10375-10375 1/2 N SHARP AVE 91331

Certificate Information: 10375-10375 1/2 N SHARP AVE 91331

Application / Permit
20014-20000-05090
Plan Check / Job No.
B20VN14975
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 26'8" X 21' ADDITION TOO AND CONVERT THE (E) 21' X 21' DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22.C33(C) AND (E), ALL WORK PER ENGINEERING "COMPLY WITH DEPARTMENT ORDER effective date 07/08/2008. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE.
Permit Issued
Issued on 12/6/2021
Issuing Office
Current Status
CofO Issued on 1/25/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/21/2020 APPLICANT
Assigned to Plan Check Engineer 12/7/2020 RARES BODEA
Corrections Issued 12/7/2020 RARES BODEA
Building Plans Picked Up 12/18/2020 APPLICANT
Applicant returned to address corrections 7/26/2021 RARES BODEA
Applicant returned to address corrections 9/20/2021 RARES BODEA
Applicant returned to address corrections 11/2/2021 RARES BODEA
Plan Check Approved 11/23/2021 RARES BODEA
Issued 12/6/2021 APPLICANT
CofO in Progress 1/10/2023 JENNIFER RABUCHIN
Permit Finaled 1/25/2023 MICHAEL SMITH
CofO Issued 1/25/2023 MICHAEL SMITH
Permit Finaled 1/25/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 3/31/2021 MARKOS PEREZ-BRAN
ZA Case Cleared 4/5/2021 LOUIS ORTEGA
ZA Case Cleared 4/5/2021 LOUIS ORTEGA
Eng Process Fee Ord 176,300 Cleared 4/12/2021 MARKOS PEREZ-BRAN
Low Impact Development Cleared 6/25/2021 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 7/6/2021 CARLOS AGUILERA
Sewer availability Cleared 7/6/2021 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 1/19/2022 Corrections Issued MICHAEL TEMPLE
PLUMBING-Rough 1/27/2022 Partial Approval JENNIFER RABUCHIN
Sewer 1/27/2022 Partial Approval JENNIFER RABUCHIN
Footing/Foundation/Slab 2/2/2022 Conditional Approval JENNIFER RABUCHIN
METHANE-Barrier 2/2/2022 Approved JENNIFER RABUCHIN
METHANE-Subgrade 2/2/2022 Approved JENNIFER RABUCHIN
Underground Mechanical 2/15/2022 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 3/7/2022 Partial Approval JENNIFER RABUCHIN
Green Building Rough 3/7/2022 Not Ready for Inspection JENNIFER RABUCHIN
MERV13>=Rough 3/7/2022 Not Ready for Inspection JENNIFER RABUCHIN
METHANE-Rough 3/7/2022 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 3/29/2022 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 3/29/2022 Not Ready for Inspection JENNIFER RABUCHIN
Gas Test 3/29/2022 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 3/29/2022 Corrections Issued JENNIFER RABUCHIN
Deputy Drilled-In Anchors 4/18/2022 Conditional Approval MICHAEL TEMPLE
Footing/Foundation/Slab 4/18/2022 Corrections Issued JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 4/28/2022 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 5/10/2022 Corrections Issued DEANDRE HOFFMAN
BUILDING-Rough-Frame 5/13/2022 Partial Inspection JENNIFER RABUCHIN
ELECTRICAL-Rough 5/13/2022 Approved JENNIFER RABUCHIN
Green Building Rough 5/13/2022 Approved JENNIFER RABUCHIN
HVAC-Rough 5/13/2022 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 5/13/2022 Partial Approval JENNIFER RABUCHIN
MERV13>=Rough 5/13/2022 Approved JENNIFER RABUCHIN
PLUMBING-Rough 5/13/2022 Partial Approval JENNIFER RABUCHIN
Insulation 5/17/2022 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 5/17/2022 Partial Approval JENNIFER RABUCHIN
Drywall Nailing 5/26/2022 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 6/6/2022 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 10/3/2022 Approved JENNIFER RABUCHIN
Final 10/3/2022 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 10/3/2022 Approved JENNIFER RABUCHIN
Green Building Final 10/3/2022 Corrections Issued JENNIFER RABUCHIN
MERV13>=Final 10/3/2022 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 10/3/2022 SGSOV Not Ready JENNIFER RABUCHIN
Smoke Detectors 10/3/2022 Not Ready for Inspection JENNIFER RABUCHIN
Final 1/3/2023 Corrections Issued JENNIFER RABUCHIN
Green Building Final 1/3/2023 Approved JENNIFER RABUCHIN
MERV13>=Final 1/3/2023 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 1/3/2023 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 1/3/2023 Approved JENNIFER RABUCHIN
HVAC-Final 1/9/2023 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 1/10/2023 Approved JENNIFER RABUCHIN
Final 1/10/2023 OK to Issue CofO JENNIFER RABUCHIN
HVAC-Final 1/10/2023 Approved JENNIFER RABUCHIN
PLUMBING-Final 1/10/2023 Approved JENNIFER RABUCHIN