9653-9655 N AQUEDUCT AVE 91343

Certificate Information: 9653-9655 N AQUEDUCT AVE 91343

Application / Permit
20014-20000-04981
Plan Check / Job No.
B20VN14612
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
15' x 32'2" ADDITION TO AND CONVERT 11'5" x 19'7" PORTION OF THE (E) GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e). ALL WORK PER ENG.
Permit Issued
Issued on 3/2/2022
Issuing Office
Current Status
CofO Issued on 9/23/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/18/2020 APPLICANT
Assigned to Plan Check Engineer 11/30/2020 JEFFREY TANGONAN
Corrections Issued 11/30/2020 JEFFREY TANGONAN
Applicant returned to address corrections 12/9/2021 JEFFREY TANGONAN
Plan Check Approved 1/24/2022 JEFFREY TANGONAN
Building Plans Picked Up 2/9/2022 APPLICANT
Issued 3/2/2022 APPLICANT
CofO in Progress 9/16/2025 GAREN HAYRAPETYAN
CofO Issued 9/23/2025 RUBEN SALAS
Permit Finaled 9/23/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 12/31/2020 WALLIE JONG
Roof/Waste drainage to street Cleared 12/31/2020 WALLIE JONG
ZA Case Cleared 2/17/2021 LAUREN PADICK
ZA Case Cleared 2/17/2021 LAUREN PADICK
Eng Process Fee Ord 176,300 Cleared 5/17/2021 WALLIE JONG
Sewer availability Cleared 5/19/2021 WALLIE JONG
Low Impact Development Cleared 1/5/2022 JORGE MEJIA LEMUS

Contact Information

Contractor Owner-Builder       ,
Engineer Chavez,, Eduardo; Lic. No.: C76372 437 ARCADIA WAY      WALNUT, CA 91789

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/3/2023 Approved RAUL OLAGI
PLUMBING-Rough 7/27/2023 Not Ready for Inspection RAUL OLAGI
PLUMBING-Rough 8/3/2023 Corrections Issued JUAN VALENZUELA
Sewer 8/3/2023 Approved JUAN VALENZUELA
PLUMBING-Rough 8/16/2023 Partial Approval RAUL OLAGI
Footing/Foundation/Slab 9/27/2023 Approved RAUL OLAGI
BUILDING-Rough-Frame 11/2/2023 Corrections Issued RAUL OLAGI
Deputy Wood Construction 11/2/2023 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 11/6/2023 Partial Approval RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 11/10/2023 Partial Approval JUAN VALENZUELA
Green Building Rough 11/10/2023 Not Ready for Inspection JUAN VALENZUELA
MERV13>=Rough 11/10/2023 Not Ready for Inspection JUAN VALENZUELA
BUILDING-Rough-Frame 1/25/2024 Not Ready for Inspection RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 1/25/2024 Approved RAUL OLAGI
Rough-Elec/Plmb/HVAC 1/25/2024 Not Ready for Inspection RAUL OLAGI
BUILDING-Rough-Frame 2/21/2024 Corrections Issued RAUL OLAGI
Green Building Rough 2/21/2024 Approved RAUL OLAGI
Interior/Exterior Lathing 2/21/2024 Partial Approval RAUL OLAGI
MERV13>=Rough 2/21/2024 Approved RAUL OLAGI
Rough-Elec/Plmb/HVAC 2/21/2024 Approved RAUL OLAGI
BUILDING-Rough-Frame 2/28/2024 Approved SALVADOR MARTINEZ
Insulation 2/28/2024 Corrections Issued SALVADOR MARTINEZ
Insulation 3/11/2024 Approved SALVADOR MARTINEZ
Drywall Nailing 4/10/2024 Approved RAUL OLAGI
Shower Pan 4/10/2024 Approved RAUL OLAGI
Interior/Exterior Lathing 6/3/2024 Approved SALVADOR MARTINEZ
Final 7/26/2024 Corrections Issued SALVADOR MARTINEZ
Green Building Final 7/26/2024 Not Ready for Inspection SALVADOR MARTINEZ
MERV13>=Final 7/26/2024 Corrections Issued SALVADOR MARTINEZ
SGSOV-Seismic Gas S/O Valve 7/26/2024 SGSOV No Gas SALVADOR MARTINEZ
Smoke Detectors 7/26/2024 Corrections Issued SALVADOR MARTINEZ
Final 9/16/2025 OK to Issue CofO GAREN HAYRAPETYAN
Green Building Final 9/16/2025 Approved GAREN HAYRAPETYAN
MERV13>=Final 9/16/2025 Approved GAREN HAYRAPETYAN
Smoke Detectors 9/16/2025 Approved GAREN HAYRAPETYAN