9006-9008 N RUBIO AVE 91343

Certificate Information: 9006-9008 N RUBIO AVE 91343

Application / Permit
20014-20000-05087
Plan Check / Job No.
B20VN14964
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD 5' 6" X 12' 6" TO ATTACHED GARAGE AND CONVERT TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (e). ALL WORK DONE PER WFPP.
Permit Issued
Issued on 9/27/2021
Issuing Office
Current Status
CofO Issued on 3/16/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/17/2020 APPLICANT
Assigned to Plan Check Engineer 11/24/2020 GURUNATH NESARAJAH
Corrections Issued 11/26/2020 GURUNATH NESARAJAH
Plan Check Approved 8/25/2021 GURUNATH NESARAJAH
No Progress 8/25/2021 GURUNATH NESARAJAH
Plan Check Approved 9/13/2021 GURUNATH NESARAJAH
Building Plans Picked Up 9/17/2021 APPLICANT
Issued 9/27/2021 APPLICANT
CofO in Progress 2/23/2022 RAUL OLAGI
Permit Finaled 3/16/2022 RONALD MYRICK
CofO Issued 3/16/2022 RONALD MYRICK
Permit Finaled 3/16/2022 RONALD MYRICK

Permit Application Clearance Information

Address approval Cleared 3/15/2021 JOHN TRIANTAFYLLOS
Roof/Waste drainage to street Cleared 3/15/2021 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 3/16/2021 JOHN TRIANTAFYLLOS
Sewer availability Cleared 3/16/2021 JOHN TRIANTAFYLLOS

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 10/20/2021 Approved ALAN MORELOS
Underground Mechanical 10/20/2021 Approved ALAN MORELOS
Deputy Drilled-In Anchors 10/21/2021 Conditional Approval RAUL OLAGI
Underground Mechanical 10/26/2021 Corrections Issued RAUL OLAGI
Footing/Foundation/Slab 11/2/2021 Approved MICHAEL TEMPLE
PLUMBING-Rough 11/2/2021 Partial Approval MICHAEL TEMPLE
Floor/Roof Diaphrgm/Shear Wall 11/10/2021 Partial Approval RAUL OLAGI
ELECTRICAL-Rough 12/3/2021 Approved ALAN MORELOS
Floor/Roof Diaphrgm/Shear Wall 12/3/2021 Approved ALAN MORELOS
PLUMBING-Rough 12/3/2021 Corrections Issued ALAN MORELOS
BUILDING-Rough-Frame 12/7/2021 Partial Approval RAUL OLAGI
Green Building Rough 12/7/2021 Not Ready for Inspection RAUL OLAGI
HVAC-Rough 12/7/2021 Approved RAUL OLAGI
Insulation 12/7/2021 Partial Approval RAUL OLAGI
PLUMBING-Rough 12/7/2021 Approved RAUL OLAGI
Drywall Nailing 12/28/2021 Corrections Issued RAUL OLAGI
Interior/Exterior Lathing 12/28/2021 Partial Approval RAUL OLAGI
Drywall Nailing 1/7/2022 Approved MICHAEL TEMPLE
BUILDING-Rough-Frame 1/24/2022 Approved STEPHANIE SWANSON
Green Building Rough 1/24/2022 Approved STEPHANIE SWANSON
Interior/Exterior Lathing 1/24/2022 Approved STEPHANIE SWANSON
Interior/Exterior Lathing 1/24/2022 Partial Approval STEPHANIE SWANSON
ELECTRICAL-Final 2/17/2022 Approved RAUL OLAGI
Final 2/17/2022 Corrections Issued RAUL OLAGI
HVAC-Final 2/17/2022 Approved RAUL OLAGI
PLUMBING-Final 2/17/2022 Approved RAUL OLAGI
Final 2/22/2022 OK to Issue CofO RAUL OLAGI
Green Building Final 2/22/2022 Approved RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 2/22/2022 SGSOV Approved RAUL OLAGI
Smoke Detectors 2/22/2022 Approved RAUL OLAGI