20716 W STAGG ST 91306

Certificate Information: 20716 W STAGG ST 91306

Application / Permit
20014-20000-05043
Plan Check / Job No.
B20VN14801
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
12' 6" X 26' 6" MASTER BEDROOM/BATHROOM/CLOSET ADDITION TO REAR OF (E) SFD. ALL WORK DONE PER STRUCTURAL ENGINEERING.
Permit Issued
Issued on 6/11/2021
Issuing Office
Current Status
CofO Issued on 9/23/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/15/2020 APPLICANT
Assigned to Plan Check Engineer 11/20/2020 GURUNATH NESARAJAH
Corrections Issued 11/22/2020 GURUNATH NESARAJAH
Plan Check Approved 3/20/2021 GURUNATH NESARAJAH
Issued 6/11/2021 APPLICANT
Building Plans Picked Up 6/16/2021 APPLICANT
CofO in Progress 9/20/2022 STEVEN BACK
Permit Finaled 9/23/2022 JOHN JANSON
CofO Issued 9/23/2022 JOHN JANSON
Permit Finaled 9/23/2022 JOHN JANSON

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 12/15/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 12/17/2020 ADRIAN CASTRO
Sewer availability Cleared 12/17/2020 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Yenjai,, Seree; Lic. No.: C73151 3249 SHADYLAWN DRIVE      DUARTE, CA 91010

Inspector Information

DAVID FASTIGGI, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI
ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/21/2021 Approved HENRY KIM
Footing/Foundation/Slab 8/25/2021 Corrections Issued HENRY KIM
PLUMBING-Rough 8/25/2021 Corrections Issued HENRY KIM
BUILDING-Rough-Frame 8/30/2021 Corrections Issued HENRY KIM
Footing/Foundation/Slab 8/30/2021 Corrections Issued HENRY KIM
PLUMBING-Rough 8/30/2021 Corrections Issued HENRY KIM
Footing/Foundation/Slab 9/8/2021 Corrections Issued HENRY KIM
Footing/Foundation/Slab 9/14/2021 Approved HENRY KIM
BUILDING-Rough-Frame 10/5/2021 Not Ready for Inspection HENRY KIM
ELECTRICAL-Rough 10/5/2021 Approved HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 10/5/2021 Partial Approval HENRY KIM
Interior/Exterior Lathing 2/2/2022 Not Ready for Inspection JAVIER RAMOS JR
Shower Pan 2/2/2022 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 2/11/2022 Partial Approval STEVEN BACK
BUILDING-Rough-Frame 3/16/2022 Approved STEVEN BACK
Green Building Rough 3/16/2022 Approved STEVEN BACK
HVAC-Rough 3/16/2022 Approved STEVEN BACK
PLUMBING-Rough 3/16/2022 Approved STEVEN BACK
Insulation 3/24/2022 Approved JESUS PINEDA
Drywall Nailing 4/13/2022 Approved JESUS PINEDA
Interior/Exterior Lathing 5/18/2022 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 9/15/2022 SGSOV Not Ready STEVEN BACK
Final 9/20/2022 OK to Issue CofO STEVEN BACK
Green Building Final 9/20/2022 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 9/20/2022 SGSOV Approved STEVEN BACK
Smoke Detectors 9/20/2022 Approved STEVEN BACK