17323 W OTSEGO ST 91316
Certificate Information: 17323 W OTSEGO ST 91316
- Application / Permit
- 20014-20000-05044
- Plan Check / Job No.
- B20VN14805
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 25' 7" X 16' 2" ADDITION TO REAR AND MAJOR INTERIOR REMODEL TO REVISE FLOOR PLAN LAYOUT OF (E) SFD. ALL WORK DONE PER STRUCTURAL ENGINEERING.
- Permit Issued
- Issued on 4/8/2021
- Issuing Office
- Current Status
- CofO Issued on 8/27/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/16/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/24/2020 | GURUNATH NESARAJAH |
| Corrections Issued | 11/27/2020 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 2/19/2021 | GURUNATH NESARAJAH |
| Plan Check Approved | 3/7/2021 | GURUNATH NESARAJAH |
| Issued | 4/8/2021 | APPLICANT |
| Building Plans Picked Up | 4/13/2021 | APPLICANT |
| CofO in Progress | 7/15/2022 | SEAN HAUPT |
| Permit Finaled | 8/27/2022 | MICHAEL SMITH |
| CofO Issued | 8/27/2022 | MICHAEL SMITH |
| Permit Finaled | 8/27/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Sewer availability | Cleared | 12/18/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 12/22/2020 | ADRIAN CASTRO |
| Low Impact Development | Cleared | 2/4/2021 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 2/8/2021 | ADRIAN CASTRO |
| ZI | Cleared | 2/24/2021 | LAUREN PADICK |
Contact Information
| Architect | Spock,, Karen Zindler- Shuler; Lic. No.: C25136 | 1127 N LA BREA AVENUE INGLEWOOD, CA 90302 |
| Contractor | Build Method Construction Inc; Lic. No.: 1059684-B | 12117 VALLEYHEART DRIVE SUITE 305 STUDIO CITY, CA 91604 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/14/2021 | Corrections Issued | STEVEN BACK |
| Footing/Foundation/Slab | 4/22/2021 | Corrections Issued | STEVEN BACK |
| BUILDING-Rough-Frame | 5/4/2021 | Partial Approval | STEVEN BACK |
| Excavation/Setback/Form/Re-Bar | 5/4/2021 | Approved | STEVEN BACK |
| Footing/Foundation/Slab | 5/4/2021 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 5/6/2021 | Partial Approval | STEVEN BACK |
| Insulation | 5/6/2021 | Corrections Issued | STEVEN BACK |
| PLUMBING-Rough | 5/6/2021 | Partial Approval | STEVEN BACK |
| Insulation | 5/11/2021 | Partial Approval | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 5/18/2021 | Partial Approval | RONALD COWAN |
| Deputy Drilled-In Anchors | 6/7/2021 | Conditional Approval | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 6/10/2021 | Corrections Issued | STEVEN BACK |
| Deputy Wood Construction | 6/11/2021 | Conditional Approval | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 6/17/2021 | Approved | STEVEN BACK |
| PLUMBING-Rough | 7/2/2021 | Approved | STEVEN BACK |
| ELECTRICAL-Rough | 7/20/2021 | Approved | RONALD COWAN |
| HVAC-Rough | 7/22/2021 | Approved | STEVEN BACK |
| Insulation | 8/3/2021 | Not Ready for Inspection | STEVEN BACK |
| Interior/Exterior Lathing | 8/3/2021 | Partial Approval | STEVEN BACK |
| Shower Pan | 8/3/2021 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 8/12/2021 | Approved | STEVEN BACK |
| Green Building Rough | 8/12/2021 | Corrections Issued | STEVEN BACK |
| Interior/Exterior Lathing | 8/12/2021 | Approved | STEVEN BACK |
| Green Building Rough | 8/17/2021 | Approved | STEVEN BACK |
| Insulation | 8/17/2021 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 8/17/2021 | Approved | STEVEN BACK |
| Drywall Nailing | 8/26/2021 | Partial Approval | RYAN SALAZAR |
| Drywall Nailing | 8/27/2021 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 8/30/2021 | Partial Inspection | RYAN SALAZAR |
| Gas Test | 12/14/2021 | Approved | SEAN HAUPT |
| ELECTRICAL-Final | 1/19/2022 | Approved | SEAN HAUPT |
| Final | 1/19/2022 | Corrections Issued | SEAN HAUPT |
| Green Building Final | 1/19/2022 | Approved | SEAN HAUPT |
| HVAC-Final | 1/19/2022 | Corrections Issued | SEAN HAUPT |
| PLUMBING-Final | 1/19/2022 | Approved | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 1/19/2022 | SGSOV Approved | SEAN HAUPT |
| Smoke Detectors | 1/19/2022 | Approved | SEAN HAUPT |
| Final | 7/15/2022 | OK to Issue CofO | SEAN HAUPT |