10450 N LEV AVE 91331

Certificate Information: 10450 N LEV AVE 91331

Application / Permit
20014-20000-05195
Plan Check / Job No.
B20VN15272
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
REMOVE 14'-9" x 5'-0" BREEZEWAY AND 16'-0" x 20'-0" PATIO COVER TO SEPARATE SINGLE FAMILY DWELLING FROM GARAGE. REMOVE 4'-10" x 24'-2" PORTION OF (E) GARAGE, CONVERT 15'-4" x 24'-2" REMEANING PORTION OF (E) GARAGE TO ACCESSORY DWELLING UNIT AND ADD 25'-9" x 15'-10" AND 23'-1" x 15'-4" TO IT PER LAMC 12.22 A.33 (c)-(d). ALL WORK DONE PER WFPP.
Permit Issued
Issued on 1/28/2022
Issuing Office
Current Status
CofO Issued on 8/25/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/2/2020 APPLICANT
Assigned to Plan Check Engineer 12/15/2020 SARKIS HARABEDIAN
Corrections Issued 12/17/2020 SARKIS HARABEDIAN
Plan Check Approved 1/7/2022 SARKIS HARABEDIAN
Building Plans Picked Up 1/13/2022 APPLICANT
Issued 1/28/2022 APPLICANT
CofO in Progress 6/27/2023 JENNIFER RABUCHIN
Permit Finaled 8/25/2023 RUBEN SALAS
CofO Issued 8/25/2023 RUBEN SALAS
Permit Finaled 8/25/2023 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 1/5/2021 JOHN TRIANTAFYLLOS
Permit Cleared 1/7/2021 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 1/13/2021 JOHN TRIANTAFYLLOS
Sewer availability Cleared 1/13/2021 JOHN TRIANTAFYLLOS
Construction near power lines Cleared 4/27/2021 RIDWAN HARDY
Construction within easement Cleared 4/27/2021 RIDWAN HARDY
Hydrant and Access approval Cleared 8/6/2021 GILBERT URREA
Low Impact Development Cleared 11/17/2021 TA ANH
Roof/Waste drainage to street Cleared 12/8/2021 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/8/2022 Partial Inspection JENNIFER RABUCHIN
Footing/Foundation/Slab 6/3/2022 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 6/3/2022 Not Ready for Inspection JENNIFER RABUCHIN
METHANE-Rough 6/3/2022 Not Ready for Inspection JENNIFER RABUCHIN
PLUMBING-Rough 6/3/2022 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 6/16/2022 Approved JENNIFER RABUCHIN
METHANE-Barrier 6/16/2022 Approved JENNIFER RABUCHIN
METHANE-Subgrade 6/16/2022 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 7/7/2022 Partial Approval JENNIFER RABUCHIN
Green Building Rough 7/7/2022 Not Ready for Inspection JENNIFER RABUCHIN
METHANE-Rough 7/7/2022 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 8/16/2022 Corrections Issued JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 8/16/2022 Partial Approval JENNIFER RABUCHIN
HVAC-Rough 8/16/2022 Not Ready for Inspection JENNIFER RABUCHIN
PLUMBING-Rough 8/16/2022 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 8/26/2022 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 8/26/2022 Approved JENNIFER RABUCHIN
Green Building Rough 8/26/2022 Approved JENNIFER RABUCHIN
HVAC-Rough 8/26/2022 Partial Approval JENNIFER RABUCHIN
Interior/Exterior Lathing 8/26/2022 Partial Approval JENNIFER RABUCHIN
Insulation 9/6/2022 Not Ready for Inspection JENNIFER RABUCHIN
Insulation 9/13/2022 No Access for Inspection CHRISTOPHER DELLEFIELD
Shower Pan 9/13/2022 No Access for Inspection CHRISTOPHER DELLEFIELD
Insulation 9/21/2022 Approved JENNIFER RABUCHIN
Shower Pan 9/21/2022 Corrections Issued JENNIFER RABUCHIN
Drywall Nailing 10/6/2022 Approved JENNIFER RABUCHIN
Sewer 10/12/2022 Approved JENNIFER RABUCHIN
Shower Pan 10/12/2022 Approved JENNIFER RABUCHIN
Special/Order Compliance 10/12/2022 Corrections Issued JENNIFER RABUCHIN
Underground Mechanical 10/12/2022 Partial Approval JENNIFER RABUCHIN
Interior/Exterior Lathing 12/8/2022 Approved JENNIFER RABUCHIN
Service/Power Release 3/23/2023 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Final 4/27/2023 Approved JENNIFER RABUCHIN
PLUMBING-Final 4/27/2023 Approved JENNIFER RABUCHIN
Final 6/22/2023 Corrections Issued JENNIFER RABUCHIN
Green Building Final 6/22/2023 Approved JENNIFER RABUCHIN
HVAC-Final 6/22/2023 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 6/22/2023 SGSOV Not Ready JENNIFER RABUCHIN
Service/Power Release 6/22/2023 Conditional Approval JENNIFER RABUCHIN
Smoke Detectors 6/22/2023 Approved JENNIFER RABUCHIN
Final 6/27/2023 OK to Issue CofO JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 6/27/2023 SGSOV Approved JENNIFER RABUCHIN