11908 W BLYTHE ST 91605
Certificate Information: 11908 W BLYTHE ST 91605
- Application / Permit
- 20014-20000-04982
- Plan Check / Job No.
- B20VN14618
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED 31'X25'10-1/2" ACCESSORY DWELLING UNIT (ADU) ADDITION PER LAMC 12.22A33 (c) & (d) TO EX DETACHED GARAGE W/ PREFAB ROOF TRUSS OVER ADU.
- Permit Issued
- Issued on 3/2/2022
- Issuing Office
- Current Status
- CofO Issued on 5/15/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/10/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/20/2020 | HAYATO TSUCHIYA |
| Corrections Issued | 11/22/2020 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 8/30/2021 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 10/28/2021 | HAYATO TSUCHIYA |
| Plan Check Approved | 1/28/2022 | HAYATO TSUCHIYA |
| Building Plans Picked Up | 2/1/2022 | APPLICANT |
| Issued | 3/2/2022 | APPLICANT |
| CofO in Progress | 5/8/2025 | NICHOLAS TROWBRIDGE |
| Permit Finaled | 5/15/2025 | RUBEN SALAS |
| CofO Issued | 5/15/2025 | RUBEN SALAS |
| Permit Finaled | 5/15/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 3/16/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 3/16/2021 | GABRIEL ROBLES |
| Clean Up Green Up | Cleared | 3/24/2021 | MIGUEL GAMBOA |
| Sewer availability | Cleared | 5/19/2021 | CARLOS AGUILERA |
| Permit | Cleared | 5/24/2021 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 5/25/2021 | RIDWAN HARDY |
| Low Impact Development | Cleared | 8/13/2021 | YVAINNE GALSIM |
| Roof/Waste drainage to street | Cleared | 8/14/2021 | CARLOS AGUILERA |
Contact Information
| Architect | Williams,, Max Allan; Lic. No.: C21044 | PO BOX 2154 FRAZIER PARK, CA 93225 |
| Contractor | Owner-Builder | , |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/9/2022 | Approved | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 3/29/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Sewer | 3/29/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Footing/Foundation/Slab | 4/8/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Pre-Inspection | 4/8/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Underground Mechanical | 4/8/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 5/16/2022 | Approved | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 6/22/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 6/22/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Gas Test | 6/22/2022 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 6/22/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 6/22/2022 | Approved | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 7/1/2022 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 7/1/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 7/1/2022 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 7/1/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Insulation | 7/12/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Shower Pan | 7/12/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 7/20/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Shower Pan | 7/20/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 7/25/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Special/Order Compliance | 7/25/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 11/9/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| PLUMBING-Final | 11/9/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Smoke Detectors | 11/9/2022 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 12/8/2022 | Approved | MATTHEW NELSON |
| Final | 12/8/2022 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 12/8/2022 | Approved | MATTHEW NELSON |
| Grounding or Bonding | 12/8/2022 | Approved | MATTHEW NELSON |
| HVAC-Final | 12/8/2022 | Approved | MATTHEW NELSON |
| PLUMBING-Final | 12/8/2022 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 12/8/2022 | SGSOV Approved | MATTHEW NELSON |
| Service/Power Release | 12/8/2022 | Not Ready for Inspection | MATTHEW NELSON |
| Final | 5/7/2025 | OK to Issue CofO | NICHOLAS TROWBRIDGE |