5457 N VAN NOORD AVE 91401

Certificate Information: 5457 N VAN NOORD AVE 91401

Application / Permit
20014-20000-04986
Plan Check / Job No.
B20VN14629
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
36' X 35' 9" IRR.-SHAPE ADDITION FOR LIVING ROOM EXTENSION & COVERED PORCH, 19' 5" X 2' ADDITION TO SIDE OF ATTACHED GARAGE, 35' 9" X 5' ADDITION TO SIDE OF (E) SFD, ADD LAUNDRY, REMOVE LOAD-BEARING WALLS BETWEEN KITCHEN, DINING & LIVING ROOM FOR OPEN FLOOR PLAN LAYOUT, REMODEL ALL (E) BEDROOMS/BATHROOMS AND ADD (1) BATHROOM. ALL WORK DONE PER STRUCTURAL ENGINEERING.
Permit Issued
Issued on 4/5/2021
Issuing Office
Current Status
CofO Issued on 10/15/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/11/2020 APPLICANT
Assigned to Plan Check Engineer 11/20/2020 GURUNATH NESARAJAH
Corrections Issued 11/22/2020 GURUNATH NESARAJAH
Plan Check Approved 3/11/2021 GURUNATH NESARAJAH
Building Plans Picked Up 3/12/2021 APPLICANT
Issued 4/5/2021 APPLICANT
CofO in Progress 9/21/2022 RAFAEL CORTES
CofO Issued 10/15/2022 MICHAEL SMITH
Permit Finaled 10/15/2022 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/7/2020 JOHN TRIANTAFYLLOS
Low Impact Development Cleared 2/26/2021 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 3/1/2021 JOHN TRIANTAFYLLOS

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/26/2021 No Result Entered GREG ALLTON
Footing/Foundation/Slab 7/13/2021 Corrections Issued CHRISTOPHE COCHRAN
Footing/Foundation/Slab 7/23/2021 Approved CHRISTOPHE COCHRAN
Deputy Drilled-In Anchors 8/4/2021 Approved JUSTIN HAWLEY
Footing/Foundation/Slab 8/10/2021 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 8/10/2021 Partial Approval CHRISTOPHE COCHRAN
Insulation 10/27/2021 Partial Approval CHRISTOPHE COCHRAN
Deputy Drilled-In Anchors 11/29/2021 Partial Approval MATT KELLERMAN
HVAC-Rough 2/25/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
PLUMBING-Rough 2/25/2022 Approved CHRISTOPHE COCHRAN
Sewer 2/25/2022 Approved CHRISTOPHE COCHRAN
Underground Mechanical 2/25/2022 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 3/1/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
Green Building Rough 3/1/2022 Approved CHRISTOPHE COCHRAN
HVAC-Rough 3/1/2022 Approved CHRISTOPHE COCHRAN
Gas Test 3/4/2022 Partial Approval CHRISTOPHE COCHRAN
Interior/Exterior Lathing 3/4/2022 Partial Approval CHRISTOPHE COCHRAN
PLUMBING-Rough 3/4/2022 Approved CHRISTOPHE COCHRAN
Sewer 3/4/2022 Approved CHRISTOPHE COCHRAN
Insulation 3/8/2022 Approved CHRISTOPHE COCHRAN
Drywall Nailing 3/16/2022 Approved CLAYTON GRAHAM
Interior/Exterior Lathing 3/31/2022 Partial Approval ASHLEY THOMPSON
Shower Pan 3/31/2022 Approved ASHLEY THOMPSON
Shower Pan 5/24/2022 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 9/20/2022 Approved RAFAEL CORTES
Final 9/20/2022 OK to Issue CofO RAFAEL CORTES
Green Building Final 9/20/2022 Approved RAFAEL CORTES
SGSOV-Seismic Gas S/O Valve 9/20/2022 SGSOV Approved RAFAEL CORTES
Smoke Detectors 9/20/2022 Approved RAFAEL CORTES