6550-6552 N RANDI AVE 91303
Certificate Information: 6550-6552 N RANDI AVE 91303
- Application / Permit
- 20014-20000-04990
- Plan Check / Job No.
- B20VN14644
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) IRREGULAR SHAPED 33'-6" X 45' ADDITION WITH REAR PORCH TO (E) SINGLE FAMILY DWELLING AND CONVERT (E) 18'-2" X 20'-2" GARAGE AND 13'-1" X 17' PORTION OF (E) SINGLE FAMILY TO (N) JUNIOR ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) and 65852.22 ALL WORK PER ENGINEERING NFPA 13D REQUIRED THROUGHOUT SEE COMMENTS
- Permit Issued
- Issued on 9/15/2021
- Issuing Office
- Current Status
- CofO Issued on 1/5/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/10/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/10/2020 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 1/14/2021 | SEWADA ZADOORIAN MILAGARDI |
| Quality Review Completed | 1/15/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 1/19/2021 | APPLICANT |
| Applicant returned to address corrections | 7/12/2021 | SEWADA ZADOORIAN MILAGARDI |
| Applicant returned to address corrections | 8/30/2021 | SEWADA ZADOORIAN MILAGARDI |
| Plan Check Approved | 9/15/2021 | SEWADA ZADOORAN MILAGARDI |
| Issued | 9/15/2021 | APPLICANT |
| CofO in Progress | 12/27/2022 | TROY SANDERS |
| CofO Issued | 1/5/2023 | JOHN JANSON |
| Permit Finaled | 1/5/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 2/26/2021 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 3/2/2021 | ADRIAN CASTRO |
| Sewer availability | Cleared | 3/2/2021 | ADRIAN CASTRO |
| Miscellaneous | Cleared | 3/4/2021 | JASON CHAN |
| Hydrant and Access approval | Cleared | 5/18/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 7/2/2021 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 7/6/2021 | CARLOS AGUILERA |
Contact Information
| Architect | Miller,, Michael; Lic. No.: C26956 | 12756 MITCHELL AVE LOS ANGELES, CA 90066 |
| Contractor | C T C Renovation Inc; Lic. No.: 1007234-B | 21356 NORDHOFF STREET #107 CHATSWORTH, CA 91311 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/21/2021 | Approved | TROY SANDERS |
| Footing/Foundation/Slab | 9/21/2021 | Approved | TROY SANDERS |
| Deputy Drilled-In Anchors | 9/22/2021 | Partial Approval | TROY SANDERS |
| BUILDING-Rough-Frame | 9/28/2021 | Partial Approval | TROY SANDERS |
| Gas Test | 9/28/2021 | Partial Approval | TROY SANDERS |
| Insulation | 9/28/2021 | Partial Approval | TROY SANDERS |
| Rough-Elec/Plmb/HVAC | 9/28/2021 | Partial Approval | TROY SANDERS |
| BUILDING-Rough-Frame | 9/29/2021 | Partial Approval | TROY SANDERS |
| Green Building Rough | 9/29/2021 | Partial Approval | TROY SANDERS |
| Insulation | 9/29/2021 | Partial Approval | TROY SANDERS |
| Interior/Exterior Lathing | 9/29/2021 | Partial Approval | TROY SANDERS |
| Drywall Nailing | 10/1/2021 | Partial Approval | TROY SANDERS |
| Insulation | 10/1/2021 | Not Ready for Inspection | TROY SANDERS |
| Wood Frame | 10/1/2021 | Not Ready for Inspection | TROY SANDERS |
| BUILDING-Rough-Frame | 10/8/2021 | Partial Approval | TROY SANDERS |
| PLUMBING-Rough | 10/8/2021 | Approved | TROY SANDERS |
| Insulation | 10/12/2021 | Partial Approval | TROY SANDERS |
| PLUMBING-Rough | 10/12/2021 | Not Ready for Inspection | TROY SANDERS |
| BUILDING-Rough-Frame | 10/26/2021 | Partial Approval | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 10/26/2021 | Partial Approval | TROY SANDERS |
| Green Building Rough | 10/26/2021 | Not Ready for Inspection | TROY SANDERS |
| Special/Order Compliance | 10/26/2021 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 12/6/2021 | Partial Approval | TROY SANDERS |
| Drywall Nailing | 12/6/2021 | Not Ready for Inspection | TROY SANDERS |
| ELECTRICAL-Rough | 12/6/2021 | Approved | TROY SANDERS |
| Final | 12/6/2021 | Not Ready for Inspection | TROY SANDERS |
| Green Building Final | 12/6/2021 | Not Ready for Inspection | TROY SANDERS |
| Green Building Rough | 12/6/2021 | Not Ready for Inspection | TROY SANDERS |
| PLUMBING-Rough | 12/6/2021 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 12/6/2021 | SGSOV Not Ready | TROY SANDERS |
| Smoke Detectors | 12/6/2021 | Partial Approval | TROY SANDERS |
| HVAC-Rough | 12/13/2021 | Approved | TROY SANDERS |
| Insulation | 12/13/2021 | Not Ready for Inspection | TROY SANDERS |
| Drywall Nailing | 12/20/2021 | Approved | TROY SANDERS |
| Drywall Nailing | 12/20/2021 | Not Ready for Inspection | JESUS PINEDA |
| Green Building Rough | 12/20/2021 | Approved | TROY SANDERS |
| Insulation | 12/20/2021 | Approved | TROY SANDERS |
| Shower Pan | 12/20/2021 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 1/25/2022 | Approved | JESUS PINEDA |
| BUILDING-Rough-Frame | 8/12/2022 | Approved | TROY SANDERS |
| Drywall Nailing | 8/12/2022 | Approved | TROY SANDERS |
| ELECTRICAL-Final | 8/12/2022 | Approved | TROY SANDERS |
| Final | 8/12/2022 | Corrections Issued | TROY SANDERS |
| Green Building Final | 8/12/2022 | Approved | TROY SANDERS |
| HVAC-Final | 8/12/2022 | Approved | TROY SANDERS |
| PLUMBING-Final | 8/12/2022 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 8/12/2022 | SGSOV Approved | TROY SANDERS |
| Smoke Detectors | 8/12/2022 | Approved | TROY SANDERS |
| Verify Sprinkler Sign Off | 8/12/2022 | Approved | TROY SANDERS |
| Final | 12/27/2022 | OK to Issue CofO | TROY SANDERS |