14668 W MUMFORD ST 91402
Certificate Information: 14668 W MUMFORD ST 91402
- Application / Permit
- 20014-20000-05198
- Plan Check / Job No.
- B20VN15301
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD IRREGULAR 19'-10" X 43'-6" FOR NEW BEDROOM/BATHROOM, EXTEND (E) BEDROOM AND LIVING ROOM, INTERIOR REMODEL THROUGHOUT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 5/17/2021
- Issuing Office
- Current Status
- CofO Issued on 5/11/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/24/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/3/2020 | JENNIFER LEE |
| Corrections Issued | 12/7/2020 | JENNIFER LEE |
| Plan Check Approved | 5/17/2021 | JENNIFER LEE |
| Issued | 5/17/2021 | APPLICANT |
| Building Plans Picked Up | 5/18/2021 | APPLICANT |
| CofO in Progress | 5/3/2022 | JENNIFER RABUCHIN |
| Permit Finaled | 5/11/2022 | RONALD MYRICK |
| CofO Issued | 5/11/2022 | RONALD MYRICK |
| Permit Finaled | 5/11/2022 | RONALD MYRICK |
Permit Application Clearance Information
| Low Impact Development | Cleared | 4/15/2021 | MARTIN FRAGOSO |
| Eng Process Fee Ord 176,300 | Cleared | 5/7/2021 | ADRIAN CASTRO |
| Sewer availability | Cleared | 5/7/2021 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 5/10/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Garcia, Zelada, Eddy Alexander; Lic. No.: S6159 | 17958 LULL ST RESEDA, CA 91335 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/21/2021 | Conditional Approval | MORRIS JACKSON |
| Footing/Foundation/Slab | 6/29/2021 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 7/14/2021 | Partial Inspection | JENNIFER RABUCHIN |
| PLUMBING-Rough | 7/14/2021 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 7/19/2021 | Partial Approval | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 8/16/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 8/16/2021 | Not Ready for Inspection | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 9/24/2021 | Partial Approval | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 9/24/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 9/24/2021 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 9/24/2021 | Not Ready for Inspection | JENNIFER RABUCHIN |
| HVAC-Rough | 9/24/2021 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 10/6/2021 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 10/6/2021 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 10/6/2021 | Approved | JENNIFER RABUCHIN |
| Insulation | 10/6/2021 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 10/6/2021 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 10/6/2021 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 10/15/2021 | Approved | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 10/15/2021 | Approved | ASHLEY THOMPSON |
| Final | 2/14/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 2/14/2022 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 2/14/2022 | SGSOV Not Ready | JENNIFER RABUCHIN |
| Smoke Detectors | 2/14/2022 | Approved | JENNIFER RABUCHIN |
| Final | 3/29/2022 | Partial Approval | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 3/29/2022 | SGSOV Not Ready | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 5/2/2022 | Approved | JENNIFER RABUCHIN |
| Final | 5/2/2022 | OK to Issue CofO | JENNIFER RABUCHIN |
| HVAC-Final | 5/2/2022 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 5/2/2022 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 5/2/2022 | SGSOV Approved | JENNIFER RABUCHIN |