354 S 5TH AVE 90291

Certificate Information: 354 S 5TH AVE 90291

Application / Permit
20014-20000-04798
Plan Check / Job No.
B20VN14197
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL & ADDITION TO (E) 1 STORY SFD AND TO CONNECT (E) DET. GARAGE TO SFD ;FIRE SPRINKLER NFPA-13D
Permit Issued
Issued on 3/20/2023
Issuing Office
Current Status
CofO Issued on 1/8/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/1/2020 APPLICANT
Assigned to Plan Check Engineer 11/19/2020 MOHAMMAD ESMAILI
Corrections Issued 11/25/2020 MOHAMMAD ESMAILI
Quality Review Completed 12/10/2020 OMID HEDAYAT
Building Plans Picked Up 12/11/2020 APPLICANT
Applicant returned to address corrections 9/27/2021 MOHAMMAD ESMAILI
Applicant returned to address corrections 2/11/2022 MOHAMMAD ESMAILI
Applicant returned to address corrections 2/25/2022 MOHAMMAD ESMAILI
Applicant returned to address corrections 3/23/2022 MOHAMMAD ESMAILI
Applicant returned to address corrections 12/5/2022 MOHAMMAD ESMAILI
Plan Check Approved 2/27/2023 MOHAMMAD ESMAILI
Issued 3/20/2023 APPLICANT
Permit Expired-Status Void 9/20/2024 DAVID FEILER
Re-Activate Permit 9/24/2024 DAVID FEILER
CofO in Progress 1/7/2026 DAVID FEILER
Permit Finaled 1/8/2026 RICHARD STEINBACH
CofO Issued 1/8/2026 RICHARD STEINBACH
Permit Finaled 1/8/2026 RICHARD STEINBACH

Permit Application Clearance Information

Miscellaneous Cleared 3/16/2021 MIGUEL GAMBOA
Miscellaneous Cleared 3/16/2021 MIGUEL GAMBOA
Address approval Cleared 3/17/2021 NIKTA MOUSAVI
Highway dedication Cleared 4/7/2021 RAYMOND MUGAMBWA
Low Impact Development Cleared 6/3/2022 ANDRES COVARRUBIAS
Coastal Zone Cleared 11/2/2022 NATHAN ROMINE
Frnt yard landscape/Water mgmt Cleared 11/2/2022 NATHAN ROMINE
Specific Plan Cleared 11/2/2022 NATHAN ROMINE
ZI Cleared 11/2/2022 NATHAN ROMINE
ZI Cleared 11/2/2022 NATHAN ROMINE
ZI Cleared 11/2/2022 NATHAN ROMINE
Specific Plan Cleared 11/7/2022 FREDDY GARCIA
Miscellaneous Cleared 11/18/2022 NATHAN ROMINE
Eng Process Fee Ord 176,300 Cleared 12/30/2022 DINAH GARIN
Roof/Waste drainage to street Cleared 12/30/2022 DINAH GARIN
Sewer availability Cleared 12/30/2022 DINAH GARIN

Contact Information

Contractor Owner-Builder       ,
Engineer Rahman,, Moksudur; Lic. No.: C69263 14616 MCKENDREE AVE      CHINO, CA 91708

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Special/Order Compliance 9/20/2024 Not Ready for Inspection DAVID FEILER
PLUMBING-Rough 12/10/2024 Partial Approval HERBERT GIRON
Deputy Drilled-In Anchors 12/19/2024 Conditional Approval HERBERT GIRON
Footing/Foundation/Slab 1/14/2025 Not Ready for Inspection HERBERT GIRON
METHANE-Barrier 1/14/2025 Not Ready for Inspection HERBERT GIRON
METHANE-Subgrade 1/14/2025 Not Ready for Inspection HERBERT GIRON
Sewer 1/14/2025 Partial Approval HERBERT GIRON
Underground Mechanical 1/14/2025 Partial Approval HERBERT GIRON
Footing/Foundation/Slab 2/3/2025 Partial Approval HERBERT GIRON
Footing/Foundation/Slab 3/5/2025 Partial Approval HERBERT GIRON
Footing/Foundation/Slab 3/24/2025 Partial Approval JESUS RODRIGUEZ
Gas Test 4/25/2025 Approved JESUS RODRIGUEZ
PLUMBING-Rough 4/25/2025 Approved JESUS RODRIGUEZ
ELECTRICAL-Rough 5/16/2025 Approved JESUS RODRIGUEZ
HVAC-Rough 5/16/2025 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 5/22/2025 Corrections Issued JESUS RODRIGUEZ
BUILDING-Rough-Frame 7/3/2025 Conditional Approval JESUS RODRIGUEZ
Footing/Foundation/Slab 7/3/2025 Approved JESUS RODRIGUEZ
Green Building Rough 7/3/2025 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 7/3/2025 Approved JESUS RODRIGUEZ
Shower Pan 7/3/2025 Approved JESUS RODRIGUEZ
Verify Sprinkler Sign Off 7/3/2025 Approved JESUS RODRIGUEZ
Insulation 7/10/2025 Corrections Issued JESUS PINEDA
Insulation 7/14/2025 Corrections Issued JESUS PINEDA
Drywall Nailing 7/23/2025 Approved TEMISTOCLES CAAL
Final 7/23/2025 Corrections Issued TEMISTOCLES CAAL
BUILDING-Rough-Frame 11/20/2025 Approved RUBEN RIVAS
Final 11/20/2025 Not Ready for Inspection RUBEN RIVAS
Green Building Final 11/20/2025 Approved RUBEN RIVAS
HVAC-Final 11/20/2025 Approved RUBEN RIVAS
METHANE-Final 11/20/2025 Not Ready for Inspection RUBEN RIVAS
SGSOV-Seismic Gas S/O Valve 11/20/2025 SGSOV Approved RUBEN RIVAS
Smoke Detectors 11/20/2025 Not Ready for Inspection RUBEN RIVAS
ELECTRICAL-Final 11/21/2025 Approved RUBEN RIVAS
Service/Power Release 11/21/2025 Approved RUBEN RIVAS
Final 12/17/2025 Corrections Issued RUBEN RIVAS
Gas Test 12/17/2025 Approved RUBEN RIVAS
PLUMBING-Final 12/17/2025 Approved RUBEN RIVAS
Smoke Detectors 12/17/2025 Approved RUBEN RIVAS
HVAC-Final 12/22/2025 Approved RUBEN RIVAS
Final 12/23/2025 Partial Approval RUBEN RIVAS
Final 12/30/2025 Corrections Issued RUBEN RIVAS
Final 1/2/2026 OK to Issue CofO RUBEN RIVAS