5747 N ZELZAH AVE 91316

Certificate Information: 5747 N ZELZAH AVE 91316

Application / Permit
20014-20000-05063
Plan Check / Job No.
B20VN14878
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
29'-9" X 42'-8" IRREG SHAPED ADDITION AND REMODEL TO ENLARGE KITCHEN AND ADD NEW BEDROOM AND BATHROOM. 28'-6" X 4'-2" IRREG SHAPED ADDITION TO ENLARGE TWO (E) BEDROOMS AND REMODEL TWO BATHROOMS.
Permit Issued
Issued on 5/9/2021
Issuing Office
Current Status
CofO Issued on 9/15/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/16/2020 APPLICANT
Assigned to Plan Check Engineer 11/24/2020 JEROME MAGAT PALMA
Corrections Issued 11/27/2020 JEROME MAGAT PALMA
Applicant returned to address corrections 4/26/2021 JEROME MAGAT PALMA
Plan Check Approved 4/30/2021 JEROME MAGAT PALMA
Issued 5/9/2021 APPLICANT
Building Plans Picked Up 5/14/2021 APPLICANT
CofO in Progress 8/23/2022 SEAN HAUPT
CofO Issued 9/15/2022 MICHAEL SMITH
Permit Finaled 9/15/2022 MICHAEL SMITH

Permit Application Clearance Information

Low Impact Development Cleared 4/9/2021 MITESH PATEL
Eng Process Fee Ord 176,300 Cleared 4/12/2021 GABRIEL ROBLES
Sewer availability Cleared 4/12/2021 GABRIEL ROBLES
Roof/Waste drainage to street Cleared 4/14/2021 GABRIEL ROBLES
ZI Cleared 4/16/2021 MIGUEL GAMBOA

Contact Information

Contractor Sb Construction & Remodeling Inc; Lic. No.: 1061509-B P O BOX 260915      ENCINO, CA 91426
Engineer Standley,, Craig Erick; Lic. No.: C87675 5330 ZELZAH AVE UNIT 7      ENCINO, CA 91316

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/15/2021 Corrections Issued STEVEN BACK
Excavation/Setback/Form/Re-Bar 7/20/2021 Not Ready for Inspection PETER FOLLING
PLUMBING-Rough 7/30/2021 Partial Approval STEVEN BACK
BUILDING-Rough-Frame 8/3/2021 Partial Approval STEVEN BACK
Footing/Foundation/Slab 8/3/2021 Not Ready for Inspection STEVEN BACK
Green Building Rough 8/3/2021 Not Ready for Inspection STEVEN BACK
Insulation 8/3/2021 Partial Approval STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 8/5/2021 Partial Approval RONALD COWAN
Footing/Foundation/Slab 8/5/2021 Approved RONALD COWAN
BUILDING-Rough-Frame 8/17/2021 Partial Approval STEVEN BACK
PLUMBING-Rough 8/17/2021 Partial Approval STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 9/17/2021 Partial Approval STEVEN BACK
ELECTRICAL-Rough 10/14/2021 Approved SEAN HAUPT
HVAC-Rough 10/14/2021 Approved SEAN HAUPT
PLUMBING-Rough 10/14/2021 Approved SEAN HAUPT
Interior/Exterior Lathing 10/25/2021 Approved SEAN HAUPT
Shower Pan 10/25/2021 Approved SEAN HAUPT
Green Building Rough 10/29/2021 Approved SEAN HAUPT
Interior/Exterior Lathing 10/29/2021 Partial Approval SEAN HAUPT
Insulation 11/3/2021 Partial Approval JAVIER RAMOS JR
Drywall Nailing 11/9/2021 Approved SEAN HAUPT
Interior/Exterior Lathing 12/10/2021 Partial Approval JUSTIN HAWLEY
Interior/Exterior Lathing 12/21/2021 Approved SEAN HAUPT
ELECTRICAL-Final 1/27/2022 Not Ready for Inspection PETER FOLLING
BUILDING-Rough-Frame 2/4/2022 Approved SEAN HAUPT
ELECTRICAL-Final 2/4/2022 Approved SEAN HAUPT
Final 2/4/2022 Corrections Issued SEAN HAUPT
Green Building Final 2/4/2022 Not Ready for Inspection SEAN HAUPT
HVAC-Final 2/4/2022 Approved SEAN HAUPT
PLUMBING-Final 2/4/2022 Approved SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 2/4/2022 SGSOV Not Ready SEAN HAUPT
Smoke Detectors 2/4/2022 Approved SEAN HAUPT
Final 8/23/2022 OK to Issue CofO SEAN HAUPT
Green Building Final 8/23/2022 Approved SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 8/23/2022 SGSOV Approved SEAN HAUPT