7752 N LOUISE AVE 91406

Certificate Information: 7752 N LOUISE AVE 91406

Application / Permit
20014-20000-04822
Plan Check / Job No.
B20VN14241
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c)(d) (NFPA-13D FIRE SPRINKLERS THRUOGHOUT)
Permit Issued
Issued on 4/29/2021
Issuing Office
Current Status
CofO Issued on 11/8/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/30/2020 APPLICANT
Assigned to Plan Check Engineer 11/24/2020 NILOOFAR MEHRAIN
Corrections Issued 12/1/2020 NILOOFAR MEHRAIN
Quality Review Completed 12/1/2020 CHON CHIO KUO
Building Plans Picked Up 12/1/2020 APPLICANT
Applicant returned to address corrections 1/14/2021 NILOOFAR MEHRAIN
Applicant returned to address corrections 3/26/2021 NILOOFAR MEHRAIN
Applicant returned to address corrections 4/9/2021 NILOOFAR MEHRAIN
Plan Check Approved 4/18/2021 NILOOFAR MEHRAIN
Issued 4/29/2021 APPLICANT
CofO in Progress 7/30/2024 RAUL OLAGI
Permit Finaled 11/8/2024 DANIEL ORRANTE
CofO Issued 11/8/2024 DANIEL ORRANTE
Permit Finaled 11/8/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 12/16/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 12/16/2020 ADRIAN CASTRO
Sewer availability Cleared 12/16/2020 ADRIAN CASTRO
Hydrant and Access approval Cleared 1/21/2021 MATTHEW CRAIG
Low Impact Development Cleared 3/16/2021 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 3/26/2021 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/19/2021 Approved ARTHUR SARGSYAN
Footing/Foundation/Slab 5/28/2021 Approved ARTHUR SARGSYAN
Pre-Inspection 10/6/2021 Approved JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 11/10/2021 Partial Approval RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 12/2/2021 Not Ready for Inspection RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 12/7/2021 Approved RAUL OLAGI
ELECTRICAL-Rough 12/10/2021 Not Ready for Inspection JENNIFER RABUCHIN
Gas Test 12/10/2021 Partial Approval JENNIFER RABUCHIN
HVAC-Rough 12/10/2021 Partial Approval JENNIFER RABUCHIN
Interior/Exterior Lathing 12/10/2021 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 12/10/2021 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 12/14/2021 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 12/14/2021 Corrections Issued RAUL OLAGI
Green Building Rough 12/14/2021 Approved RAUL OLAGI
Verify Sprinkler Sign Off 12/14/2021 Corrections Issued RAUL OLAGI
Shower Pan 12/22/2021 Approved ALAN MORELOS
Interior/Exterior Lathing 12/29/2021 Approved RAUL OLAGI
BUILDING-Rough-Frame 1/3/2022 No Access for Inspection ALAN MORELOS
Drywall Nailing 1/3/2022 Not Ready for Inspection ALAN MORELOS
BUILDING-Rough-Frame 1/6/2022 Approved RAUL OLAGI
Insulation 1/6/2022 Approved RAUL OLAGI
Special/Order Compliance 1/6/2022 Corrections Issued RAUL OLAGI
Verify Sprinkler Sign Off 1/6/2022 Approved RAUL OLAGI
Drywall Nailing 1/13/2022 Approved RAUL OLAGI
ELECTRICAL-Final 8/15/2022 Not Ready for Inspection RAUL OLAGI
Gas Test 8/15/2022 Not Ready for Inspection RAUL OLAGI
HVAC-Final 8/15/2022 Not Ready for Inspection RAUL OLAGI
PLUMBING-Final 8/15/2022 Not Ready for Inspection RAUL OLAGI
Service/Power Release 8/15/2022 Not Ready for Inspection RAUL OLAGI
ELECTRICAL-Final 9/2/2022 No Access for Inspection RAUL OLAGI
Gas Test 9/2/2022 No Access for Inspection RAUL OLAGI
HVAC-Final 9/2/2022 No Access for Inspection RAUL OLAGI
PLUMBING-Final 9/2/2022 No Access for Inspection RAUL OLAGI
ELECTRICAL-Final 9/15/2022 Corrections Issued RAUL OLAGI
Final 9/15/2022 Corrections Issued RAUL OLAGI
Green Building Final 9/15/2022 Approved RAUL OLAGI
HVAC-Final 9/15/2022 Approved RAUL OLAGI
PLUMBING-Final 9/15/2022 Corrections Issued RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 9/15/2022 SGSOV Not Ready RAUL OLAGI
Smoke Detectors 9/15/2022 Approved RAUL OLAGI
ELECTRICAL-Final 7/30/2024 Approved RAUL OLAGI
Final 7/30/2024 OK to Issue CofO RAUL OLAGI
PLUMBING-Final 7/30/2024 Approved RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 7/30/2024 SGSOV Approved RAUL OLAGI
Service/Power Release 7/30/2024 Approved RAUL OLAGI