5362 E TEMPLETON ST 90032
Certificate Information: 5362 E TEMPLETON ST 90032
- Application / Permit
- 20014-20000-04854
- Plan Check / Job No.
- B20VN14327
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL AND 68 SQ. FT. ADDITION TO (E) SFD, REPLACE ALL WINDOWS W/SAME SIZE. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 9/14/2021
- Issuing Office
- Current Status
- CofO Issued on 3/25/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/18/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/17/2020 | COLIN LOREDO |
| Corrections Issued | 12/21/2020 | COLIN LOREDO |
| Quality Review Completed | 12/31/2020 | OMID HEDAYAT |
| Plan Check Approved | 6/17/2021 | COLIN LOREDO |
| Issued | 9/14/2021 | APPLICANT |
| Building Plans Picked Up | 9/21/2021 | APPLICANT |
| CofO in Progress | 3/22/2023 | AMY COLIN |
| Permit Finaled | 3/25/2023 | DEROLD HAUFF |
| CofO Issued | 3/25/2023 | DEROLD HAUFF |
| Permit Finaled | 3/25/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 2/16/2021 | WALLIE JONG |
| Sewer availability | Cleared | 2/16/2021 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 2/18/2021 | WALLIE JONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adams,, Robert Charles; Lic. No.: C21234 | 22129 BRYANT STREET CANOGA PARK, CA 91304 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/8/2021 | Corrections Issued | COREY HUPP |
| Footing/Foundation/Slab | 3/3/2022 | No Access for Inspection | COREY HUPP |
| Rough-Elec/Plmb/HVAC | 6/24/2022 | Approved | AMY COLIN |
| HVAC-Rough | 7/5/2022 | Not Ready for Inspection | AMY COLIN |
| Wood Frame | 7/5/2022 | Corrections Issued | AMY COLIN |
| BUILDING-Rough-Frame | 7/8/2022 | Conditional Approval | AMY COLIN |
| Green Building Rough | 7/8/2022 | Not Ready for Inspection | AMY COLIN |
| Insulation | 7/19/2022 | Approved | AMY COLIN |
| Interior/Exterior Lathing | 7/19/2022 | Partial Approval | AMY COLIN |
| Drywall Nailing | 8/5/2022 | Approved | ALIZAH MAYAGOITIA |
| Green Building Rough | 8/5/2022 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 8/5/2022 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 3/17/2023 | Approved | AMY COLIN |
| Final | 3/17/2023 | Partial Approval | AMY COLIN |
| Footing/Foundation/Slab | 3/17/2023 | Approved | AMY COLIN |
| Green Building Final | 3/17/2023 | Approved | AMY COLIN |
| SGSOV-Seismic Gas S/O Valve | 3/17/2023 | SGSOV Approved | AMY COLIN |
| Smoke Detectors | 3/17/2023 | Approved | AMY COLIN |
| Final | 3/22/2023 | OK to Issue CofO | AMY COLIN |