18137 W SUNBURST ST 91325
Certificate Information: 18137 W SUNBURST ST 91325
- Application / Permit
- 20014-20000-04978
- Plan Check / Job No.
- B20VN14602
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERAT (E) GARAGE TO ADU W/2-STORY ADDITION. PER LAMC 12.22A.33(c)& (d)
- Permit Issued
- Issued on 4/1/2021
- Issuing Office
- Current Status
- CofO Issued on 1/12/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/10/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/10/2020 | CHON CHIO KUO |
| Corrections Issued | 12/14/2020 | CHON CHIO KUO |
| Quality Review Completed | 12/18/2020 | STEVEN KIM |
| Building Plans Picked Up | 12/21/2020 | APPLICANT |
| Plan Check Approved | 2/8/2021 | CHON CHIO KUO |
| Issued | 4/1/2021 | APPLICANT |
| CofO in Progress | 1/12/2023 | JOHN KIDWELL |
| Permit Finaled | 1/12/2023 | JOHN JANSON |
| CofO Issued | 1/12/2023 | JOHN JANSON |
| Permit Finaled | 1/12/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 1/5/2021 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 1/5/2021 | JOHN TRIANTAFYLLOS |
| Roof/Waste drainage to street | Cleared | 1/5/2021 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 1/5/2021 | JOHN TRIANTAFYLLOS |
| Hydrant and Access approval | Cleared | 1/21/2021 | MATTHEW CRAIG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Koma,, Shahram Javadi; Lic. No.: C69497 | 23241 VENTURA BLVD 300 WOODLAND HILLS, CA 91364 |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/3/2021 | Partial Approval | JEFFREY PARD |
| Sewer | 11/3/2021 | Approved | JEFFREY PARD |
| Deputy Drilled-In Anchors | 11/5/2021 | Approved | JEFFREY PARD |
| Footing/Foundation/Slab | 11/10/2021 | Approved | JEFFREY PARD |
| Floor/Roof Diaphrgm/Shear Wall | 11/18/2021 | Partial Approval | JEFFREY PARD |
| Floor/Roof Diaphrgm/Shear Wall | 12/6/2021 | Partial Approval | JEFFREY PARD |
| ELECTRICAL-Rough | 1/18/2022 | Corrections Issued | DAVID SCANTLIN |
| HVAC-Rough | 1/18/2022 | Corrections Issued | DAVID SCANTLIN |
| PLUMBING-Rough | 1/18/2022 | Approved | DAVID SCANTLIN |
| Rough-Elec/Plmb/HVAC | 1/18/2022 | Partial Approval | DAVID SCANTLIN |
| ELECTRICAL-Rough | 1/27/2022 | Approved | JEFFREY PARD |
| HVAC-Rough | 1/27/2022 | Approved | JEFFREY PARD |
| Interior/Exterior Lathing | 1/27/2022 | Approved | JEFFREY PARD |
| Insulation | 2/3/2022 | Approved | JEFFREY PARD |
| Drywall Nailing | 2/17/2022 | Approved | MORRIS JACKSON |
| ELECTRICAL-Final | 9/16/2022 | Corrections Issued | DAVID SANDOVAL |
| HVAC-Final | 9/16/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| PLUMBING-Final | 9/16/2022 | Approved | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 12/29/2022 | Approved | DAVID SCANTLIN |
| ELECTRICAL-Final | 12/29/2022 | Approved | DAVID SCANTLIN |
| Final | 12/29/2022 | Corrections Issued | DAVID SCANTLIN |
| Green Building Final | 12/29/2022 | Approved | DAVID SCANTLIN |
| Green Building Rough | 12/29/2022 | Approved | DAVID SCANTLIN |
| HVAC-Final | 12/29/2022 | Approved | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 12/29/2022 | SGSOV Approved | DAVID SCANTLIN |
| Smoke Detectors | 12/29/2022 | Approved | DAVID SCANTLIN |
| ELECTRICAL-Final | 1/4/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| Final | 1/4/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| Final | 1/11/2023 | OK to Issue CofO | JOHN KIDWELL |