Certificate Information: 5327 N NATICK AVE 91411
- Application / Permit
- 20014-20000-04975
- Plan Check / Job No.
- B20VN14596
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 40'-0" X 15'-0" IRRELGULAR SHAPED ADDITION & MAJOR REMODEL TO (E) SFD, NEW WINDOWS/DOORS, NEW ROOF. NFPA 13 D FIRE SPRINKLER REQUIRED THROUGHOUT. "COMPLY WITH DEPARTMENT ORDER effective date 05/09/2022. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 8/10/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/12/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/10/2020 | MARVEL DELACRUZ |
| Corrections Issued | 12/16/2020 | MARVEL DELACRUZ |
| Quality Review Completed | 12/24/2020 | STEVEN KIM |
| Building Plans Picked Up | 12/30/2020 | APPLICANT |
| Applicant returned to address corrections | 6/14/2022 | RAPHAEL ROSAS |
| Plan Check Approved | 8/4/2022 | RAPHAEL ROSAS |
| Issued | 8/10/2022 | APPLICANT |
| CofO in Progress | 9/25/2024 | PTOLEMY HILL |
| Permit Finaled | 10/17/2024 | DANIEL SANCHEZ |
| CofO Issued | 10/17/2024 | DANIEL SANCHEZ |
| Permit Finaled | 10/17/2024 | DANIEL SANCHEZ |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/21/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 5/21/2021 | GABRIEL ROBLES |
| Low Impact Development | Cleared | 1/24/2022 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 1/25/2022 | CARLOS AGUILERA |
| Green Code | Cleared | 6/14/2022 | MARVEL DELACRUZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Carrillo,, Jesus Eduardo; Lic. No.: C77737 | 8207 BROOKGREEN RD DOWNEY, CA 90240 |
Inspector Information
| JOEL ORDAZ, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| PTOLEMY HILL, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| JONATHAN FRANCHINI, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVAKIAN, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| EDMOND DECKERT, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| TIMOTHY KEY, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERT CHAVEZ, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/12/2023 | Corrections Issued | PATRICK LIEBREGT |
| Footing/Foundation/Slab | 7/14/2023 | Corrections Issued | JOEL ORDAZ |
| Footing/Foundation/Slab | 7/21/2023 | Approved | JOEL ORDAZ |
| PLUMBING-Rough | 8/4/2023 | Not Ready for Inspection | JOEL ORDAZ |
| PLUMBING-Rough | 8/8/2023 | Approved | PATRICK LIEBREGT |
| Pre-Inspection | 8/8/2023 | Corrections Issued | PATRICK LIEBREGT |
| Insulation | 8/11/2023 | Partial Approval | PATRICK LIEBREGT |
| Floor/Roof Diaphrgm/Shear Wall | 8/14/2023 | Not Ready for Inspection | PATRICK LIEBREGT |
| Floor/Roof Diaphrgm/Shear Wall | 8/16/2023 | Partial Approval | PATRICK LIEBREGT |
| BUILDING-Rough-Frame | 10/6/2023 | Corrections Issued | PATRICK LIEBREGT |
| Green Building Rough | 10/6/2023 | Approved | PATRICK LIEBREGT |
| ELECTRICAL-Rough | 10/11/2023 | Not Ready for Inspection | PATRICK LIEBREGT |
| ELECTRICAL-Rough | 11/1/2023 | Approved | PATRICK LIEBREGT |
| HVAC-Rough | 11/1/2023 | Not Ready for Inspection | PATRICK LIEBREGT |
| PLUMBING-Rough | 11/1/2023 | Partial Approval | PATRICK LIEBREGT |
| Wood Frame | 11/1/2023 | Not Ready for Inspection | PATRICK LIEBREGT |
| BUILDING-Rough-Frame | 12/21/2023 | Not Ready for Inspection | ARAM AVAKIAN |
| ELECTRICAL-Rough | 12/21/2023 | Approved | ARAM AVAKIAN |
| HVAC-Rough | 12/21/2023 | Approved | ARAM AVAKIAN |
| PLUMBING-Rough | 12/21/2023 | Not Ready for Inspection | ARAM AVAKIAN |
| Insulation | 1/3/2024 | Approved | ARAM AVAKIAN |
| Drywall Nailing | 1/12/2024 | Approved | JOEL ORDAZ |
| Shower Pan | 2/12/2024 | Approved | ARAM AVAKIAN |
| BUILDING-Rough-Frame | 5/23/2024 | Approved | ARAM AVAKIAN |
| PLUMBING-Rough | 5/23/2024 | Approved | ARAM AVAKIAN |
| Wood Frame | 5/23/2024 | Approved | ARAM AVAKIAN |
| Special/Order Compliance | 6/13/2024 | Corrections Issued | JOEL ORDAZ |
| ELECTRICAL-Final | 9/20/2024 | Approved | PTOLEMY HILL |
| Final | 9/20/2024 | Not Ready for Inspection | PTOLEMY HILL |
| Green Building Final | 9/20/2024 | Approved | PTOLEMY HILL |
| SGSOV-Seismic Gas S/O Valve | 9/20/2024 | SGSOV Approved | PTOLEMY HILL |
| Service/Power Release | 9/20/2024 | Approved | PTOLEMY HILL |
| Smoke Detectors | 9/20/2024 | Approved | PTOLEMY HILL |
| Final | 9/25/2024 | OK to Issue CofO | PTOLEMY HILL |