4320 N SUTTON PL 91403

Certificate Information: 4320 N SUTTON PL 91403

Application / Permit
20014-20000-05192
Plan Check / Job No.
B20VN15263
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
IRREGULAR ADDITIONS TO (E) 1-STORY SFD W/ ATTACHED GARAGE; INTERIOR REMODEL
Permit Issued
Issued on 5/8/2021
Issuing Office
Current Status
CofO Issued on 9/19/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/24/2020 APPLICANT
Assigned to Plan Check Engineer 12/3/2020 NILOOFAR MEHRAIN
Corrections Issued 12/8/2020 NILOOFAR MEHRAIN
Quality Review Completed 12/8/2020 CHON CHIO KUO
Building Plans Picked Up 12/9/2020 APPLICANT
Applicant returned to address corrections 1/12/2021 NILOOFAR MEHRAIN
Plan Check Approved 3/26/2021 NILOOFAR MEHRAIN
Issued 5/8/2021 APPLICANT
CofO in Progress 9/19/2022 JACK KARGODORIAN
Permit Finaled 9/19/2022 DANIEL ORRANTE
CofO Issued 9/19/2022 DANIEL ORRANTE
Permit Finaled 9/19/2022 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/5/2021 ADRIAN CASTRO
Sewer availability Cleared 1/5/2021 ADRIAN CASTRO
GPI Written Notices Cleared 1/12/2021 NILOOFAR MEHRAIN
Grading Pre-Inspection Cleared 1/12/2021 NILOOFAR MEHRAIN
Hydrant and Access approval Cleared 3/19/2021 MATTHEW CRAIG
Low Impact Development Cleared 4/30/2021 MITESH PATEL
Roof/Waste drainage to street Cleared 5/3/2021 JOHN TRIANTAFYLLOS

Contact Information

Contractor Zimmitti Construction Inc; Lic. No.: 701765-B 6319 BERQUIST AVENUE      WOODLAND HILLS, CA 91367
Engineer Berkoz,, Ertunga; Lic. No.: S2504 4665 ELLENITA AVE      TARZANA, CA 91356

Inspector Information

RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/25/2021 Corrections Issued CHRISTOPHE COCHRAN
Underground Mechanical 6/25/2021 Approved CHRISTOPHE COCHRAN
Footing/Foundation/Slab 7/2/2021 Approved ARTHUR SARGSYAN
Deputy Drilled-In Anchors 7/8/2021 Conditional Approval CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 7/13/2021 Partial Approval CHARLES POWELL
Deputy Reinf. Concrete 7/14/2021 Conditional Approval CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 7/16/2021 Partial Approval CHARLES POWELL
Floor/Roof Diaphrgm/Shear Wall 8/25/2021 Partial Approval CHARLES POWELL
Deputy Wood Construction 9/27/2021 Conditional Approval MICHAEL PELHAM
BUILDING-Rough-Frame 10/26/2021 Approved JACK KARGODORIAN
ELECTRICAL-Rough 10/26/2021 Approved JACK KARGODORIAN
Green Building Rough 10/26/2021 Approved JACK KARGODORIAN
HVAC-Rough 10/26/2021 Approved JACK KARGODORIAN
PLUMBING-Rough 10/26/2021 Approved JACK KARGODORIAN
Insulation 10/29/2021 Conditional Approval MICHAEL PELHAM
Interior/Exterior Lathing 11/1/2021 Partial Approval CHRISTOPHE COCHRAN
Drywall Nailing 11/8/2021 Approved ASHLEY THOMPSON
Drywall Nailing 11/10/2021 Approved JACK KARGODORIAN
Shower Pan 11/15/2021 Conditional Approval ASHLEY THOMPSON
Interior/Exterior Lathing 12/2/2021 Approved JACK KARGODORIAN
Final 9/12/2022 Corrections Issued JACK KARGODORIAN
Green Building Final 9/12/2022 Not Ready for Inspection JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 9/12/2022 SGSOV Not Ready JACK KARGODORIAN
Smoke Detectors 9/12/2022 Approved JACK KARGODORIAN
Final 9/16/2022 OK to Issue CofO JACK KARGODORIAN
Green Building Final 9/16/2022 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 9/16/2022 SGSOV Approved JACK KARGODORIAN