6677 N ETHEL AVE 91606

Certificate Information: 6677 N ETHEL AVE 91606

Application / Permit
20014-20000-04865
Plan Check / Job No.
B20VN14347
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
28' X 22'-11" ADDITION OF A 2-STORY ACCESSORY DWELLING UNIT TO (E) DETACHED GARAGE PER LAMC 12.22 A.33(c)-(d).
Permit Issued
Issued on 3/23/2021
Issuing Office
Current Status
CofO Issued on 2/17/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/4/2020 APPLICANT
Assigned to Plan Check Engineer 12/3/2020 SERGIO MUNIZ
Corrections Issued 12/7/2020 SERGIO MUNIZ
Quality Review Completed 12/18/2020 OMID HEDAYAT
Building Plans Picked Up 12/18/2020 APPLICANT
Plan Check Approved 3/23/2021 SERGIO MUNIZ
Issued 3/23/2021 APPLICANT
CofO in Progress 1/31/2022 JENNIFER RABUCHIN
Permit Finaled 2/17/2022 MICHAEL SMITH
CofO Issued 2/17/2022 MICHAEL SMITH
Permit Finaled 2/17/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 12/21/2020 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 12/23/2020 GABRIEL ROBLES
Sewer availability Cleared 12/23/2020 GABRIEL ROBLES
Construction near power lines Cleared 2/5/2021 RIDWAN HARDY
Low Impact Development Cleared 3/9/2021 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 3/9/2021 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/5/2021 Approved DANIEL ORRANTE
Underground Mechanical 5/7/2021 Approved RICHARD DOCKUS
Footing/Foundation/Slab 5/17/2021 Approved RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 7/30/2021 Partial Approval CHRISTOPHE COCHRAN
Deputy Wood Construction 8/4/2021 No Access for Inspection JUSTIN HAWLEY
Floor/Roof Diaphrgm/Shear Wall 8/6/2021 Partial Approval CHRISTOPHE COCHRAN
HVAC-Rough 8/6/2021 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 8/6/2021 Partial Approval CHRISTOPHE COCHRAN
ELECTRICAL-Rough 8/11/2021 Approved DANIEL DREW
PLUMBING-Rough 8/11/2021 Approved DANIEL DREW
HVAC-Rough 8/17/2021 Not Ready for Inspection JOHN HAYES
Wood Frame 8/17/2021 Corrections Issued JOHN HAYES
BUILDING-Rough-Frame 8/19/2021 Corrections Issued CHRISTOPHER DELLEFIELD
Green Building Rough 8/19/2021 Not Ready for Inspection CHRISTOPHER DELLEFIELD
HVAC-Rough 8/19/2021 Approved CHRISTOPHER DELLEFIELD
PLUMBING-Rough 8/19/2021 Approved CHRISTOPHER DELLEFIELD
Wood Frame 8/19/2021 Not Ready for Inspection CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 8/23/2021 Conditional Approval CHRISTOPHE COCHRAN
Green Building Rough 8/23/2021 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 8/23/2021 Partial Approval CHRISTOPHE COCHRAN
Insulation 8/26/2021 Corrections Issued ALIZAH MAYAGOITIA
Shower Pan 8/26/2021 Not Ready for Inspection ALIZAH MAYAGOITIA
Drywall Nailing 9/1/2021 Approved CHRISTOPHE COCHRAN
Insulation 9/1/2021 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 9/16/2021 Approved DANIEL DREW
Shower Pan 9/16/2021 Approved DANIEL DREW
Service/Power Release 11/4/2021 Not Ready for Inspection CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 1/11/2022 Approved CHRISTOPHE COCHRAN
Final 1/11/2022 Corrections Issued CHRISTOPHE COCHRAN
Gas Test 1/11/2022 Approved CHRISTOPHE COCHRAN
Green Building Final 1/11/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 1/11/2022 SGSOV Not Ready CHRISTOPHE COCHRAN
Smoke Detectors 1/11/2022 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Final 1/27/2022 Approved JENNIFER RABUCHIN
Final 1/27/2022 OK to Issue CofO JENNIFER RABUCHIN
Green Building Final 1/27/2022 Approved JENNIFER RABUCHIN
HVAC-Final 1/27/2022 Approved JENNIFER RABUCHIN
PLUMBING-Final 1/27/2022 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 1/27/2022 SGSOV Approved JENNIFER RABUCHIN