5175 N CASPAR AVE 90041
Certificate Information: 5175 N CASPAR AVE 90041
- Application / Permit
- 20014-20000-05103
- Plan Check / Job No.
- B20VN14997
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD 12' 2" X 16' 10" TO DETACHED GARAGE AND CONVERT TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK DONE PER STRUCTURAL ENGINEERING.
- Permit Issued
- Issued on 7/24/2021
- Issuing Office
- Current Status
- CofO Issued on 12/1/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/19/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/17/2020 | GURUNATH NESARAJAH |
| Corrections Issued | 12/19/2020 | GURUNATH NESARAJAH |
| Quality Review Completed | 1/6/2021 | OMID HEDAYAT |
| Applicant returned to address corrections | 4/10/2021 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 5/15/2021 | GURUNATH NESARAJAH |
| Plan Check Approved | 6/21/2021 | GURUNATH NESARAJAH |
| Building Plans Picked Up | 7/22/2021 | APPLICANT |
| Issued | 7/24/2021 | APPLICANT |
| CofO in Progress | 11/29/2021 | CRAIG VAUGHAN |
| Permit Finaled | 12/1/2021 | DEROLD HAUFF |
| CofO Issued | 12/1/2021 | DEROLD HAUFF |
| Permit Finaled | 12/1/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/10/2021 | RENZ SORIANO |
| Permit | Cleared | 2/10/2021 | RENZ SORIANO |
| Construction near power lines | Cleared | 2/16/2021 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 2/17/2021 | RENZ SORIANO |
| Grading Pre-Inspection | Cleared | 3/16/2021 | PATRICK MISCHLICH |
| Roof/Waste drainage to street | Cleared | 4/27/2021 | RENZ SORIANO |
| Sewer availability | Cleared | 5/18/2021 | RENZ SORIANO |
Contact Information
| Architect | Agaian,, Raffi; Lic. No.: C32156 | 2234 DEL MAR ROAD UNIT # 1 MONTROSE, CA 91020 |
| Contractor | Gil Hugo; Lic. No.: 534005-B | 5720 OWENSMOUTH AVE 181 WOODLAND HILLS, CA 91367 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/29/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Underground Mechanical | 8/4/2021 | Partial Approval | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 8/5/2021 | Corrections Issued | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 8/5/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| Underground Mechanical | 8/9/2021 | Partial Approval | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 8/12/2021 | Approved | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 8/12/2021 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 8/30/2021 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 8/30/2021 | Approved | CRAIG VAUGHAN |
| Green Building Rough | 8/30/2021 | Approved | CRAIG VAUGHAN |
| PLUMBING-Rough | 8/30/2021 | Approved | CRAIG VAUGHAN |
| Wood Frame | 8/30/2021 | Approved | CRAIG VAUGHAN |
| HVAC-Rough | 9/3/2021 | Partial Approval | CRAIG VAUGHAN |
| Insulation | 9/3/2021 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 9/3/2021 | Approved | CRAIG VAUGHAN |
| Drywall Nailing | 9/10/2021 | Approved | CRAIG VAUGHAN |
| HVAC-Rough | 9/10/2021 | Approved | CRAIG VAUGHAN |
| Shower Pan | 9/30/2021 | Approved | KATHRYN BUTTERWORTH |
| ELECTRICAL-Final | 11/9/2021 | Approved | CRAIG VAUGHAN |
| Final | 11/9/2021 | Corrections Issued | CRAIG VAUGHAN |
| Green Building Final | 11/9/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| HVAC-Final | 11/9/2021 | Approved | CRAIG VAUGHAN |
| PLUMBING-Final | 11/9/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 11/9/2021 | SGSOV Approved | CRAIG VAUGHAN |
| Smoke Detectors | 11/9/2021 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Final | 11/15/2021 | Approved | CRAIG VAUGHAN |
| Final | 11/15/2021 | Conditional Approval | CRAIG VAUGHAN |
| Gas Test | 11/15/2021 | Approved | CRAIG VAUGHAN |
| Green Building Final | 11/15/2021 | Approved | CRAIG VAUGHAN |
| HVAC-Final | 11/15/2021 | Approved | CRAIG VAUGHAN |
| PLUMBING-Final | 11/15/2021 | Approved | CRAIG VAUGHAN |