5051 N COLFAX AVE 91601
Certificate Information: 5051 N COLFAX AVE 91601
- Application / Permit
- 20014-20000-05084
- Plan Check / Job No.
- B20VN14957
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED MASTER BEDRM W/ BATH ADDN (27'6"X14') AT REAR OF EXISTING 1-STORY SFD PER ENGR DESIGN.
- Permit Issued
- Issued on 10/5/2021
- Issuing Office
- Current Status
- CofO Issued on 1/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/30/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/4/2020 | HAYATO TSUCHIYA |
| Corrections Issued | 12/7/2020 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 2/11/2021 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 4/6/2021 | LUIS RINCON |
| Plan Check Approved | 4/21/2021 | LUIS RINCON |
| Building Plans Picked Up | 4/22/2021 | APPLICANT |
| Issued | 10/5/2021 | APPLICANT |
| CofO in Progress | 1/17/2023 | DAVID MATSON |
| CofO Issued | 1/21/2023 | MICHAEL SMITH |
| Permit Finaled | 1/21/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 12/30/2020 | LEE GUILBEAUX |
| Sewer availability | Cleared | 12/30/2020 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 1/12/2021 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 1/12/2021 | LEE GUILBEAUX |
| Specific Plan | Cleared | 1/20/2021 | ANDREW JORGENSEN |
| Specific Plan | Cleared | 1/20/2021 | ANDREW JORGENSEN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Wu,, Harold Ping-Hung; Lic. No.: C35693 | 1168 SAN GABRIEL BLVD NO N ROSEMEAD, CA 91770 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/12/2021 | Conditional Approval | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 11/5/2021 | Conditional Approval | THOMAS FINNILA |
| PLUMBING-Rough | 11/5/2021 | Conditional Approval | THOMAS FINNILA |
| PLUMBING-Rough | 11/9/2021 | Corrections Issued | CALEB MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 11/15/2021 | Partial Approval | ARAM AVEDISIAN |
| Insulation | 11/15/2021 | Partial Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 11/15/2021 | Partial Approval | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/23/2021 | Partial Approval | THOMAS FINNILA |
| BUILDING-Rough-Frame | 12/2/2021 | Partial Approval | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 12/2/2021 | Partial Approval | THOMAS FINNILA |
| Interior/Exterior Lathing | 12/20/2021 | Partial Approval | CALEB MEISTER |
| Shower Pan | 12/20/2021 | Approved | CALEB MEISTER |
| ELECTRICAL-Rough | 12/23/2021 | Approved | MATT KELLERMAN |
| PLUMBING-Rough | 12/23/2021 | Approved | MATT KELLERMAN |
| Insulation | 12/28/2021 | Corrections Issued | DEANDRE HOFFMAN |
| Insulation | 12/29/2021 | Approved | THOMAS FINNILA |
| Drywall Nailing | 1/5/2022 | Approved | THOMAS FINNILA |
| Green Building Rough | 1/5/2022 | Approved | THOMAS FINNILA |
| BUILDING-Rough-Frame | 2/25/2022 | Approved | THOMAS FINNILA |
| Final | 2/25/2022 | Not Ready for Inspection | THOMAS FINNILA |
| Footing/Foundation/Slab | 2/25/2022 | Approved | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 2/25/2022 | SGSOV Not Ready | THOMAS FINNILA |
| Final | 9/23/2022 | Not Ready for Inspection | THOMAS FINNILA |
| Green Building Final | 9/23/2022 | Approved | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 9/23/2022 | SGSOV Approved | THOMAS FINNILA |
| Smoke Detectors | 9/23/2022 | Approved | THOMAS FINNILA |
| Final | 10/7/2022 | Corrections Issued | THOMAS FINNILA |
| Final | 1/17/2023 | OK to Issue CofO | DAVID MATSON |