2237 S SELBY AVE 90064

Certificate Information: 2237 S SELBY AVE 90064

Application / Permit
20014-20000-04917
Plan Check / Job No.
B20VN14461
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD 25'-7" X 21' IRREGULAR SHAPED (2) STORY TO AND CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 7/30/2021
Issuing Office
Current Status
CofO Issued on 6/7/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/9/2020 APPLICANT
Assigned to Plan Check Engineer 12/3/2020 SELLA BENYAMIN
Corrections Issued 12/8/2020 SELLA BENYAMIN
Quality Review Completed 12/14/2020 STEVEN KIM
Building Plans Picked Up 12/16/2020 APPLICANT
Plan Check Approved 5/26/2021 SELLA BENYAMIN
Issued 7/30/2021 APPLICANT
CofO in Progress 5/26/2023 CLAYTON GRAHAM
Permit Finaled 6/7/2023 DANIEL ORRANTE
CofO Issued 6/7/2023 DANIEL ORRANTE
Permit Finaled 6/7/2023 DANIEL ORRANTE

Permit Application Clearance Information

Construction near power lines Cleared 2/5/2021 RIDWAN HARDY
Grading Pre-Inspection Cleared 2/5/2021 BRIAN MILLER
Address approval Cleared 2/17/2021 CATHERINE ADROVER
Eng Process Fee Ord 176,300 Cleared 2/17/2021 CATHERINE ADROVER
Hydrant and Access approval Cleared 3/11/2021 MATTHEW CRAIG
Sewer availability Cleared 3/15/2021 CATHERINE ADROVER
Low Impact Development Cleared 5/10/2021 SUNG JOON WON
Roof/Waste drainage to street Cleared 5/12/2021 HISASHI KOBAYAKAWA
GPI Written Notices Cleared 7/22/2021 SELLA BENYAMIN

Contact Information

Contractor Forsyth Construction Inc; Lic. No.: 560243-B 578 WASHINGTON BLVD #377      MARINA DEL REY, CA 90292
Engineer Saberi,, Masoud; Lic. No.: C71553 1438 25TH ST APT 4      SANTA MONICA, CA 90404

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/23/2021 Partial Inspection KEVIN SARGSYAN
METHANE-Subgrade 9/3/2021 Approved KEVIN SARGSYAN
Underground Mechanical 9/24/2021 Partial Approval OGANES TARAKHCHYAN
Deputy Methane Barrier 9/27/2021 Conditional Approval JAVIER RAMOS JR
Footing/Foundation/Slab 10/1/2021 Corrections Issued KEVIN SARGSYAN
METHANE-Barrier 10/1/2021 Approved KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 10/4/2021 Approved EVAN COOPER
PLUMBING-Rough 10/4/2021 Corrections Issued EVAN COOPER
Reinforced Concrete Frame 10/4/2021 Approved EVAN COOPER
Deputy Reinf. Concrete 10/5/2021 Conditional Approval KRISTEN CAUSEY
Deputy Wood Construction 11/22/2021 Conditional Approval KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 11/29/2021 Partial Approval KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 12/2/2021 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 12/22/2021 Partial Approval KEVIN SARGSYAN
ELECTRICAL-Rough 1/5/2022 Corrections Issued KEVIN SARGSYAN
HVAC-Rough 1/5/2022 Approved KEVIN SARGSYAN
METHANE-Rough 1/5/2022 Approved KEVIN SARGSYAN
PLUMBING-Rough 1/5/2022 Corrections Issued KEVIN SARGSYAN
BUILDING-Rough-Frame 1/7/2022 Approved KEVIN SARGSYAN
ELECTRICAL-Rough 1/7/2022 Approved KEVIN SARGSYAN
Green Building Rough 1/7/2022 Approved KEVIN SARGSYAN
PLUMBING-Rough 1/7/2022 Approved KEVIN SARGSYAN
Insulation 1/14/2022 Corrections Issued DEANDRE HOFFMAN
Shower Pan 1/14/2022 Approved DEANDRE HOFFMAN
Insulation 1/21/2022 Approved KEVIN SARGSYAN
Drywall Nailing 2/3/2022 Approved KEVIN SARGSYAN
ELECTRICAL-Final 6/6/2022 Corrections Issued GERMAN RODRIGUEZ MENDOZA
HVAC-Final 6/6/2022 Corrections Issued GERMAN RODRIGUEZ MENDOZA
PLUMBING-Final 6/6/2022 Corrections Issued GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Final 6/10/2022 Corrections Issued KEVIN SARGSYAN
Final 6/10/2022 Corrections Issued KEVIN SARGSYAN
Footing/Foundation/Slab 6/10/2022 Approved KEVIN SARGSYAN
Green Building Final 6/10/2022 Approved KEVIN SARGSYAN
HVAC-Final 6/10/2022 Approved KEVIN SARGSYAN
PLUMBING-Final 6/10/2022 Approved KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 6/10/2022 SGSOV Approved KEVIN SARGSYAN
Service/Power Release 6/10/2022 Not Ready for Inspection KEVIN SARGSYAN
Smoke Detectors 6/10/2022 Approved KEVIN SARGSYAN
ELECTRICAL-Final 7/1/2022 Approved KEVIN SARGSYAN
Final 7/1/2022 Not Ready for Inspection KEVIN SARGSYAN
Final 7/21/2022 No Access for Inspection OGANES TARAKHCHYAN
Special/Order Compliance 7/22/2022 No Access for Inspection OGANES TARAKHCHYAN
Final 7/28/2022 Corrections Issued CHRISTOPHER WILSON
Final 8/3/2022 Corrections Issued PATRICK QUALEY
Special/Order Compliance 5/5/2023 Corrections Issued KENNETH NAGLE
Final 5/25/2023 OK to Issue CofO CLAYTON GRAHAM
SGSOV-Seismic Gas S/O Valve 5/25/2023 SGSOV Approved CLAYTON GRAHAM
Service/Power Release 5/26/2023 Approved CLAYTON GRAHAM