13453 W MARGATE ST 91401

Certificate Information: 13453 W MARGATE ST 91401

Application / Permit
20014-20000-05008
Plan Check / Job No.
B20VN14685
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMOVE ALL EXTERIOR AND INTERIOR WALLS OF AN EXISTING ONE STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE EXCEPT 10'3" LF AT SOUTH PORTION OF THE SITE AND BUILD AN IRREGULAR 55' X 44'3" TWO STORY SINGLE FAMILY DWELLING WITH AN ATTACHED TWO CAR GARAGE, NFPA-13D FIRE SPRINKLERS REQUIRED , ALL WORK PER ENGINEERING "COMPLY WITH DEPARTMENT ORDER effective date 04/13/2021. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 7/1/2021
Issuing Office
Current Status
CofO Issued on 6/15/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/11/2020 APPLICANT
Assigned to Plan Check Engineer 12/10/2020 RARES BODEA
Corrections Issued 12/24/2020 RARES BODEA
Quality Review Completed 12/28/2020 STEVEN KIM
Building Plans Picked Up 12/30/2020 APPLICANT
Applicant returned to address corrections 6/15/2021 RARES BODEA
Plan Check Approved 6/29/2021 RARES BODEA
Issued 7/1/2021 APPLICANT
CofO in Progress 6/14/2022 ROBERT MINASSIANS
CofO Issued 6/15/2022 DANIEL SANCHEZ
Permit Finaled 6/15/2022 DANIEL SANCHEZ

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/19/2021 JOHN TRIANTAFYLLOS
Permit Cleared 2/19/2021 JOHN TRIANTAFYLLOS
Sewer availability Cleared 2/19/2021 JOHN TRIANTAFYLLOS
Trees in Parkway Cleared 3/8/2021 JOHN KIM
Hydrant and Access approval Cleared 4/21/2021 MATTHEW CRAIG
Low Impact Development Cleared 5/20/2021 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 5/24/2021 GABRIEL ROBLES

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno S; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

JOEL ORDAZ, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
PTOLEMY HILL, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
JONATHAN FRANCHINI, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVAKIAN, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
EDMOND DECKERT, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
TIMOTHY KEY, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
ROBERT CHAVEZ, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 9/7/2021 No Access for Inspection GORDON ZUBER
Underground Mechanical 9/9/2021 Approved GORDON ZUBER
Excavation/Setback/Form/Re-Bar 9/21/2021 Approved GORDON ZUBER
Footing/Foundation/Slab 9/21/2021 Approved GORDON ZUBER
Floor/Roof Diaphrgm/Shear Wall 10/4/2021 Approved GORDON ZUBER
Floor/Roof Diaphrgm/Shear Wall 11/2/2021 Corrections Issued GORDON ZUBER
Floor/Roof Diaphrgm/Shear Wall 11/8/2021 Conditional Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 11/24/2021 Approved GORDON ZUBER
HVAC-Rough 11/24/2021 Approved GORDON ZUBER
ELECTRICAL-Rough 11/30/2021 Corrections Issued GORDON ZUBER
PLUMBING-Rough 11/30/2021 Approved GORDON ZUBER
ELECTRICAL-Rough 12/6/2021 Corrections Issued GORDON ZUBER
BUILDING-Rough-Frame 12/7/2021 Approved GORDON ZUBER
ELECTRICAL-Rough 12/7/2021 Approved GORDON ZUBER
Green Building Rough 12/7/2021 Approved GORDON ZUBER
Interior/Exterior Lathing 12/7/2021 Approved GORDON ZUBER
Shower Pan 12/7/2021 Approved GORDON ZUBER
Insulation 12/16/2021 Approved GORDON ZUBER
Gas Test 12/22/2021 Approved GORDON ZUBER
Interior/Exterior Lathing 12/22/2021 Approved GORDON ZUBER
Drywall Nailing 1/10/2022 Approved GORDON ZUBER
Gas Test 1/10/2022 Approved GORDON ZUBER
PLUMBING-Final 5/13/2022 Approved GORDON ZUBER
Final 5/26/2022 Not Ready for Inspection ZEYDI STEWART
Green Building Final 5/26/2022 Not Ready for Inspection ZEYDI STEWART
SGSOV-Seismic Gas S/O Valve 5/26/2022 SGSOV Not Ready ZEYDI STEWART
Service/Power Release 5/26/2022 Not Ready for Inspection ZEYDI STEWART
Smoke Detectors 5/26/2022 Not Ready for Inspection ZEYDI STEWART
Final 5/31/2022 OK to Issue CofO GORDON ZUBER
Green Building Final 5/31/2022 Approved GORDON ZUBER
SGSOV-Seismic Gas S/O Valve 5/31/2022 SGSOV Approved GORDON ZUBER
Service/Power Release 5/31/2022 Approved GORDON ZUBER
Smoke Detectors 5/31/2022 Approved GORDON ZUBER