11542 W HESBY ST 91601
Certificate Information: 11542 W HESBY ST 91601
- Application / Permit
- 20014-20000-04923
- Plan Check / Job No.
- B20VN14469
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMOVE ALL EXTERIOR AND INTERIOR WALLS OF AN EXISTING ONE STORY DWELLING EXCEPT FOR 36'2", 5'6", 4'3" LF AT NORTH WEST SIDE AND 1'3" AND 9" AT EAST SIDE AND BUILD AN IREEGULAR SHAPED 60'6" X 42' ONE STORY SINGLE FAMILY DWELLING , NFPA-13D FIRE SPRINKLERS REQUIRED , ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 9/8/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/8/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/7/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/3/2020 | RARES BODEA |
| Corrections Issued | 12/5/2020 | RARES BODEA |
| Quality Review Completed | 12/16/2020 | STEVEN KIM |
| Building Plans Picked Up | 12/16/2020 | APPLICANT |
| Applicant returned to address corrections | 2/14/2022 | RARES BODEA |
| Applicant returned to address corrections | 7/27/2022 | RARES BODEA |
| Plan Check Approved | 8/5/2022 | RARES BODEA |
| Issued | 9/8/2022 | APPLICANT |
| CofO in Progress | 7/10/2024 | VINCENT HANLEY |
| CofO in Progress | 7/22/2024 | CHRISTOPHER ROJAS |
| CofO in Progress | 7/22/2024 | CHRISTOPHER ROJAS |
| Permit Finaled | 8/8/2024 | RUBEN SALAS |
| CofO Issued | 8/8/2024 | RUBEN SALAS |
| Permit Finaled | 8/8/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 2/26/2021 | JOHN CONNEALLY |
| Sewer availability | Cleared | 5/25/2021 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 6/2/2021 | ADRIAN CASTRO |
| Low Impact Development | Cleared | 9/27/2021 | NICK RAYGOZA |
| Roof/Waste drainage to street | Cleared | 12/29/2021 | JOSE DUARTE-DIAZ |
| Specific Plan | Cleared | 6/13/2022 | ERIN NASH |
| ZI | Cleared | 6/13/2022 | ERIN NASH |
| ZI | Cleared | 6/13/2022 | ERIN NASH |
Contact Information
| Contractor | Savs Enterprises; Lic. No.: 814956-B | 4500 SUNNYCREST DRIVE LOS ANGELES, CA 90065 |
| Engineer | Avila,, Albert Guerrero; Lic. No.: C41726 | 10034 GLADE AVNENUE CHATSWORTH, CA 91311 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/2/2022 | Partial Approval | JACK KARGODORIAN |
| Excavation/Setback/Form/Re-Bar | 11/18/2022 | Corrections Issued | JACK KARGODORIAN |
| Footing/Foundation/Slab | 11/18/2022 | Partial Approval | JACK KARGODORIAN |
| Footing/Foundation/Slab | 12/15/2022 | Not Ready for Inspection | JOHN COLEMAN |
| Footing/Foundation/Slab | 12/20/2022 | Approved | JACK KARGODORIAN |
| Drywall Nailing | 1/11/2023 | Not Ready for Inspection | JACK KARGODORIAN |
| Green Building Rough | 1/11/2023 | Approved | JACK KARGODORIAN |
| Insulation | 1/11/2023 | Not Ready for Inspection | JACK KARGODORIAN |
| PLUMBING-Rough | 1/11/2023 | Partial Approval | JACK KARGODORIAN |
| PLUMBING-Rough | 1/12/2023 | Partial Approval | JACK KARGODORIAN |
| Deputy Drilled-In Anchors | 1/13/2023 | Approved | JACK KARGODORIAN |
| Deputy Wood Construction | 3/10/2023 | Conditional Approval | JUAN VALENZUELA |
| Deputy Wood Construction | 3/15/2023 | Partial Approval | JACK KARGODORIAN |
| Underground Mechanical | 3/22/2023 | Partial Approval | JACK KARGODORIAN |
| HVAC-Rough | 3/30/2023 | Approved | JACK KARGODORIAN |
| Underground Mechanical | 3/30/2023 | Not Ready for Inspection | JACK KARGODORIAN |
| PLUMBING-Rough | 4/13/2023 | Partial Approval | JACK KARGODORIAN |
| ELECTRICAL-Rough | 5/25/2023 | Corrections Issued | THOMAS FINNILA |
| Interior/Exterior Lathing | 5/25/2023 | Not Ready for Inspection | THOMAS FINNILA |
| ELECTRICAL-Rough | 5/30/2023 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 5/30/2023 | Partial Approval | JACK KARGODORIAN |
| Wood Frame | 6/2/2023 | Corrections Issued | JACK KARGODORIAN |
| Insulation | 6/8/2023 | Approved | JACK KARGODORIAN |
| Wood Frame | 6/8/2023 | Approved | JACK KARGODORIAN |
| Drywall Nailing | 6/23/2023 | Approved | JACK KARGODORIAN |
| Shower Pan | 7/28/2023 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 8/7/2023 | Partial Approval | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 6/20/2024 | Approved | CHRISTOPHER ROJAS |
| Final | 6/20/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Final | 6/20/2024 | Approved | CHRISTOPHER ROJAS |
| MERV13>=Final | 6/20/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| MERV13>=Rough | 6/20/2024 | Approved | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 6/20/2024 | SGSOV Approved | CHRISTOPHER ROJAS |
| Smoke Detectors | 6/20/2024 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 6/28/2024 | Approved | VINCENT HANLEY |
| Final | 6/28/2024 | OK to Issue CofO | VINCENT HANLEY |
| HVAC-Final | 6/28/2024 | Approved | VINCENT HANLEY |
| MERV13>=Final | 6/28/2024 | Approved | VINCENT HANLEY |