5050 N BILOXI AVE 91601
Certificate Information: 5050 N BILOXI AVE 91601
- Application / Permit
- 20014-20000-04937
- Plan Check / Job No.
- B20VN14504
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 16'-10" X 42'-9" IRREGULAR SHAPED ADDITION TO (E) SFD. ALL WORK PER ENGINEERING. NFPA 13D FIRE SPRINKLERS THROUGH OUT.
- Permit Issued
- Issued on 6/29/2022
- Issuing Office
- Current Status
- CofO Issued on 2/7/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/16/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/30/2020 | RAPHAEL ROSAS |
| Corrections Issued | 1/2/2021 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 6/7/2021 | RAPHAEL ROSAS |
| Plan Check Approved | 6/23/2021 | RAPHAEL ROSAS |
| Building Plans Picked Up | 6/24/2021 | APPLICANT |
| Plan Check Approved | 6/27/2022 | RAPHAEL ROSAS |
| Issued | 6/29/2022 | APPLICANT |
| CofO in Progress | 1/24/2024 | JENNIFER RABUCHIN |
| Permit Finaled | 2/7/2024 | RUBEN SALAS |
| CofO Issued | 2/7/2024 | RUBEN SALAS |
| Permit Finaled | 2/7/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/6/2021 | ADRIAN CASTRO |
| Sewer availability | Cleared | 1/6/2021 | ADRIAN CASTRO |
| Low Impact Development | Cleared | 4/28/2021 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 6/7/2021 | ABDULLAH SADOZAI |
Contact Information
| Contractor | Makeover Builders Inc; Lic. No.: 986740-B | 21781 VENTURA BLVD UNIT 634 WOODLAND HILLS, CA 91364 |
| Engineer | Basso,, Alexandre; Lic. No.: C77670 | 7231 SUMMITROSE ST TUJUNGA, CA 91042 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/13/2022 | Partial Approval | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 7/28/2022 | Corrections Issued | GREGG CUMMINGS |
| Footing/Foundation/Slab | 7/28/2022 | Corrections Issued | GREGG CUMMINGS |
| PLUMBING-Rough | 7/28/2022 | Partial Approval | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 8/3/2022 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 8/3/2022 | Partial Approval | JENNIFER RABUCHIN |
| Insulation | 8/3/2022 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 9/8/2022 | Partial Approval | JOHN HAYES |
| ELECTRICAL-Rough | 10/28/2022 | Not Ready for Inspection | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 10/28/2022 | Partial Approval | JOHN HAYES |
| Gas Test | 10/28/2022 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 10/28/2022 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 11/4/2022 | Approved | JOHN HAYES |
| Gas Test | 11/4/2022 | Approved | JOHN HAYES |
| Green Building Rough | 11/4/2022 | Approved | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 11/4/2022 | Approved | JOHN HAYES |
| Insulation | 11/14/2022 | Approved | JOHN HAYES |
| Drywall Nailing | 11/17/2022 | Approved | JOHN HAYES |
| Shower Pan | 11/22/2022 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 12/1/2022 | Approved | JORDAN KUTZLY |
| Final | 9/18/2023 | Corrections Issued | JOHN HAYES |
| Footing/Foundation/Slab | 9/18/2023 | Approved | JOHN HAYES |
| Green Building Final | 9/18/2023 | Approved | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 9/18/2023 | SGSOV Approved | JOHN HAYES |
| Smoke Detectors | 9/18/2023 | Approved | JOHN HAYES |
| Final | 11/7/2023 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 1/23/2024 | Approved | JENNIFER RABUCHIN |
| Final | 1/23/2024 | OK to Issue CofO | JENNIFER RABUCHIN |
| HVAC-Final | 1/23/2024 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 1/23/2024 | Approved | JENNIFER RABUCHIN |