3048 N PASSMORE DR 90068
Certificate Information: 3048 N PASSMORE DR 90068
- Application / Permit
- 20014-20000-04870
- Plan Check / Job No.
- B20VN14361
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION OF (N) BEDROOM, BATHROOM, DINING ROOM, LAUNDRY ROOM & PLAY ROOM (IRR 26'-4" X 20'-11") TO (E) 1-STORY SFD W/ ATTACHED GARAGE
- Permit Issued
- Issued on 3/8/2021
- Issuing Office
- Current Status
- CofO Issued on 1/8/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/4/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/12/2020 | NILOOFAR MEHRAIN |
| Corrections Issued | 11/17/2020 | NILOOFAR MEHRAIN |
| Plan Check Approved | 2/9/2021 | NILOOFAR MEHRAIN |
| Issued | 3/8/2021 | APPLICANT |
| Building Plans Picked Up | 3/10/2021 | APPLICANT |
| CofO in Progress | 10/27/2021 | BRIAN SULLIVAN |
| Permit Finaled | 1/8/2022 | DEROLD HAUFF |
| CofO Issued | 1/8/2022 | DEROLD HAUFF |
| Permit Finaled | 1/8/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Miscellaneous | Cleared | 11/20/2020 | LIZZI BEDUYA |
| Specific Plan | Cleared | 11/20/2020 | LIZZI BEDUYA |
| ZI | Cleared | 11/20/2020 | LIZZI BEDUYA |
| Hydrant and Access approval | Cleared | 1/6/2021 | MATTHEW CRAIG |
| Eng Process Fee Ord 176,300 | Cleared | 1/25/2021 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 1/25/2021 | JOHN TRIANTAFYLLOS |
| Low Impact Development | Cleared | 2/4/2021 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 2/4/2021 | JOHN TRIANTAFYLLOS |
| Grading Pre-Inspection | Cleared | 2/9/2021 | NILOOFAR MEHRAIN |
Contact Information
| Contractor | Shenon Construction; Lic. No.: 939809-B | 1420 N ALTA VISTA BLVD #404 LOS ANGELES, CA 90046 |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 22121 CLARENDON ST APT 340 WOODLAND HILLS, CA 91367 |
Inspector Information
| ROY SPAULDING, (213) 202-3461 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/11/2021 | Conditional Approval | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 3/16/2021 | Corrections Issued | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 3/17/2021 | Approved | BRIAN SULLIVAN |
| PLUMBING-Rough | 3/30/2021 | Partial Approval | BRIAN SULLIVAN |
| Wood Frame | 3/30/2021 | Partial Approval | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/8/2021 | Partial Approval | BRIAN SULLIVAN |
| Insulation | 4/8/2021 | Partial Approval | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/9/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Insulation | 4/9/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/5/2021 | Partial Approval | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 5/11/2021 | Conditional Approval | BRIAN SULLIVAN |
| HVAC-Rough | 5/11/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| PLUMBING-Rough | 5/11/2021 | Approved | BRIAN SULLIVAN |
| Insulation | 5/17/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 5/17/2021 | Corrections Issued | BRIAN SULLIVAN |
| Shower Pan | 5/17/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 5/20/2021 | Partial Approval | BRIAN SULLIVAN |
| Shower Pan | 5/20/2021 | Approved | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 5/27/2021 | Approved | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 6/3/2021 | Approved | BRIAN SULLIVAN |
| Green Building Rough | 6/3/2021 | Approved | BRIAN SULLIVAN |
| HVAC-Rough | 6/3/2021 | Approved | BRIAN SULLIVAN |
| Insulation | 6/7/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 6/11/2021 | Approved | THOMAS LOGRASSO |
| ELECTRICAL-Final | 9/9/2021 | Approved | BRIAN SULLIVAN |
| Final | 9/9/2021 | Corrections Issued | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 9/9/2021 | Approved | BRIAN SULLIVAN |
| Green Building Final | 9/9/2021 | Approved | BRIAN SULLIVAN |
| HVAC-Final | 9/9/2021 | Approved | BRIAN SULLIVAN |
| PLUMBING-Final | 9/9/2021 | Approved | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 9/9/2021 | SGSOV Not Ready | BRIAN SULLIVAN |
| Smoke Detectors | 9/9/2021 | Approved | BRIAN SULLIVAN |
| Final | 10/26/2021 | OK to Issue CofO | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 10/26/2021 | SGSOV Approved | BRIAN SULLIVAN |