18137 W SUNBURST ST 91325

Certificate Information: 18137 W SUNBURST ST 91325

Application / Permit
20014-20000-04978
Plan Check / Job No.
B20VN14602
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERAT (E) GARAGE TO ADU W/2-STORY ADDITION. PER LAMC 12.22A.33(c)& (d)
Permit Issued
Issued on 4/1/2021
Issuing Office
Current Status
CofO Issued on 1/12/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/10/2020 APPLICANT
Assigned to Plan Check Engineer 12/10/2020 CHON CHIO KUO
Corrections Issued 12/14/2020 CHON CHIO KUO
Quality Review Completed 12/18/2020 STEVEN KIM
Building Plans Picked Up 12/21/2020 APPLICANT
Plan Check Approved 2/8/2021 CHON CHIO KUO
Issued 4/1/2021 APPLICANT
CofO in Progress 1/12/2023 JOHN KIDWELL
Permit Finaled 1/12/2023 JOHN JANSON
CofO Issued 1/12/2023 JOHN JANSON
Permit Finaled 1/12/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 1/5/2021 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 1/5/2021 JOHN TRIANTAFYLLOS
Roof/Waste drainage to street Cleared 1/5/2021 JOHN TRIANTAFYLLOS
Sewer availability Cleared 1/5/2021 JOHN TRIANTAFYLLOS
Hydrant and Access approval Cleared 1/21/2021 MATTHEW CRAIG

Contact Information

Contractor Owner-Builder       ,
Engineer Koma,, Shahram Javadi; Lic. No.: C69497 23241 VENTURA BLVD 300      WOODLAND HILLS, CA 91364

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/3/2021 Partial Approval JEFFREY PARD
Sewer 11/3/2021 Approved JEFFREY PARD
Deputy Drilled-In Anchors 11/5/2021 Approved JEFFREY PARD
Footing/Foundation/Slab 11/10/2021 Approved JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 11/18/2021 Partial Approval JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 12/6/2021 Partial Approval JEFFREY PARD
ELECTRICAL-Rough 1/18/2022 Corrections Issued DAVID SCANTLIN
HVAC-Rough 1/18/2022 Corrections Issued DAVID SCANTLIN
PLUMBING-Rough 1/18/2022 Approved DAVID SCANTLIN
Rough-Elec/Plmb/HVAC 1/18/2022 Partial Approval DAVID SCANTLIN
ELECTRICAL-Rough 1/27/2022 Approved JEFFREY PARD
HVAC-Rough 1/27/2022 Approved JEFFREY PARD
Interior/Exterior Lathing 1/27/2022 Approved JEFFREY PARD
Insulation 2/3/2022 Approved JEFFREY PARD
Drywall Nailing 2/17/2022 Approved MORRIS JACKSON
ELECTRICAL-Final 9/16/2022 Corrections Issued DAVID SANDOVAL
HVAC-Final 9/16/2022 Not Ready for Inspection DAVID SANDOVAL
PLUMBING-Final 9/16/2022 Approved DAVID SANDOVAL
BUILDING-Rough-Frame 12/29/2022 Approved DAVID SCANTLIN
ELECTRICAL-Final 12/29/2022 Approved DAVID SCANTLIN
Final 12/29/2022 Corrections Issued DAVID SCANTLIN
Green Building Final 12/29/2022 Approved DAVID SCANTLIN
Green Building Rough 12/29/2022 Approved DAVID SCANTLIN
HVAC-Final 12/29/2022 Approved DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 12/29/2022 SGSOV Approved DAVID SCANTLIN
Smoke Detectors 12/29/2022 Approved DAVID SCANTLIN
ELECTRICAL-Final 1/4/2023 Not Ready for Inspection DAVID SCANTLIN
Final 1/4/2023 Not Ready for Inspection DAVID SCANTLIN
Final 1/11/2023 OK to Issue CofO JOHN KIDWELL