330 W 118TH ST 90061

Certificate Information: 330 W 118TH ST 90061

Application / Permit
20014-20000-05073
Plan Check / Job No.
B20VN14915
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 20' X 22' 2-CAR GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK DONE PER WFPP.
Permit Issued
Issued on 10/5/2021
Issuing Office
Current Status
CofO Issued on 3/9/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/17/2020 APPLICANT
Assigned to Plan Check Engineer 11/24/2020 GURUNATH NESARAJAH
Corrections Issued 11/26/2020 GURUNATH NESARAJAH
Applicant returned to address corrections 5/3/2021 LUISANGEL VALENZUELA
Plan Check Approved 6/8/2021 LUISANGEL VALENZUELA
No Progress 8/26/2021 GURUNATH NESARAJAH
Plan Check Approved 10/4/2021 GURUNATH NESARAJAH
Issued 10/5/2021 APPLICANT
Building Plans Picked Up 10/6/2021 APPLICANT
CofO in Progress 10/3/2022 ALIZAH MAYAGOITIA
CofO Issued 3/9/2023 ANSON MAGLASANG
Permit Finaled 3/9/2023 ANSON MAGLASANG

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 4/8/2021 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 5/4/2021 THOMAS LANG
Address approval Cleared 6/2/2021 JEREMY CHOK
Sewer availability Cleared 6/2/2021 JEREMY CHOK

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 12/28/2021 Corrections Issued EUGENE CASSIDY
Gas Test 12/28/2021 Corrections Issued EUGENE CASSIDY
PLUMBING-Rough 12/28/2021 Corrections Issued EUGENE CASSIDY
Wood Frame 12/28/2021 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Rough 2/16/2022 Approved JOHN KLARIN
Gas Test 2/16/2022 Partial Approval JOHN KLARIN
Interior/Exterior Lathing 2/16/2022 Corrections Issued JOHN KLARIN
PLUMBING-Rough 2/16/2022 Approved JOHN KLARIN
Smoke Detectors 2/16/2022 Not Ready for Inspection JOHN KLARIN
Wood Frame 2/16/2022 Approved JOHN KLARIN
Insulation 2/22/2022 Partial Approval JOHN KLARIN
Interior/Exterior Lathing 2/22/2022 Not Ready for Inspection JOHN KLARIN
Insulation 2/25/2022 Approved JOHN KLARIN
Interior/Exterior Lathing 2/25/2022 Approved JOHN KLARIN
Drywall Nailing 3/7/2022 Corrections Issued JOHN KLARIN
Service/Power Release 3/7/2022 Not Ready for Inspection JOHN KLARIN
Drywall Nailing 3/14/2022 Approved JOHN KLARIN
Service/Power Release 3/14/2022 Not Ready for Inspection JOHN KLARIN
BUILDING-Rough-Frame 4/21/2022 Approved JOHN KLARIN
Final 4/21/2022 Corrections Issued JOHN KLARIN
Green Building Final 4/21/2022 Corrections Issued JOHN KLARIN
Green Building Rough 4/21/2022 Approved JOHN KLARIN
MERV13>=Final 4/21/2022 Approved JOHN KLARIN
MERV13>=Rough 4/21/2022 Approved JOHN KLARIN
METHANE-Final 4/21/2022 Approved JOHN KLARIN
METHANE-Rough 4/21/2022 Approved JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 4/21/2022 SGSOV Approved JOHN KLARIN
Smoke Detectors 4/21/2022 Approved JOHN KLARIN
Footing/Foundation/Slab 6/2/2022 No Access for Inspection JOHN KLARIN
Final 6/3/2022 Corrections Issued JOHN KLARIN
Green Building Final 6/3/2022 Approved JOHN KLARIN
Final 6/27/2022 Corrections Issued JOHN KLARIN
Final 7/1/2022 Conditional Approval ALIZAH MAYAGOITIA
ELECTRICAL-Final 7/25/2022 Approved JOHN KLARIN
Final 9/7/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Final 10/3/2022 OK to Issue CofO ALIZAH MAYAGOITIA