5715 N TROOST AVE 91601

Certificate Information: 5715 N TROOST AVE 91601

Application / Permit
20014-20000-04877
Plan Check / Job No.
B20VN14381
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL. REBUILT 45'-3" X 43'-4" OF (E) SINGLE FAMILY DWELLING WITH ATTACHED GARAGE AND ADD 31' X 42'ADDITION. 17'-2" OF (E) WALL TO REMAIN. FIRE SPRIKLER REQUIRED NFPA-13D.
Permit Issued
Issued on 4/20/2021
Issuing Office
Current Status
CofO Issued on 6/27/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/4/2020 APPLICANT
Assigned to Plan Check Engineer 12/3/2020 SERGIO MUNIZ
Corrections Issued 12/7/2020 SERGIO MUNIZ
Quality Review Completed 12/18/2020 OMID HEDAYAT
Applicant returned to address corrections 3/19/2021 SERGIO MUNIZ
Plan Check Approved 4/7/2021 SERGIO MUNIZ
Building Plans Picked Up 4/8/2021 APPLICANT
Issued 4/20/2021 APPLICANT
CofO in Progress 5/24/2022 THOMAS FINNILA
Permit Finaled 6/27/2022 RONALD MYRICK
CofO Issued 6/27/2022 RONALD MYRICK
Permit Finaled 6/27/2022 RONALD MYRICK

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/11/2021 ADRIAN CASTRO
Permit Cleared 1/11/2021 ADRIAN CASTRO
Sewer availability Cleared 1/11/2021 ADRIAN CASTRO
Trees in Parkway Cleared 2/24/2021 JOHN KIM
Low Impact Development Cleared 3/10/2021 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 3/10/2021 ABDULLAH SADOZAI

Contact Information

Contractor Owner-Builder       ,
Engineer Le,, Thang Huu; Lic. No.: S4978 507 MAGELLAN RD      ARCADIA, CA 91007

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/10/2021 Approved THOMAS FINNILA
Footing/Foundation/Slab 5/26/2021 Corrections Issued THOMAS FINNILA
Footing/Foundation/Slab 6/2/2021 Conditional Approval THOMAS FINNILA
Deputy Drilled-In Anchors 6/3/2021 Conditional Approval ALAN MORELOS
Deputy Reinf. Concrete 6/3/2021 Conditional Approval ALAN MORELOS
Floor/Roof Diaphrgm/Shear Wall 6/17/2021 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 6/28/2021 Partial Approval THOMAS FINNILA
BUILDING-Rough-Frame 7/1/2021 Partial Approval ARAM AVEDISIAN
Insulation 7/1/2021 Partial Approval ARAM AVEDISIAN
PLUMBING-Rough 7/1/2021 Partial Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 7/7/2021 No Access for Inspection RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 7/7/2021 Partial Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 8/9/2021 Corrections Issued THOMAS FINNILA
Deputy Wood Construction 8/10/2021 Conditional Approval AMY COLIN
Floor/Roof Diaphrgm/Shear Wall 8/23/2021 Partial Approval THOMAS FINNILA
ELECTRICAL-Rough 8/31/2021 Corrections Issued THOMAS FINNILA
PLUMBING-Rough 9/1/2021 Corrections Issued THOMAS FINNILA
Special/Order Compliance 9/1/2021 Partial Inspection LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 9/2/2021 Conditional Approval THOMAS FINNILA
BUILDING-Rough-Frame 9/3/2021 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Rough 9/3/2021 Approved THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 9/22/2021 Partial Approval THOMAS FINNILA
HVAC-Rough 9/24/2021 Approved THOMAS FINNILA
PLUMBING-Rough 10/5/2021 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 10/7/2021 Approved WILLIAM KUEHN
Green Building Rough 10/7/2021 Approved WILLIAM KUEHN
Interior/Exterior Lathing 10/7/2021 Partial Inspection WILLIAM KUEHN
MERV13>=Rough 10/7/2021 Approved WILLIAM KUEHN
Insulation 10/12/2021 Not Ready for Inspection THOMAS FINNILA
Insulation 10/15/2021 Approved THOMAS FINNILA
Shower Pan 10/18/2021 Approved MISAEL ESPARZA
Drywall Nailing 10/27/2021 Approved THOMAS FINNILA
Interior/Exterior Lathing 11/1/2021 Approved THOMAS FINNILA
ELECTRICAL-Final 2/28/2022 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Final 2/28/2022 Not Ready for Inspection THOMAS FINNILA
Underground Mechanical 2/28/2022 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Final 3/16/2022 Partial Approval THOMAS FINNILA
Underground Mechanical 3/16/2022 Partial Approval THOMAS FINNILA
PLUMBING-Final 3/23/2022 Approved DAVID MATSON
ELECTRICAL-Final 3/29/2022 Corrections Issued THOMAS FINNILA
ELECTRICAL-Final 4/7/2022 Approved THOMAS FINNILA
HVAC-Final 4/7/2022 Corrections Issued THOMAS FINNILA
HVAC-Final 4/21/2022 Approved JENNIFER RABUCHIN
MERV13>=Final 4/21/2022 Approved JENNIFER RABUCHIN
Final 5/4/2022 Not Ready for Inspection DAVID MATSON
Footing/Foundation/Slab 5/4/2022 Approved THOMAS FINNILA
Final 5/23/2022 OK to Issue CofO THOMAS FINNILA
Green Building Final 5/23/2022 Approved THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 5/23/2022 SGSOV Approved THOMAS FINNILA
Smoke Detectors 5/23/2022 Approved THOMAS FINNILA