13823 W BROMWICH ST 91331

Certificate Information: 13823 W BROMWICH ST 91331

Application / Permit
20014-20000-05056
Plan Check / Job No.
B20VN14852
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT 6'-4" X 13'-0" IRREG SHAPED PORTION OF COVERED PATIO TO ENLARGE BEDROOM. 6'-4" X 11'-0" ADDITION FOR NEW BATHROOM AND CLOSET. ALL WORK PER WFPP.
Permit Issued
Issued on 3/17/2021
Issuing Office
Current Status
CofO Issued on 6/11/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/19/2020 APPLICANT
Assigned to Plan Check Engineer 11/24/2020 JEROME MAGAT PALMA
Corrections Issued 11/26/2020 JEROME MAGAT PALMA
Plan Check Approved 3/17/2021 JEROME MAGAT PALMA
Issued 3/17/2021 APPLICANT
CofO in Progress 4/5/2022 GREGG CUMMINGS
Permit Finaled 6/11/2022 DANIEL ORRANTE
CofO Issued 6/11/2022 DANIEL ORRANTE
Permit Finaled 6/11/2022 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/16/2020 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 12/16/2020 ADRIAN CASTRO

Contact Information

Contractor Aligned Construction Company Inc; Lic. No.: 894983-B 8905 GLENOAKS BLVD UNIT L      SUN VALLEY, CA 91352

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/12/2021 Approved GREGG CUMMINGS
Excavation/Setback/Form/Re-Bar 4/22/2021 Approved GREGG CUMMINGS
Footing/Foundation/Slab 4/22/2021 Approved GREGG CUMMINGS
PLUMBING-Rough 4/22/2021 Partial Approval GREGG CUMMINGS
BUILDING-Rough-Frame 5/10/2021 Partial Approval GREGG CUMMINGS
Insulation 5/10/2021 Partial Approval GREGG CUMMINGS
PLUMBING-Rough 5/10/2021 Partial Approval GREGG CUMMINGS
PLUMBING-Rough 5/17/2021 Not Ready for Inspection DANIEL ORRANTE
ELECTRICAL-Rough 9/13/2021 Approved GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 9/13/2021 Approved GREGG CUMMINGS
Green Building Rough 9/13/2021 Approved GREGG CUMMINGS
PLUMBING-Rough 9/13/2021 Not Ready for Inspection GREGG CUMMINGS
BUILDING-Rough-Frame 10/5/2021 Approved GREGG CUMMINGS
HVAC-Rough 10/5/2021 Approved GREGG CUMMINGS
PLUMBING-Rough 10/5/2021 Approved GREGG CUMMINGS
Insulation 10/27/2021 Approved WILLIAM WREN
Interior/Exterior Lathing 10/27/2021 Approved WILLIAM WREN
Drywall Nailing 11/3/2021 Approved GREGG CUMMINGS
Interior/Exterior Lathing 12/2/2021 Approved WILLIAM WREN
Final 3/25/2022 Corrections Issued GREGG CUMMINGS
Green Building Final 3/25/2022 Approved GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 3/25/2022 SGSOV Approved GREGG CUMMINGS
Smoke Detectors 3/25/2022 Not Ready for Inspection GREGG CUMMINGS
ELECTRICAL-Final 4/5/2022 Approved GREGG CUMMINGS
Final 4/5/2022 OK to Issue CofO GREGG CUMMINGS
HVAC-Final 4/5/2022 Approved GREGG CUMMINGS
PLUMBING-Final 4/5/2022 Approved GREGG CUMMINGS
Smoke Detectors 4/5/2022 Approved GREGG CUMMINGS