3616 N BELLFIELD WAY 91604

Certificate Information: 3616 N BELLFIELD WAY 91604

Application / Permit
20014-20000-05197
Plan Check / Job No.
B20VN15294
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD (27'-1"x 26'-0") IRR SHAPE 2ND FLOOR MASTER BED/BATH & CLOSET & ADD/ EXPAND (8'-10"x 26'-0") LIVING & NEW COVERED PATIO @ FRONT TO (E) SINGLE FAMILY DWELLING. WORK PER ENGINEER.
Permit Issued
Issued on 5/6/2021
Issuing Office
Current Status
CofO Issued on 8/23/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/24/2020 APPLICANT
Assigned to Plan Check Engineer 12/3/2020 TROY DEGUZMAN
Corrections Issued 12/10/2020 TROY DEGUZMAN
Quality Review Completed 12/21/2020 CHON CHIO KUO
Building Plans Picked Up 12/21/2020 APPLICANT
Applicant returned to address corrections 4/22/2021 TROY DEGUZMAN
Plan Check Approved 4/26/2021 TROY DEGUZMAN
Issued 5/6/2021 APPLICANT
CofO in Progress 7/21/2022 BRIAN SULLIVAN
Permit Finaled 8/23/2022 DEROLD HAUFF
CofO Issued 8/23/2022 DEROLD HAUFF
Permit Finaled 8/23/2022 DEROLD HAUFF

Permit Application Clearance Information

Green Code Cleared 12/10/2020 TROY DEGUZMAN
Hydrant and Access approval Cleared 2/3/2021 MATTHEW CRAIG
Specific Plan Cleared 2/9/2021 LIZZI BEDUYA
ZI Cleared 2/9/2021 LIZZI BEDUYA
BHO/Hillside ordinance Cleared 3/11/2021 ADRIAN CASTRO
BHO/Hillside ordinance Cleared 3/11/2021 ADRIAN CASTRO
BHO/Hillside ordinance Cleared 3/11/2021 ADRIAN CASTRO
BHO/Hillside ordinance Cleared 3/11/2021 ADRIAN CASTRO
BHO/Hillside ordinance Cleared 3/11/2021 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 3/11/2021 ADRIAN CASTRO
Sewer availability Cleared 3/11/2021 ADRIAN CASTRO
Low Impact Development Cleared 4/8/2021 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 4/15/2021 ADRIAN CASTRO
Grading Pre-Inspection Cleared 4/22/2021 TROY DEGUZMAN

Contact Information

Architect Gilliam,, Jonathan; Lic. No.: C33995 15017 ARCHWOOD STREET      VAN NUYS, CA 91405
Contractor Swp Construction Inc; Lic. No.: 890291-B 5460 WHITE OAK AVE. #A-313      ENCINO, CA 91316
Engineer Sivushenka,, Mikita; Lic. No.: C87698 22121 CLARENDON ST APT 340      WOODLAND HILLS, CA 91367

Inspector Information

ROY SPAULDING, (213) 202-3461 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/1/2021 Approved BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 6/7/2021 Not Ready for Inspection BRIAN SULLIVAN
Footing/Foundation/Slab 6/7/2021 Not Ready for Inspection BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 6/8/2021 Approved BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 6/22/2021 Partial Approval BRIAN SULLIVAN
Insulation 6/22/2021 Partial Approval BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 7/8/2021 Partial Approval BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 9/17/2021 Conditional Approval RAUL BARAJAS
HVAC-Rough 10/1/2021 Approved BRIAN SULLIVAN
PLUMBING-Rough 10/8/2021 Approved DANIEL GONZALEZ
Special/Order Compliance 10/8/2021 Partial Approval DANIEL GONZALEZ
Deputy Drilled-In Anchors 10/12/2021 Conditional Approval JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 10/19/2021 Partial Approval BRIAN SULLIVAN
Shower Pan 10/19/2021 Approved BRIAN SULLIVAN
ELECTRICAL-Rough 10/29/2021 Partial Approval RAUL BARAJAS
Interior/Exterior Lathing 11/8/2021 Partial Approval BRIAN SULLIVAN
BUILDING-Rough-Frame 11/23/2021 Conditional Approval BRIAN SULLIVAN
Green Building Rough 11/23/2021 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 11/23/2021 Partial Approval BRIAN SULLIVAN
BUILDING-Rough-Frame 11/30/2021 Approved BRIAN SULLIVAN
Insulation 11/30/2021 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 11/30/2021 Approved BRIAN SULLIVAN
Drywall Nailing 12/13/2021 Approved BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 4/6/2022 Not Ready for Inspection BRIAN SULLIVAN
Footing/Foundation/Slab 4/25/2022 Approved BRIAN SULLIVAN
ELECTRICAL-Final 6/9/2022 Approved BRIAN SULLIVAN
Final 6/9/2022 Corrections Issued BRIAN SULLIVAN
Green Building Final 6/9/2022 Approved BRIAN SULLIVAN
HVAC-Final 6/9/2022 Approved BRIAN SULLIVAN
PLUMBING-Final 6/9/2022 Approved BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 6/9/2022 SGSOV Approved BRIAN SULLIVAN
Smoke Detectors 6/9/2022 Approved BRIAN SULLIVAN
Final 6/14/2022 Corrections Issued BRIAN SULLIVAN
Final 7/20/2022 OK to Issue CofO BRIAN SULLIVAN