3783 S MAY ST 90066

Certificate Information: 3783 S MAY ST 90066

Application / Permit
20014-20000-04967
Plan Check / Job No.
B20VN14576
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
14'6" x 12'5" ADDITION FOR NEW BEDROOM, CONVERT EX. BEDROOM TO BATHROOM. REMODEL (E) KITCHEN AND BATHROOMS. CHANGE OUT WINDOWS. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 3/4/2021
Issuing Office
Current Status
CofO Issued on 11/22/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/10/2020 APPLICANT
Assigned to Plan Check Engineer 11/20/2020 JEFFREY TANGONAN
Corrections Issued 11/20/2020 JEFFREY TANGONAN
Applicant returned to address corrections 1/21/2021 JEFFREY TANGONAN
Applicant returned to address corrections 1/28/2021 JEFFREY TANGONAN
Plan Check Approved 2/5/2021 JEFFREY TANGONAN
Issued 3/4/2021 APPLICANT
CofO in Progress 11/9/2021 ENRIQUE MIRELES
Permit Finaled 11/22/2021 DANIEL ORRANTE
CofO Issued 11/22/2021 DANIEL ORRANTE
Permit Finaled 11/22/2021 DANIEL ORRANTE

Permit Application Clearance Information

Specific Plan Cleared 12/18/2020 PEDRO AYALA
Grading Pre-Inspection Cleared 1/21/2021 JEFFREY TANGONAN
Eng Process Fee Ord 176,300 Cleared 1/27/2021 ANTHONY MAINEZ
Roof/Waste drainage to street Cleared 2/4/2021 ANTHONY MAINEZ

Contact Information

Architect Mehta,, Nita J; Lic. No.: C27172 21848 PROVIDENCIA STREET      WOODLAND HILLS, CA 91364
Contractor Owner-Builder       ,
Engineer Nishimura,, Kentaro James; Lic. No.: C73821 5138 RAPHAEL ST      LOS ANGELES, CA 90042

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/13/2021 Approved ENRIQUE MIRELES
Deputy Drilled-In Anchors 4/14/2021 Approved ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 4/15/2021 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 4/15/2021 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 4/20/2021 Partial Approval ENRIQUE MIRELES
Wood Frame 4/20/2021 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 4/21/2021 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 5/7/2021 Approved ENRIQUE MIRELES
PLUMBING-Rough 5/7/2021 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 5/14/2021 Approved ENRIQUE MIRELES
HVAC-Rough 5/14/2021 Not Ready for Inspection ENRIQUE MIRELES
Shower Pan 5/14/2021 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 5/17/2021 Not Ready for Inspection PIERRE VEGA
Final 5/17/2021 Not Ready for Inspection PIERRE VEGA
Footing/Foundation/Slab 5/17/2021 Not Ready for Inspection PIERRE VEGA
Green Building Final 5/17/2021 Not Ready for Inspection PIERRE VEGA
Green Building Rough 5/17/2021 Not Ready for Inspection PIERRE VEGA
Interior/Exterior Lathing 5/17/2021 Partial Approval PIERRE VEGA
SGSOV-Seismic Gas S/O Valve 5/17/2021 SGSOV Not Ready PIERRE VEGA
Smoke Detectors 5/17/2021 Not Ready for Inspection PIERRE VEGA
BUILDING-Rough-Frame 5/21/2021 Approved ENRIQUE MIRELES
Green Building Rough 5/21/2021 Approved ENRIQUE MIRELES
Insulation 6/3/2021 Approved ENRIQUE MIRELES
Drywall Nailing 6/10/2021 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 7/20/2021 Approved ENRIQUE MIRELES
Final 10/15/2021 Corrections Issued ENRIQUE MIRELES
Footing/Foundation/Slab 10/15/2021 Approved ENRIQUE MIRELES
Green Building Final 10/15/2021 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 10/15/2021 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 10/15/2021 Approved ENRIQUE MIRELES
Final 11/9/2021 OK to Issue CofO ENRIQUE MIRELES