17345 W GILMORE ST 91406

Certificate Information: 17345 W GILMORE ST 91406

Application / Permit
20014-20000-04910
Plan Check / Job No.
B20VN14439
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD TWO (N) BEDROOMS & (1) FULL BATHROOM (28'-10" X 20'-2") TO (E) 1-STORY SFD; INTERIOR REMODEL
Permit Issued
Issued on 1/21/2021
Issuing Office
Current Status
CofO Issued on 9/24/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/5/2020 APPLICANT
Assigned to Plan Check Engineer 11/12/2020 NILOOFAR MEHRAIN
Corrections Issued 11/17/2020 NILOOFAR MEHRAIN
Building Plans Picked Up 11/17/2020 APPLICANT
Plan Check Approved 12/17/2020 NILOOFAR MEHRAIN
Issued 1/21/2021 APPLICANT
CofO in Progress 9/22/2021 STEVEN BACK
Permit Finaled 9/24/2021 JOHN JANSON
CofO Issued 9/24/2021 JOHN JANSON
Permit Finaled 9/24/2021 JOHN JANSON

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 12/2/2020 THOMAS LANG
Sewer availability Cleared 12/2/2020 THOMAS LANG
ZI Cleared 12/2/2020 RICHARD REASER
Eng Process Fee Ord 176,300 Cleared 12/3/2020 THOMAS LANG

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/28/2021 Approved DAVID SANDOVAL
Underground Mechanical 1/28/2021 Partial Approval DAVID SANDOVAL
BUILDING-Rough-Frame 2/11/2021 Partial Approval STEVEN BACK
PLUMBING-Rough 2/11/2021 Partial Approval STEVEN BACK
Insulation 2/16/2021 Partial Approval CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 2/22/2021 Partial Approval STEVEN BACK
ELECTRICAL-Final 3/1/2021 Corrections Issued STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 3/1/2021 Partial Approval STEVEN BACK
ELECTRICAL-Rough 5/4/2021 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 5/4/2021 Corrections Issued STEVEN BACK
HVAC-Rough 5/4/2021 Corrections Issued STEVEN BACK
PLUMBING-Rough 5/4/2021 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 5/18/2021 Approved VINCENT HANLEY
Interior/Exterior Lathing 6/1/2021 Partial Approval LILIANA PORTILLO
BUILDING-Rough-Frame 6/7/2021 Approved STEVEN BACK
Green Building Rough 6/7/2021 Approved STEVEN BACK
HVAC-Rough 6/7/2021 Approved STEVEN BACK
Insulation 6/11/2021 Approved ALIZAH MAYAGOITIA
Drywall Nailing 6/14/2021 Approved KRISTEN CAUSEY
Shower Pan 6/21/2021 Approved SHAVONNE ESPINOZA
Interior/Exterior Lathing 6/25/2021 Approved RYAN SALAZAR
Final 9/22/2021 OK to Issue CofO STEVEN BACK
Green Building Final 9/22/2021 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 9/22/2021 SGSOV Approved STEVEN BACK
Smoke Detectors 9/22/2021 Approved STEVEN BACK