13456 W BESSEMER ST 91401

Certificate Information: 13456 W BESSEMER ST 91401

Application / Permit
20014-20000-05130
Plan Check / Job No.
B20VN15137
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 29'8" X 21'7" TWO STORY DETACHED ACCESSORY DWELLING UNIT AS PER LAMC 12.22.A33.(C) AND (E), ALL WORK PER ENGINEERING
Permit Issued
Issued on 4/12/2022
Issuing Office
Current Status
CofO Issued on 7/31/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/2/2020 APPLICANT
Assigned to Plan Check Engineer 12/30/2020 RARES BODEA
Corrections Issued 1/3/2021 RARES BODEA
Quality Review Completed 1/7/2021 STEVEN KIM
Building Plans Picked Up 1/7/2021 APPLICANT
Applicant returned to address corrections 11/15/2021 RARES BODEA
Applicant returned to address corrections 11/23/2021 RARES BODEA
Plan Check Approved 11/23/2021 RARES BODEA
Issued 4/12/2022 APPLICANT
CofO in Progress 6/25/2024 JOSE AVILA
Permit Finaled 7/31/2024 RUBEN SALAS
CofO Issued 7/31/2024 RUBEN SALAS
Permit Finaled 7/31/2024 RUBEN SALAS

Permit Application Clearance Information

Permit Cleared 2/1/2021 GABRIEL ROBLES
Sewer availability Cleared 2/22/2021 GABRIEL ROBLES
Construction near power lines Cleared 3/3/2021 WALTER RAMIREZ
Construction within easement Cleared 3/3/2021 WALTER RAMIREZ
Address approval Cleared 3/30/2021 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 4/5/2021 GABRIEL ROBLES
Low Impact Development Cleared 8/12/2021 YVAINNE GALSIM
Roof/Waste drainage to street Cleared 8/13/2021 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/29/2022 Not Ready for Inspection RAFAEL CORTES
PLUMBING-Rough 9/29/2022 Corrections Issued RAFAEL CORTES
Footing/Foundation/Slab 10/6/2022 Corrections Issued RAFAEL CORTES
Footing/Foundation/Slab 11/3/2022 Approved WILLIAM WREN
PLUMBING-Rough 11/3/2022 Partial Approval WILLIAM WREN
Wood Frame 11/23/2022 Corrections Issued MISAEL ESPARZA
Wood Frame 12/2/2022 Partial Approval JORDAN KUTZLY
Wood Frame 12/29/2022 Conditional Approval JOHN COLEMAN
ELECTRICAL-Rough 2/17/2023 Approved KIRK SANDERS
HVAC-Rough 2/17/2023 Approved KIRK SANDERS
PLUMBING-Rough 2/17/2023 Corrections Issued KIRK SANDERS
Underground Mechanical 2/17/2023 Approved KIRK SANDERS
Wood Frame 2/17/2023 Not Ready for Inspection KIRK SANDERS
BUILDING-Rough-Frame 2/24/2023 Conditional Approval KIRK SANDERS
PLUMBING-Rough 2/24/2023 Approved KIRK SANDERS
Insulation 2/27/2023 Approved WILLIAM WREN
Interior/Exterior Lathing 2/27/2023 Approved WILLIAM WREN
Drywall Nailing 3/7/2023 Approved KIRK SANDERS
Green Building Rough 3/7/2023 Approved KIRK SANDERS
Interior/Exterior Lathing 3/7/2023 Approved KIRK SANDERS
Shower Pan 3/7/2023 Approved KIRK SANDERS
Sewer 4/10/2023 Approved KIRK SANDERS
BUILDING-Rough-Frame 6/6/2023 Not Ready for Inspection KIRK SANDERS
ELECTRICAL-Final 6/6/2023 Corrections Issued KIRK SANDERS
Final 6/6/2023 Corrections Issued KIRK SANDERS
Green Building Final 6/6/2023 Approved KIRK SANDERS
HVAC-Final 6/6/2023 Corrections Issued KIRK SANDERS
PLUMBING-Final 6/6/2023 Corrections Issued KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 6/6/2023 SGSOV Not Ready KIRK SANDERS
Service/Power Release 6/6/2023 Not Ready for Inspection KIRK SANDERS
Smoke Detectors 6/6/2023 Not Ready for Inspection KIRK SANDERS
Verify Sprinkler Sign Off 6/6/2023 Not Ready for Inspection KIRK SANDERS
BUILDING-Rough-Frame 1/12/2024 Not Ready for Inspection CHRISTOPHER ROJAS
ELECTRICAL-Final 1/12/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Final 1/12/2024 Corrections Issued CHRISTOPHER ROJAS
HVAC-Final 1/12/2024 Not Ready for Inspection CHRISTOPHER ROJAS
PLUMBING-Final 1/12/2024 Not Ready for Inspection CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 1/12/2024 SGSOV Not Ready CHRISTOPHER ROJAS
Service/Power Release 1/12/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Smoke Detectors 1/12/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Verify Sprinkler Sign Off 1/12/2024 Not Ready for Inspection CHRISTOPHER ROJAS
BUILDING-Rough-Frame 1/29/2024 Approved JOSE AVILA
ELECTRICAL-Final 1/29/2024 Corrections Issued JOSE AVILA
SGSOV-Seismic Gas S/O Valve 1/29/2024 SGSOV Approved JOSE AVILA
Smoke Detectors 1/29/2024 Corrections Issued JOSE AVILA
Verify Sprinkler Sign Off 1/29/2024 Approved JOSE AVILA
ELECTRICAL-Final 2/16/2024 Not Ready for Inspection JENNIFER RABUCHIN
Gas Test 2/16/2024 Approved JENNIFER RABUCHIN
HVAC-Final 2/16/2024 Approved JENNIFER RABUCHIN
Special/Order Compliance 2/16/2024 Corrections Issued JENNIFER RABUCHIN
Final 5/13/2024 Corrections Issued JENNIFER RABUCHIN
Green Building Final 5/13/2024 Approved JENNIFER RABUCHIN
Service/Power Release 5/13/2024 Not Ready for Inspection JENNIFER RABUCHIN
Smoke Detectors 5/13/2024 Approved JENNIFER RABUCHIN
Final 6/24/2024 OK to Issue CofO JOSE AVILA
Service/Power Release 6/24/2024 Approved JOSE AVILA