10938 W NETTLETON ST 91352
Certificate Information: 10938 W NETTLETON ST 91352
- Application / Permit
- 20014-20000-05168
- Plan Check / Job No.
- B20VN15216
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2 STORY ACCESSORY DWELLING UNIT (27'-0"X 31'-0") PER FIRE SPRINKLERS NFPA 13D
- Permit Issued
- Issued on 11/23/2021
- Issuing Office
- Current Status
- CofO Issued on 3/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/23/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/23/2020 | MOHAMMAD ESMAILI |
| Corrections Issued | 1/14/2021 | MOHAMMAD ESMAILI |
| Quality Review Completed | 1/14/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 1/14/2021 | APPLICANT |
| Plan Check Approved | 11/22/2021 | MOHAMMAD ESMAILI |
| Issued | 11/23/2021 | APPLICANT |
| CofO in Progress | 2/21/2023 | DAVID ANDERSON |
| Permit Finaled | 3/21/2023 | MICHAEL SMITH |
| CofO Issued | 3/21/2023 | MICHAEL SMITH |
| Permit Finaled | 3/21/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 1/19/2021 | GABRIEL ROBLES |
| Clean Up Green Up | Cleared | 1/20/2021 | LAUREN PADICK |
| ZI | Cleared | 1/20/2021 | LAUREN PADICK |
| Eng Process Fee Ord 176,300 | Cleared | 2/3/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 2/3/2021 | GABRIEL ROBLES |
| Low Impact Development | Cleared | 5/16/2021 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 6/14/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 8/31/2021 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 10/10/2021 | RUEL COLE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Papazyan,, Andranik; Lic. No.: C56824 | 635 W COLORADO ST STE 104 GLENDALE, CA 91204 |
Inspector Information
| DAVID ANDERSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/16/2022 | Partial Approval | MISAEL ESPARZA |
| PLUMBING-Rough | 2/16/2022 | Partial Approval | MISAEL ESPARZA |
| Footing/Foundation/Slab | 2/24/2022 | Approved | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 4/27/2022 | Corrections Issued | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 5/2/2022 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 6/14/2022 | Conditional Approval | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/23/2022 | Conditional Approval | MATT KELLERMAN |
| PLUMBING-Rough | 6/23/2022 | Conditional Approval | MATT KELLERMAN |
| Underground Mechanical | 6/23/2022 | Approved | MATT KELLERMAN |
| Deputy Wood Construction | 6/24/2022 | Conditional Approval | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/22/2022 | Approved | DAVID ANDERSON |
| Green Building Rough | 7/22/2022 | Approved | DAVID ANDERSON |
| HVAC-Rough | 7/22/2022 | Approved | DAVID ANDERSON |
| Wood Frame | 7/22/2022 | Approved | DAVID ANDERSON |
| Insulation | 7/27/2022 | Corrections Issued | DAVID ANDERSON |
| Special/Order Compliance | 7/27/2022 | Approved | DAVID MATSON |
| Insulation | 8/1/2022 | Not Ready for Inspection | DAVID ANDERSON |
| Insulation | 8/3/2022 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 8/10/2022 | Approved | DAVID ANDERSON |
| Drywall Nailing | 8/15/2022 | Approved | DAVID ANDERSON |
| Shower Pan | 8/19/2022 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 8/24/2022 | Approved | DAVID ANDERSON |
| Special/Order Compliance | 10/28/2022 | Not Ready for Inspection | DAVID ANDERSON |
| Underground Mechanical | 10/28/2022 | Not Ready for Inspection | DAVID ANDERSON |
| ELECTRICAL-Final | 11/22/2022 | Approved | DAVID ANDERSON |
| Service/Power Release | 11/22/2022 | Corrections Issued | DAVID ANDERSON |
| BUILDING-Rough-Frame | 12/23/2022 | Approved | DAVID ANDERSON |
| Final | 12/23/2022 | Corrections Issued | DAVID ANDERSON |
| Green Building Final | 12/23/2022 | Approved | DAVID ANDERSON |
| MERV13>=Final | 12/23/2022 | Approved | DAVID ANDERSON |
| MERV13>=Rough | 12/23/2022 | Approved | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 12/23/2022 | SGSOV Approved | DAVID ANDERSON |
| Service/Power Release | 12/23/2022 | Not Ready for Inspection | DAVID ANDERSON |
| Smoke Detectors | 12/23/2022 | Approved | DAVID ANDERSON |
| Verify Sprinkler Sign Off | 12/23/2022 | Approved | DAVID ANDERSON |
| Final | 1/17/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Service/Power Release | 1/17/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Final | 2/21/2023 | OK to Issue CofO | DAVID ANDERSON |
| Service/Power Release | 2/21/2023 | Approved | DAVID ANDERSON |