12010 W BRADDOCK DR 90230

Certificate Information: 12010 W BRADDOCK DR 90230

Application / Permit
20014-20000-04797
Plan Check / Job No.
B20VN14194
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD NEW (19'-0"x 20'-0") COVERED PATIO/ LAUNDRY TO (E) DETACHED 2-CAR GARAGE & NEW (19'-0"x 40'-0") 2ND STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) and (d).
Permit Issued
Issued on 11/3/2021
Issuing Office
Current Status
CofO Issued on 7/10/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/2/2020 APPLICANT
Assigned to Plan Check Engineer 11/24/2020 TROY DEGUZMAN
Corrections Issued 11/28/2020 TROY DEGUZMAN
Quality Review Completed 11/30/2020 CHON CHIO KUO
Building Plans Picked Up 12/1/2020 APPLICANT
Applicant returned to address corrections 6/2/2021 TROY DEGUZMAN
Applicant returned to address corrections 6/11/2021 TROY DEGUZMAN
Applicant returned to address corrections 6/14/2021 TROY DEGUZMAN
Applicant returned to address corrections 10/20/2021 TROY DEGUZMAN
Plan Check Approved 11/1/2021 TROY DEGUZMAN
Issued 11/3/2021 APPLICANT
CofO in Progress 7/10/2023 JESUS RODRIGUEZ
Permit Finaled 7/10/2023 DANIEL ORRANTE
CofO Issued 7/10/2023 DANIEL ORRANTE
Permit Finaled 7/10/2023 DANIEL ORRANTE

Permit Application Clearance Information

Green Code Cleared 11/27/2020 TROY DEGUZMAN
Address approval Cleared 4/16/2021 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 4/19/2021 ANTHONY MAINEZ
Sewer availability Cleared 4/19/2021 ANTHONY MAINEZ
Specific Plan Cleared 8/11/2021 LAUREN PADICK
Highway dedication Cleared 8/13/2021 HISASHI KOBAYAKAWA
Hydrant and Access approval Cleared 9/7/2021 MATTHEW CRAIG
Low Impact Development Cleared 10/18/2021 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 10/22/2021 SAUL GARCIA

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/8/2022 Corrections Issued STEPHANIE SWANSON
PLUMBING-Rough 6/13/2022 Partial Approval JESUS RODRIGUEZ
Footing/Foundation/Slab 6/24/2022 Conditional Approval JESUS RODRIGUEZ
Footing/Foundation/Slab 6/30/2022 Partial Approval JESUS RODRIGUEZ
Footing/Foundation/Slab 7/20/2022 Corrections Issued JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 8/9/2022 Corrections Issued HERBERT GIRON
ELECTRICAL-Rough 9/12/2022 Not Ready for Inspection JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 9/28/2022 Partial Approval JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 10/17/2022 Corrections Issued HERBERT GIRON
Deputy Wood Construction 11/2/2022 Conditional Approval JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 11/3/2022 Corrections Issued JESUS RODRIGUEZ
ELECTRICAL-Rough 11/15/2022 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 11/15/2022 Approved JESUS RODRIGUEZ
Footing/Foundation/Slab 11/15/2022 Approved JESUS RODRIGUEZ
HVAC-Rough 11/15/2022 Corrections Issued JESUS RODRIGUEZ
Interior/Exterior Lathing 11/15/2022 Approved JESUS RODRIGUEZ
PLUMBING-Rough 11/15/2022 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 11/22/2022 Approved JESUS RODRIGUEZ
Final 11/22/2022 Corrections Issued JESUS RODRIGUEZ
Green Building Rough 11/22/2022 Approved JESUS RODRIGUEZ
HVAC-Rough 11/22/2022 Approved JESUS RODRIGUEZ
Insulation 11/22/2022 Approved JESUS RODRIGUEZ
Drywall Nailing 12/2/2022 Approved JESUS RODRIGUEZ
Shower Pan 12/2/2022 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 12/9/2022 Approved JOHNNY MIRANDA
Final 2/2/2023 Corrections Issued JESUS RODRIGUEZ
Green Building Final 2/2/2023 Not Ready for Inspection JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 2/2/2023 SGSOV Not Ready JESUS RODRIGUEZ
Smoke Detectors 2/2/2023 Not Ready for Inspection JESUS RODRIGUEZ
ELECTRICAL-Final 3/28/2023 Approved JESUS RODRIGUEZ
Final 3/28/2023 Corrections Issued JESUS RODRIGUEZ
Green Building Final 3/28/2023 Approved JESUS RODRIGUEZ
HVAC-Final 3/28/2023 Approved JESUS RODRIGUEZ
PLUMBING-Final 3/28/2023 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 3/28/2023 SGSOV Approved JESUS RODRIGUEZ
Service/Power Release 3/28/2023 Approved JESUS RODRIGUEZ
Smoke Detectors 3/28/2023 Approved JESUS RODRIGUEZ
Final 7/10/2023 OK to Issue CofO JESUS RODRIGUEZ