/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| Footing/Foundation/Slab | 10/13/2021 | Corrections Issued | EUGENE CASSIDY |
| Underground Mechanical | 10/13/2021 | Corrections Issued | EUGENE CASSIDY |
| Underground Mechanical | 10/18/2021 | Partial Approval | CRAIG DAVIS |
| Footing/Foundation/Slab | 10/19/2021 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 10/25/2021 | Partial Approval | EUGENE CASSIDY |
| Footing/Foundation/Slab | 11/3/2021 | Corrections Issued | EUGENE CASSIDY |
| Underground Mechanical | 11/3/2021 | Approved | EUGENE CASSIDY |
| Underground Mechanical | 11/9/2021 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 11/23/2021 | Partial Approval | EUGENE CASSIDY |
| Footing/Foundation/Slab | 11/23/2021 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 11/23/2021 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 11/29/2021 | Partial Approval | EUGENE CASSIDY |
| Insulation | 11/29/2021 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 12/3/2021 | Partial Approval | ANSON MAGLASANG |
| Wood Frame | 12/3/2021 | Partial Approval | ANSON MAGLASANG |
| PLUMBING-Rough | 12/15/2021 | Approved | ANSON MAGLASANG |
| ELECTRICAL-Rough | 12/17/2021 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 12/17/2021 | Partial Approval | EUGENE CASSIDY |
| HVAC-Rough | 12/17/2021 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 12/23/2021 | Approved | JOHN KLARIN |
| ELECTRICAL-Rough | 12/23/2021 | Approved | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 12/23/2021 | Approved | JOHN KLARIN |
| Green Building Rough | 12/23/2021 | Approved | JOHN KLARIN |
| HVAC-Rough | 12/23/2021 | Approved | JOHN KLARIN |
| Insulation | 12/23/2021 | Not Ready for Inspection | JOHN KLARIN |
| Interior/Exterior Lathing | 12/23/2021 | Approved | JOHN KLARIN |
| Insulation | 12/28/2021 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 12/28/2021 | Partial Approval | EUGENE CASSIDY |
| Drywall Nailing | 12/30/2021 | Approved | DONALD CRICHLOW |
| Interior/Exterior Lathing | 1/5/2022 | Approved | DONALD CRICHLOW |
| Final | 2/16/2022 | Not Ready for Inspection | JOHN KLARIN |
| Green Building Final | 2/16/2022 | Corrections Issued | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 2/16/2022 | SGSOV Approved | JOHN KLARIN |
| Smoke Detectors | 2/16/2022 | Approved | JOHN KLARIN |
| Final | 2/25/2022 | Corrections Issued | JOHN KLARIN |
| Green Building Final | 2/25/2022 | Not Ready for Inspection | JOHN KLARIN |
| Final | 4/12/2022 | Not Ready for Inspection | JOHN KLARIN |
| Green Building Final | 4/12/2022 | Not Ready for Inspection | JOHN KLARIN |
| ELECTRICAL-Final | 4/26/2022 | Approved | JOHN KLARIN |
| Final | 4/26/2022 | Corrections Issued | JOHN KLARIN |
| Green Building Final | 4/26/2022 | Approved | JOHN KLARIN |
| PLUMBING-Final | 4/26/2022 | Approved | JOHN KLARIN |
| Final | 5/24/2022 | OK to Issue CofO | ALIZAH MAYAGOITIA |
| HVAC-Final | 5/24/2022 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 5/26/2022 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Final | 5/26/2022 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 5/26/2022 | Approved | ALIZAH MAYAGOITIA |