5465 N SALOMA AVE 91411

Certificate Information: 5465 N SALOMA AVE 91411

Application / Permit
20014-20000-05206
Plan Check / Job No.
B20VN15318
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
12'-5" X 8'-1" IRREG SHAPED ADDITION, 20'-11" X 22'-0" IRREG SHAPED ADDITION, AND 10'-0" X 21'-2" TRELLIS ADDITION PER ENGINEER.
Permit Issued
Issued on 1/25/2021
Issuing Office
Current Status
CofO Issued on 8/7/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/24/2020 APPLICANT
Assigned to Plan Check Engineer 12/8/2020 ROSENDO MEDINA
Corrections Issued 12/8/2020 ROSENDO MEDINA
Plan Check Approved 1/12/2021 JEROME MAGAT PALMA
Issued 1/25/2021 APPLICANT
CofO in Progress 7/8/2021 CHRISTOPHE COCHRAN
Permit Finaled 8/7/2021 MICHAEL SMITH
CofO Issued 8/7/2021 MICHAEL SMITH
Permit Finaled 8/7/2021 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/18/2020 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 12/18/2020 ADRIAN CASTRO
Sewer availability Cleared 12/18/2020 ADRIAN CASTRO

Contact Information

Contractor Beaver Development & Remodeling Inc; Lic. No.: 879187-B 12606 EMELITA ST      VALLEY VILLAGE, CA 91607
Engineer Salto,, Alvaro; Lic. No.: C83859 2543 E NORMAN AVE      WEST COVINA, CA 91791

Inspector Information

DAVID ANDERSON, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI
RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/17/2021 Approved ARTHUR SARGSYAN
BUILDING-Rough-Frame 2/24/2021 Partial Approval CHARLES POWELL
Floor/Roof Diaphrgm/Shear Wall 2/26/2021 Partial Approval ARTHUR SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 3/16/2021 Approved CHARLES POWELL
PLUMBING-Rough 3/19/2021 Approved BRENDAN LOONEY
Interior/Exterior Lathing 3/23/2021 Partial Approval CHARLES POWELL
Rough-Elec/Plmb/HVAC 3/23/2021 Approved CHARLES POWELL
Deputy Wood Construction 3/24/2021 Partial Approval CHARLES POWELL
BUILDING-Rough-Frame 3/25/2021 Approved CHARLES POWELL
Green Building Rough 3/26/2021 Approved ARTHUR SARGSYAN
Interior/Exterior Lathing 3/26/2021 Approved ARTHUR SARGSYAN
Green Building Rough 3/31/2021 Approved CHARLES POWELL
Drywall Nailing 4/9/2021 Approved ARTHUR SARGSYAN
Final 6/28/2021 Corrections Issued CHRISTOPHE COCHRAN
Green Building Final 6/28/2021 Not Ready for Inspection CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 6/28/2021 SGSOV Approved CHRISTOPHE COCHRAN
Smoke Detectors 6/28/2021 Approved CHRISTOPHE COCHRAN
Final 7/8/2021 OK to Issue CofO CHRISTOPHE COCHRAN