7752 N LOUISE AVE 91406
Certificate Information: 7752 N LOUISE AVE 91406
- Application / Permit
- 20014-20000-04822
- Plan Check / Job No.
- B20VN14241
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c)(d) (NFPA-13D FIRE SPRINKLERS THRUOGHOUT)
- Permit Issued
- Issued on 4/29/2021
- Issuing Office
- Current Status
- CofO Issued on 11/8/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/30/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/24/2020 | NILOOFAR MEHRAIN |
| Corrections Issued | 12/1/2020 | NILOOFAR MEHRAIN |
| Quality Review Completed | 12/1/2020 | CHON CHIO KUO |
| Building Plans Picked Up | 12/1/2020 | APPLICANT |
| Applicant returned to address corrections | 1/14/2021 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 3/26/2021 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 4/9/2021 | NILOOFAR MEHRAIN |
| Plan Check Approved | 4/18/2021 | NILOOFAR MEHRAIN |
| Issued | 4/29/2021 | APPLICANT |
| CofO in Progress | 7/30/2024 | RAUL OLAGI |
| Permit Finaled | 11/8/2024 | DANIEL ORRANTE |
| CofO Issued | 11/8/2024 | DANIEL ORRANTE |
| Permit Finaled | 11/8/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 12/16/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 12/16/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 12/16/2020 | ADRIAN CASTRO |
| Hydrant and Access approval | Cleared | 1/21/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 3/16/2021 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 3/26/2021 | ADRIAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/19/2021 | Approved | ARTHUR SARGSYAN |
| Footing/Foundation/Slab | 5/28/2021 | Approved | ARTHUR SARGSYAN |
| Pre-Inspection | 10/6/2021 | Approved | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/10/2021 | Partial Approval | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 12/2/2021 | Not Ready for Inspection | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 12/7/2021 | Approved | RAUL OLAGI |
| ELECTRICAL-Rough | 12/10/2021 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Gas Test | 12/10/2021 | Partial Approval | JENNIFER RABUCHIN |
| HVAC-Rough | 12/10/2021 | Partial Approval | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 12/10/2021 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 12/10/2021 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 12/14/2021 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Rough | 12/14/2021 | Corrections Issued | RAUL OLAGI |
| Green Building Rough | 12/14/2021 | Approved | RAUL OLAGI |
| Verify Sprinkler Sign Off | 12/14/2021 | Corrections Issued | RAUL OLAGI |
| Shower Pan | 12/22/2021 | Approved | ALAN MORELOS |
| Interior/Exterior Lathing | 12/29/2021 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 1/3/2022 | No Access for Inspection | ALAN MORELOS |
| Drywall Nailing | 1/3/2022 | Not Ready for Inspection | ALAN MORELOS |
| BUILDING-Rough-Frame | 1/6/2022 | Approved | RAUL OLAGI |
| Insulation | 1/6/2022 | Approved | RAUL OLAGI |
| Special/Order Compliance | 1/6/2022 | Corrections Issued | RAUL OLAGI |
| Verify Sprinkler Sign Off | 1/6/2022 | Approved | RAUL OLAGI |
| Drywall Nailing | 1/13/2022 | Approved | RAUL OLAGI |
| ELECTRICAL-Final | 8/15/2022 | Not Ready for Inspection | RAUL OLAGI |
| Gas Test | 8/15/2022 | Not Ready for Inspection | RAUL OLAGI |
| HVAC-Final | 8/15/2022 | Not Ready for Inspection | RAUL OLAGI |
| PLUMBING-Final | 8/15/2022 | Not Ready for Inspection | RAUL OLAGI |
| Service/Power Release | 8/15/2022 | Not Ready for Inspection | RAUL OLAGI |
| ELECTRICAL-Final | 9/2/2022 | No Access for Inspection | RAUL OLAGI |
| Gas Test | 9/2/2022 | No Access for Inspection | RAUL OLAGI |
| HVAC-Final | 9/2/2022 | No Access for Inspection | RAUL OLAGI |
| PLUMBING-Final | 9/2/2022 | No Access for Inspection | RAUL OLAGI |
| ELECTRICAL-Final | 9/15/2022 | Corrections Issued | RAUL OLAGI |
| Final | 9/15/2022 | Corrections Issued | RAUL OLAGI |
| Green Building Final | 9/15/2022 | Approved | RAUL OLAGI |
| HVAC-Final | 9/15/2022 | Approved | RAUL OLAGI |
| PLUMBING-Final | 9/15/2022 | Corrections Issued | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 9/15/2022 | SGSOV Not Ready | RAUL OLAGI |
| Smoke Detectors | 9/15/2022 | Approved | RAUL OLAGI |
| ELECTRICAL-Final | 7/30/2024 | Approved | RAUL OLAGI |
| Final | 7/30/2024 | OK to Issue CofO | RAUL OLAGI |
| PLUMBING-Final | 7/30/2024 | Approved | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 7/30/2024 | SGSOV Approved | RAUL OLAGI |
| Service/Power Release | 7/30/2024 | Approved | RAUL OLAGI |