12328 W DEBBY ST 91606

Certificate Information: 12328 W DEBBY ST 91606

Application / Permit
20014-20000-05165
Plan Check / Job No.
B20VN15214
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
43'-1" X 23'-9" ADDITION TO (E) SFD FOR TWO BEDROOMS AND BATHROOMS. NEW 30'-5" X 23'-1" ATTACHED PATIO. REMODEL (E) BEDROOM. WORK PER ENGINEER.
Permit Issued
Issued on 4/5/2021
Issuing Office
Current Status
Issued on 4/5/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/21/2020 APPLICANT
Assigned to Plan Check Engineer 11/30/2020 ROSENDO MEDINA
Corrections Issued 12/1/2020 ROSENDO MEDINA
Applicant returned to address corrections 12/16/2020 ROSENDO MEDINA
Plan Check Approved 4/5/2021 ROSENDO MEDINA
Issued 4/5/2021 APPLICANT
Building Plans Picked Up 4/6/2021 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/11/2021 ADRIAN CASTRO
Sewer availability Cleared 1/11/2021 ADRIAN CASTRO
Low Impact Development Cleared 3/24/2021 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 3/25/2021 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Tabirara,, Vernon Nicolas; Lic. No.: C75492 17520 DAPHNE AVE      TORRANCE, CA 90504

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/13/2021 Corrections Issued RICHARD DOCKUS
Footing/Foundation/Slab 4/20/2021 Approved RICHARD DOCKUS
Underground Mechanical 5/11/2021 Approved RICHARD DOCKUS
BUILDING-Rough-Frame 5/17/2021 Partial Approval RICHARD DOCKUS
Insulation 5/17/2021 Partial Approval RICHARD DOCKUS
Wood Frame 5/21/2021 Partial Approval RICHARD DOCKUS
Wood Frame 6/2/2021 Partial Approval RICHARD DOCKUS
BUILDING-Rough-Frame 7/23/2021 Partial Approval CHRISTOPHE COCHRAN
Green Building Rough 7/23/2021 Approved CHRISTOPHE COCHRAN
MERV13>=Rough 7/23/2021 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 9/14/2021 Partial Approval CHRISTOPHE COCHRAN
ELECTRICAL-Rough 9/14/2021 Approved CHRISTOPHE COCHRAN
HVAC-Rough 9/14/2021 Approved CHRISTOPHE COCHRAN
Green Building Rough 9/20/2021 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 9/20/2021 Approved CHRISTOPHE COCHRAN
Shower Pan 9/28/2021 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 9/30/2021 Approved CHRISTOPHE COCHRAN
Insulation 10/4/2021 Approved ASHLEY THOMPSON
Drywall Nailing 10/8/2021 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 2/24/2022 Approved CHRISTOPHE COCHRAN
Final 2/24/2022 Corrections Issued CHRISTOPHE COCHRAN
Green Building Final 2/24/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
MERV13>=Final 2/24/2022 Approved CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 2/24/2022 SGSOV Approved CHRISTOPHE COCHRAN
Smoke Detectors 2/24/2022 Approved CHRISTOPHE COCHRAN