2237 S SELBY AVE 90064
Certificate Information: 2237 S SELBY AVE 90064
- Application / Permit
- 20014-20000-04917
- Plan Check / Job No.
- B20VN14461
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD 25'-7" X 21' IRREGULAR SHAPED (2) STORY TO AND CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 7/30/2021
- Issuing Office
- Current Status
- CofO Issued on 6/7/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/9/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/3/2020 | SELLA BENYAMIN |
| Corrections Issued | 12/8/2020 | SELLA BENYAMIN |
| Quality Review Completed | 12/14/2020 | STEVEN KIM |
| Building Plans Picked Up | 12/16/2020 | APPLICANT |
| Plan Check Approved | 5/26/2021 | SELLA BENYAMIN |
| Issued | 7/30/2021 | APPLICANT |
| CofO in Progress | 5/26/2023 | CLAYTON GRAHAM |
| Permit Finaled | 6/7/2023 | DANIEL ORRANTE |
| CofO Issued | 6/7/2023 | DANIEL ORRANTE |
| Permit Finaled | 6/7/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Construction near power lines | Cleared | 2/5/2021 | RIDWAN HARDY |
| Grading Pre-Inspection | Cleared | 2/5/2021 | BRIAN MILLER |
| Address approval | Cleared | 2/17/2021 | CATHERINE ADROVER |
| Eng Process Fee Ord 176,300 | Cleared | 2/17/2021 | CATHERINE ADROVER |
| Hydrant and Access approval | Cleared | 3/11/2021 | MATTHEW CRAIG |
| Sewer availability | Cleared | 3/15/2021 | CATHERINE ADROVER |
| Low Impact Development | Cleared | 5/10/2021 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 5/12/2021 | HISASHI KOBAYAKAWA |
| GPI Written Notices | Cleared | 7/22/2021 | SELLA BENYAMIN |
Contact Information
| Contractor | Forsyth Construction Inc; Lic. No.: 560243-B | 578 WASHINGTON BLVD #377 MARINA DEL REY, CA 90292 |
| Engineer | Saberi,, Masoud; Lic. No.: C71553 | 1438 25TH ST APT 4 SANTA MONICA, CA 90404 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/23/2021 | Partial Inspection | KEVIN SARGSYAN |
| METHANE-Subgrade | 9/3/2021 | Approved | KEVIN SARGSYAN |
| Underground Mechanical | 9/24/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Methane Barrier | 9/27/2021 | Conditional Approval | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 10/1/2021 | Corrections Issued | KEVIN SARGSYAN |
| METHANE-Barrier | 10/1/2021 | Approved | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 10/4/2021 | Approved | EVAN COOPER |
| PLUMBING-Rough | 10/4/2021 | Corrections Issued | EVAN COOPER |
| Reinforced Concrete Frame | 10/4/2021 | Approved | EVAN COOPER |
| Deputy Reinf. Concrete | 10/5/2021 | Conditional Approval | KRISTEN CAUSEY |
| Deputy Wood Construction | 11/22/2021 | Conditional Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/29/2021 | Partial Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/2/2021 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 12/22/2021 | Partial Approval | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 1/5/2022 | Corrections Issued | KEVIN SARGSYAN |
| HVAC-Rough | 1/5/2022 | Approved | KEVIN SARGSYAN |
| METHANE-Rough | 1/5/2022 | Approved | KEVIN SARGSYAN |
| PLUMBING-Rough | 1/5/2022 | Corrections Issued | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 1/7/2022 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 1/7/2022 | Approved | KEVIN SARGSYAN |
| Green Building Rough | 1/7/2022 | Approved | KEVIN SARGSYAN |
| PLUMBING-Rough | 1/7/2022 | Approved | KEVIN SARGSYAN |
| Insulation | 1/14/2022 | Corrections Issued | DEANDRE HOFFMAN |
| Shower Pan | 1/14/2022 | Approved | DEANDRE HOFFMAN |
| Insulation | 1/21/2022 | Approved | KEVIN SARGSYAN |
| Drywall Nailing | 2/3/2022 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Final | 6/6/2022 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Final | 6/6/2022 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Final | 6/6/2022 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Final | 6/10/2022 | Corrections Issued | KEVIN SARGSYAN |
| Final | 6/10/2022 | Corrections Issued | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 6/10/2022 | Approved | KEVIN SARGSYAN |
| Green Building Final | 6/10/2022 | Approved | KEVIN SARGSYAN |
| HVAC-Final | 6/10/2022 | Approved | KEVIN SARGSYAN |
| PLUMBING-Final | 6/10/2022 | Approved | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 6/10/2022 | SGSOV Approved | KEVIN SARGSYAN |
| Service/Power Release | 6/10/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| Smoke Detectors | 6/10/2022 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Final | 7/1/2022 | Approved | KEVIN SARGSYAN |
| Final | 7/1/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| Final | 7/21/2022 | No Access for Inspection | OGANES TARAKHCHYAN |
| Special/Order Compliance | 7/22/2022 | No Access for Inspection | OGANES TARAKHCHYAN |
| Final | 7/28/2022 | Corrections Issued | CHRISTOPHER WILSON |
| Final | 8/3/2022 | Corrections Issued | PATRICK QUALEY |
| Special/Order Compliance | 5/5/2023 | Corrections Issued | KENNETH NAGLE |
| Final | 5/25/2023 | OK to Issue CofO | CLAYTON GRAHAM |
| SGSOV-Seismic Gas S/O Valve | 5/25/2023 | SGSOV Approved | CLAYTON GRAHAM |
| Service/Power Release | 5/26/2023 | Approved | CLAYTON GRAHAM |