5051 N COLFAX AVE 91601

Certificate Information: 5051 N COLFAX AVE 91601

Application / Permit
20014-20000-05084
Plan Check / Job No.
B20VN14957
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED MASTER BEDRM W/ BATH ADDN (27'6"X14') AT REAR OF EXISTING 1-STORY SFD PER ENGR DESIGN.
Permit Issued
Issued on 10/5/2021
Issuing Office
Current Status
CofO Issued on 1/21/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/30/2020 APPLICANT
Assigned to Plan Check Engineer 12/4/2020 HAYATO TSUCHIYA
Corrections Issued 12/7/2020 HAYATO TSUCHIYA
Applicant returned to address corrections 2/11/2021 HAYATO TSUCHIYA
Applicant returned to address corrections 4/6/2021 LUIS RINCON
Plan Check Approved 4/21/2021 LUIS RINCON
Building Plans Picked Up 4/22/2021 APPLICANT
Issued 10/5/2021 APPLICANT
CofO in Progress 1/17/2023 DAVID MATSON
CofO Issued 1/21/2023 MICHAEL SMITH
Permit Finaled 1/21/2023 MICHAEL SMITH

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 12/30/2020 LEE GUILBEAUX
Sewer availability Cleared 12/30/2020 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 1/12/2021 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 1/12/2021 LEE GUILBEAUX
Specific Plan Cleared 1/20/2021 ANDREW JORGENSEN
Specific Plan Cleared 1/20/2021 ANDREW JORGENSEN

Contact Information

Contractor Owner-Builder       ,
Engineer Wu,, Harold Ping-Hung; Lic. No.: C35693 1168 SAN GABRIEL BLVD NO N      ROSEMEAD, CA 91770

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/12/2021 Conditional Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 11/5/2021 Conditional Approval THOMAS FINNILA
PLUMBING-Rough 11/5/2021 Conditional Approval THOMAS FINNILA
PLUMBING-Rough 11/9/2021 Corrections Issued CALEB MEISTER
Floor/Roof Diaphrgm/Shear Wall 11/15/2021 Partial Approval ARAM AVEDISIAN
Insulation 11/15/2021 Partial Approval ARAM AVEDISIAN
PLUMBING-Rough 11/15/2021 Partial Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 11/23/2021 Partial Approval THOMAS FINNILA
BUILDING-Rough-Frame 12/2/2021 Partial Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 12/2/2021 Partial Approval THOMAS FINNILA
Interior/Exterior Lathing 12/20/2021 Partial Approval CALEB MEISTER
Shower Pan 12/20/2021 Approved CALEB MEISTER
ELECTRICAL-Rough 12/23/2021 Approved MATT KELLERMAN
PLUMBING-Rough 12/23/2021 Approved MATT KELLERMAN
Insulation 12/28/2021 Corrections Issued DEANDRE HOFFMAN
Insulation 12/29/2021 Approved THOMAS FINNILA
Drywall Nailing 1/5/2022 Approved THOMAS FINNILA
Green Building Rough 1/5/2022 Approved THOMAS FINNILA
BUILDING-Rough-Frame 2/25/2022 Approved THOMAS FINNILA
Final 2/25/2022 Not Ready for Inspection THOMAS FINNILA
Footing/Foundation/Slab 2/25/2022 Approved THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 2/25/2022 SGSOV Not Ready THOMAS FINNILA
Final 9/23/2022 Not Ready for Inspection THOMAS FINNILA
Green Building Final 9/23/2022 Approved THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 9/23/2022 SGSOV Approved THOMAS FINNILA
Smoke Detectors 9/23/2022 Approved THOMAS FINNILA
Final 10/7/2022 Corrections Issued THOMAS FINNILA
Final 1/17/2023 OK to Issue CofO DAVID MATSON