20332 W CLARK ST 91367

Certificate Information: 20332 W CLARK ST 91367

Application / Permit
20014-20000-05157
Plan Check / Job No.
B20VN15187
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
12 X 26'5" BEDROOM ADDITION TO THE (E) SFD. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 3/18/2021
Issuing Office
Current Status
CofO Issued on 12/20/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/20/2020 APPLICANT
Assigned to Plan Check Engineer 12/3/2020 PARISA ZAHABI
Corrections Issued 12/3/2020 PARISA ZAHABI
Applicant returned to address corrections 3/3/2021 PARISA ZAHABI
Plan Check Approved 3/18/2021 PARISA ZAHABI
Issued 3/18/2021 APPLICANT
Building Plans Picked Up 3/18/2021 APPLICANT
CofO in Progress 12/17/2021 STEVEN BACK
Permit Finaled 12/20/2021 JOHN JANSON
CofO Issued 12/20/2021 JOHN JANSON
Permit Finaled 12/20/2021 JOHN JANSON

Permit Application Clearance Information

Grading Pre-Inspection Cleared 1/26/2021 BARTON HOLMES
Eng Process Fee Ord 176,300 Cleared 2/18/2021 GABRIEL ROBLES
Roof/Waste drainage to street Cleared 2/18/2021 GABRIEL ROBLES
Sewer availability Cleared 2/18/2021 GABRIEL ROBLES

Contact Information

Contractor Owner-Builder       ,
Engineer Basma,, Ali J; Lic. No.: C53080 21500 WYANDOTTE ST 106      CANOGA PARK, CA 91303

Inspector Information

DAVID FASTIGGI, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI
ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/23/2021 Corrections Issued HENRY KIM
Footing/Foundation/Slab 3/26/2021 Corrections Issued HENRY KIM
Pre-Inspection 3/26/2021 Corrections Issued HENRY KIM
Footing/Foundation/Slab 4/23/2021 Approved VINCENT HANLEY
Shower Pan 6/24/2021 Approved ASHLEY THOMPSON
ELECTRICAL-Rough 6/29/2021 Corrections Issued HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 6/29/2021 Corrections Issued HENRY KIM
Green Building Rough 6/29/2021 Not Ready for Inspection HENRY KIM
Interior/Exterior Lathing 6/29/2021 Approved HENRY KIM
MERV13>=Rough 6/29/2021 Not Ready for Inspection HENRY KIM
BUILDING-Rough-Frame 7/15/2021 Corrections Issued HENRY KIM
ELECTRICAL-Rough 7/15/2021 Approved HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 7/15/2021 Approved HENRY KIM
Green Building Rough 7/15/2021 Not Ready for Inspection HENRY KIM
Deputy Wood Construction 7/16/2021 Conditional Approval ALIZAH MAYAGOITIA
Insulation 7/26/2021 Approved RYAN SALAZAR
Interior/Exterior Lathing 7/26/2021 Corrections Issued RYAN SALAZAR
BUILDING-Rough-Frame 7/29/2021 Approved HENRY KIM
Drywall Nailing 7/29/2021 Corrections Issued HENRY KIM
Green Building Rough 7/29/2021 Approved HENRY KIM
HVAC-Rough 7/29/2021 Approved HENRY KIM
Interior/Exterior Lathing 7/29/2021 Approved HENRY KIM
MERV13>=Rough 7/29/2021 Approved HENRY KIM
Drywall Nailing 8/2/2021 Corrections Issued ASHLEY THOMPSON
Final 11/15/2021 Corrections Issued STEVEN BACK
Green Building Final 11/15/2021 Approved STEVEN BACK
MERV13>=Final 11/15/2021 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 11/15/2021 SGSOV Approved STEVEN BACK
Smoke Detectors 11/15/2021 Not Ready for Inspection STEVEN BACK
Final 11/24/2021 Not Ready for Inspection STEVEN BACK
Smoke Detectors 11/24/2021 Approved STEVEN BACK
Final 12/17/2021 OK to Issue CofO STEVEN BACK