5517 N STROHM AVE 91601

Certificate Information: 5517 N STROHM AVE 91601

Application / Permit
20014-20000-04828
Plan Check / Job No.
B20VN14257
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL & ADDITION TO (E) 1-STORY SFD W/ ATTACHED GARAGE: DEMO ENTIRE SFD EXCEPT 32'-5" OF NORTH 38'4" OF SOUTH WALLS & FOOTINGS & ADD 1-SFD W/ ATTACHED GARAGE (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
Permit Issued
Issued on 3/26/2021
Issuing Office
Current Status
CofO Issued on 8/23/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/2/2020 APPLICANT
Assigned to Plan Check Engineer 11/24/2020 NILOOFAR MEHRAIN
Corrections Issued 12/3/2020 NILOOFAR MEHRAIN
Quality Review Completed 12/3/2020 CHON CHIO KUO
Building Plans Picked Up 12/4/2020 APPLICANT
Plan Check Approved 3/4/2021 NILOOFAR MEHRAIN
Issued 3/26/2021 APPLICANT
CofO in Progress 8/16/2022 JOHN HAYES
Permit Finaled 8/23/2022 DANIEL ORRANTE
CofO Issued 8/23/2022 DANIEL ORRANTE
Permit Finaled 8/23/2022 DANIEL ORRANTE

Permit Application Clearance Information

CPC Cleared 12/7/2020 LAUREN PADICK
Sewer availability Cleared 12/15/2020 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 12/22/2020 GABRIEL ROBLES
Hydrant and Access approval Cleared 1/25/2021 KURT CORRAL
Roof/Waste drainage to street Cleared 3/1/2021 ABDULLAH SADOZAI
Low Impact Development Cleared 3/4/2021 ORVAL HERNANDEZ-MARCI

Contact Information

Contractor Owner-Builder       ,
Engineer Hajdari,, Genti; Lic. No.: C88031 140 S MENTOR AVE APT #207      PASADENA, CA 91106

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/23/2021 Approved DANIEL DREW
BUILDING-Rough-Frame 5/3/2021 Corrections Issued RICHARD DOCKUS
BUILDING-Rough-Frame 5/4/2021 Partial Approval DANIEL DREW
Insulation 5/4/2021 Partial Approval DANIEL DREW
PLUMBING-Rough 5/4/2021 Partial Approval DANIEL DREW
Floor/Roof Diaphrgm/Shear Wall 5/5/2021 Partial Approval DANIEL DREW
Floor/Roof Diaphrgm/Shear Wall 6/1/2021 Partial Approval JOHN HAYES
BUILDING-Rough-Frame 8/27/2021 Corrections Issued CHRISTOPHER DELLEFIELD
Gas Test 8/27/2021 Approved CHRISTOPHER DELLEFIELD
Green Building Rough 8/27/2021 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 8/27/2021 Conditional Approval CHRISTOPHER DELLEFIELD
Rough-Elec/Plmb/HVAC 8/27/2021 Partial Approval CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 9/7/2021 Approved DANIEL DREW
PLUMBING-Rough 9/7/2021 Approved DANIEL DREW
Drywall Nailing 9/24/2021 No Access for Inspection LILIANA PORTILLO
Insulation 9/24/2021 No Access for Inspection LILIANA PORTILLO
Drywall Nailing 9/28/2021 Approved LILIANA PORTILLO
Insulation 9/28/2021 Approved LILIANA PORTILLO
Interior/Exterior Lathing 11/3/2021 Partial Approval CALEB MEISTER
Shower Pan 11/3/2021 Approved CALEB MEISTER
Interior/Exterior Lathing 11/4/2021 Approved DANIEL DREW
Shower Pan 11/4/2021 Approved DANIEL DREW
Gas Test 12/29/2021 Partial Approval JOHN KIDWELL
Final 2/18/2022 Corrections Issued THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 2/18/2022 SGSOV Not Ready THOMAS FINNILA
Smoke Detectors 2/18/2022 No Access for Inspection THOMAS FINNILA
ELECTRICAL-Final 4/4/2022 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 8/11/2022 Approved JOHN HAYES
Final 8/11/2022 OK to Issue CofO JOHN HAYES
Green Building Final 8/11/2022 Approved JOHN HAYES
Green Building Rough 8/11/2022 Approved JOHN HAYES
SGSOV-Seismic Gas S/O Valve 8/11/2022 SGSOV Approved JOHN HAYES
Smoke Detectors 8/11/2022 Approved JOHN HAYES
Service/Power Release 8/17/2022 Approved JOHN HAYES