14380 W BEAVER ST 91342
Certificate Information: 14380 W BEAVER ST 91342
- Application / Permit
- 20014-20000-05011
- Plan Check / Job No.
- B20VN14693
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- REMOVE (E) CARPORT. 18'-0" X 8'-0" PATIO COVER ADDITION AND 18'-0" X 15'-6" ADDITION TO CONVERT (E) REC ROOM TO ACCESSORY DWELLING UNIT.
- Permit Issued
- Issued on 7/13/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/11/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/16/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/24/2020 | JEROME MAGAT PALMA |
| Corrections Issued | 11/26/2020 | JEROME MAGAT PALMA |
| Plan Check Approved | 1/5/2022 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 1/11/2022 | APPLICANT |
| Issued | 7/13/2022 | APPLICANT |
| CofO in Progress | 3/10/2023 | JENNIFER RABUCHIN |
| No Progress | 3/21/2023 | ROBERT GOLD |
| CofO in Progress | 4/5/2023 | RONALD MYRICK |
| CofO Issued | 4/11/2023 | MICHAEL SMITH |
| Permit Finaled | 4/11/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 2/22/2021 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 2/22/2021 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 3/26/2021 | ADRIAN CASTRO |
| Sewer availability | Cleared | 3/26/2021 | ADRIAN CASTRO |
| Construction near power lines | Cleared | 7/19/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/15/2022 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 9/2/2022 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Rough | 9/2/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2022 | Approved | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 9/19/2022 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 10/5/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 10/5/2022 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Rough | 10/5/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Underground Mechanical | 10/5/2022 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 10/18/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 10/18/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 10/18/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 10/18/2022 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 10/18/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 10/18/2022 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 10/18/2022 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 10/24/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Insulation | 10/24/2022 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 10/31/2022 | Partial Approval | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 10/31/2022 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 12/8/2022 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 12/8/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 12/8/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 12/8/2022 | Approved | JENNIFER RABUCHIN |
| Green Building Final | 12/8/2022 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Final | 12/8/2022 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Final | 12/8/2022 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 12/8/2022 | SGSOV Not Ready | JENNIFER RABUCHIN |
| Smoke Detectors | 12/8/2022 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 1/27/2023 | Approved | JENNIFER RABUCHIN |
| Final | 1/27/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 1/27/2023 | Partial Approval | JENNIFER RABUCHIN |
| HVAC-Final | 1/27/2023 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 1/27/2023 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 1/27/2023 | SGSOV Approved | JENNIFER RABUCHIN |
| Final | 3/10/2023 | OK to Issue CofO | JENNIFER RABUCHIN |
| Green Building Final | 3/10/2023 | Approved | JENNIFER RABUCHIN |