11325 N BALBOA BLVD 91344
Certificate Information: 11325 N BALBOA BLVD 91344
- Application / Permit
- 20014-20000-04989
- Plan Check / Job No.
- B20VN14643
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 16'-9" X 11' IRREG SHAPED ADDITION TO AND CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 9/7/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/21/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/10/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/18/2020 | JEROME MAGAT PALMA |
| Corrections Issued | 11/19/2020 | JEROME MAGAT PALMA |
| Plan Check Approved | 6/10/2021 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 4/1/2022 | APPLICANT |
| Issued | 9/7/2022 | APPLICANT |
| CofO in Progress | 11/10/2025 | STEVEN BACK |
| Permit Finaled | 11/21/2025 | MICHAEL PELHAM |
| CofO Issued | 11/21/2025 | MICHAEL PELHAM |
| Permit Finaled | 11/21/2025 | MICHAEL PELHAM |
Permit Application Clearance Information
| Address approval | Cleared | 1/19/2021 | JOHN TRIANTAFYLLOS |
| Roof/Waste drainage to street | Cleared | 1/19/2021 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 1/20/2021 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 1/20/2021 | JOHN TRIANTAFYLLOS |
| Grading Pre-Inspection | Cleared | 3/30/2021 | BRIAN MILLER |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY PARD, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN BACK, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/21/2024 | Conditional Approval | STEVEN BACK |
| Pre-Inspection | 7/1/2024 | Partial Inspection | STEVEN BACK |
| Sewer | 10/3/2024 | Approved | STEVEN BACK |
| Underground Mechanical | 10/3/2024 | Approved | STEVEN BACK |
| Excavation/Setback/Form/Re-Bar | 10/11/2024 | Approved | STEVEN BACK |
| Pre-Inspection | 10/31/2024 | Partial Inspection | STEVEN BACK |
| ELECTRICAL-Rough | 3/5/2025 | No Access for Inspection | STEVEN BACK |
| HVAC-Rough | 3/5/2025 | Not Ready for Inspection | STEVEN BACK |
| PLUMBING-Rough | 3/5/2025 | Not Ready for Inspection | STEVEN BACK |
| ELECTRICAL-Rough | 3/6/2025 | Not Ready for Inspection | STEVEN BACK |
| PLUMBING-Rough | 3/6/2025 | Partial Approval | STEVEN BACK |
| ELECTRICAL-Rough | 3/21/2025 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 3/21/2025 | Approved | STEVEN BACK |
| PLUMBING-Rough | 3/21/2025 | Approved | STEVEN BACK |
| Sewer | 3/21/2025 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 5/5/2025 | Approved | STEVEN BACK |
| Green Building Rough | 5/5/2025 | Approved | STEVEN BACK |
| HVAC-Rough | 5/5/2025 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 5/5/2025 | Partial Approval | STEVEN BACK |
| MERV13>=Rough | 5/5/2025 | Approved | STEVEN BACK |
| Insulation | 5/15/2025 | Corrections Issued | DAVID SCANTLIN |
| Insulation | 5/29/2025 | Approved | SCOTT SOBEL |
| Drywall Nailing | 6/30/2025 | Approved | STEVEN BACK |
| Drywall Nailing | 7/9/2025 | Approved | STEVEN BACK |
| Shower Pan | 7/9/2025 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 7/18/2025 | Approved | STEVEN BACK |
| Final | 11/3/2025 | Corrections Issued | STEVEN BACK |
| Footing/Foundation/Slab | 11/3/2025 | Approved | STEVEN BACK |
| Green Building Final | 11/3/2025 | Approved | STEVEN BACK |
| MERV13>=Final | 11/3/2025 | Approved | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 11/3/2025 | SGSOV Not Ready | STEVEN BACK |
| Smoke Detectors | 11/3/2025 | Approved | STEVEN BACK |
| Final | 11/5/2025 | Not Ready for Inspection | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 11/5/2025 | SGSOV Not Ready | STEVEN BACK |
| Final | 11/10/2025 | OK to Issue CofO | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 11/10/2025 | SGSOV Approved | STEVEN BACK |