6437 N SATSUMA AVE 91606
Certificate Information: 6437 N SATSUMA AVE 91606
- Application / Permit
- 20014-20000-04815
- Plan Check / Job No.
- B20VN14227
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) WORKSHOP INTO (N) ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c)(d) & ADD FOR (N) LIVING ROOM (20' X 8'-6") PER ENG'R DESIGN
- Permit Issued
- Issued on 6/25/2021
- Issuing Office
- Current Status
- CofO Issued on 4/6/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/3/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/12/2020 | NILOOFAR MEHRAIN |
| Corrections Issued | 11/17/2020 | NILOOFAR MEHRAIN |
| Plan Check Approved | 5/5/2021 | NILOOFAR MEHRAIN |
| Building Plans Picked Up | 5/7/2021 | APPLICANT |
| Issued | 6/25/2021 | APPLICANT |
| CofO in Progress | 3/15/2023 | JOHN HAYES |
| Permit Finaled | 4/6/2023 | MICHAEL SMITH |
| CofO Issued | 4/6/2023 | MICHAEL SMITH |
| Permit Finaled | 4/6/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Miscellaneous | Cleared | 2/10/2021 | MINDY NGUYEN |
| Address approval | Cleared | 2/17/2021 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 2/17/2021 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 2/19/2021 | ADRIAN CASTRO |
| Sewer availability | Cleared | 2/19/2021 | ADRIAN CASTRO |
| Hydrant and Access approval | Cleared | 4/26/2021 | MATTHEW CRAIG |
Contact Information
| Contractor | Beyond Builders Inc; Lic. No.: 1053261-B | 10012 AVONCROFT STREET WHITTIER, CA 90601 |
| Engineer | Babapirzadeh,, Ghazal; Lic. No.: C90480 | 1530 N DETROIT ST APT 109 LOS ANGELES, CA 90046 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 8/12/2021 | Approved | DANIEL DREW |
| Deputy Drilled-In Anchors | 8/20/2021 | Approved | DANIEL DREW |
| Excavation/Setback/Form/Re-Bar | 8/23/2021 | Approved | DANIEL DREW |
| Footing/Foundation/Slab | 8/23/2021 | Approved | DANIEL DREW |
| BUILDING-Rough-Frame | 10/12/2021 | Not Ready for Inspection | DANIEL DREW |
| Green Building Rough | 10/12/2021 | Not Ready for Inspection | DANIEL DREW |
| Rough-Elec/Plmb/HVAC | 10/12/2021 | Not Ready for Inspection | DANIEL DREW |
| ELECTRICAL-Rough | 11/18/2021 | Approved | DANIEL DREW |
| Floor/Roof Diaphrgm/Shear Wall | 11/18/2021 | Approved | DANIEL DREW |
| PLUMBING-Rough | 11/18/2021 | Approved | DANIEL DREW |
| Gas Test | 12/3/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| Insulation | 12/3/2021 | Corrections Issued | MISAEL ESPARZA |
| Insulation | 12/16/2021 | No Access for Inspection | MICHEL ABAJAN |
| Gas Test | 12/23/2021 | No Access for Inspection | JACK KARGODORIAN |
| Insulation | 12/23/2021 | No Access for Inspection | JACK KARGODORIAN |
| Insulation | 1/27/2022 | Corrections Issued | DAVID MATSON |
| Interior/Exterior Lathing | 1/27/2022 | Partial Approval | DAVID MATSON |
| Insulation | 2/4/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Insulation | 2/23/2022 | Not Ready for Inspection | CALEB MEISTER |
| Insulation | 3/8/2022 | Partial Approval | MATT KELLERMAN |
| BUILDING-Rough-Frame | 3/23/2022 | Approved | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/23/2022 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 3/23/2022 | Approved | ARAM AVEDISIAN |
| Insulation | 3/23/2022 | Approved | ARAM AVEDISIAN |
| Drywall Nailing | 4/26/2022 | Approved | CALEB MEISTER |
| Shower Pan | 7/11/2022 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 7/19/2022 | Approved | ASHLEY THOMPSON |
| Final | 9/19/2022 | Corrections Issued | JOHN HAYES |
| Green Building Final | 9/19/2022 | No Access for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 9/19/2022 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 9/19/2022 | Not Ready for Inspection | JOHN HAYES |
| Final | 10/24/2022 | Corrections Issued | JOHN HAYES |
| Green Building Final | 10/24/2022 | Approved | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 10/24/2022 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 10/24/2022 | Not Ready for Inspection | JOHN HAYES |
| Final | 12/19/2022 | Not Ready for Inspection | JOHN COLEMAN |
| SGSOV-Seismic Gas S/O Valve | 12/19/2022 | SGSOV Approved | JOHN COLEMAN |
| Smoke Detectors | 12/19/2022 | Approved | JOHN COLEMAN |
| Final | 1/9/2023 | Corrections Issued | JOHN HAYES |
| Final | 2/7/2023 | Corrections Issued | JOHN HAYES |
| Final | 3/6/2023 | Not Ready for Inspection | JOHN HAYES |
| Final | 3/14/2023 | OK to Issue CofO | JOHN HAYES |