5230 N HARTWICK ST 90041
Certificate Information: 5230 N HARTWICK ST 90041
- Application / Permit
- 20014-20000-04796
- Plan Check / Job No.
- B20VN14192
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD (30'-5 1/2"x 22'-11 7/8") ACCESSORY DWELLING UNIT ABOVE (E) 2- CAR DETACHED GARAGE PER LAMC 12.22 A.33 (c) and (d) WITH NFPA-13D FIRE SPRINKLER THROUGHOUT. WORK PER ENGINEER.
- Permit Issued
- Issued on 4/20/2022
- Issuing Office
- Current Status
- CofO Issued on 6/4/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/29/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/24/2020 | TROY DEGUZMAN |
| Corrections Issued | 12/3/2020 | TROY DEGUZMAN |
| Quality Review Completed | 12/3/2020 | CHON CHIO KUO |
| Building Plans Picked Up | 12/4/2020 | APPLICANT |
| Applicant returned to address corrections | 7/21/2021 | TROY DEGUZMAN |
| Applicant returned to address corrections | 11/16/2021 | TROY DEGUZMAN |
| Applicant returned to address corrections | 1/25/2022 | TROY DEGUZMAN |
| Applicant returned to address corrections | 3/4/2022 | TROY DEGUZMAN |
| Plan Check Approved | 3/30/2022 | TROY DEGUZMAN |
| Issued | 4/20/2022 | APPLICANT |
| CofO in Progress | 6/2/2026 | RONNIE MEDINA |
| Permit Finaled | 6/4/2026 | DEROLD HAUFF |
| CofO Issued | 6/4/2026 | DEROLD HAUFF |
| Permit Finaled | 6/4/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Green Code | Cleared | 12/1/2020 | TROY DEGUZMAN |
| Address approval | Cleared | 12/23/2020 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 12/24/2020 | CECILIO NAVARRO |
| Sewer availability | Cleared | 12/24/2020 | CECILIO NAVARRO |
| Hydrant and Access approval | Cleared | 1/22/2021 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 6/23/2021 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 6/29/2021 | JEANIE LAM |
| GPI Written Notices | Cleared | 7/13/2021 | TROY DEGUZMAN |
| Grading Pre-Inspection | Cleared | 7/13/2021 | TROY DEGUZMAN |
Contact Information
| Architect | Erceg,, Jelena Z; Lic. No.: C25773 | 7614 ROMAINE STREET WEST HOLLYWOOD, CA 90046 |
| Contractor | Owner-Builder | , |
| Engineer | Isaac,, Raymond; Lic. No.: C84605 | 21040 PARTHENIA ST APT 14 CANOGA PARK, CA 91304 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/15/2022 | Approved | BRIAN SULLIVAN |
| Piling/Pier/Caisson | 5/11/2023 | Corrections Issued | BRIAN SULLIVAN |
| Piling/Pier/Caisson | 5/18/2023 | Approved | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 6/23/2023 | Partial Approval | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 9/25/2023 | Approved | RICHARD DOCKUS |
| Floor/Roof Diaphrgm/Shear Wall | 12/8/2023 | Partial Approval | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/26/2023 | Partial Approval | AMY COLIN |
| Floor/Roof Diaphrgm/Shear Wall | 1/9/2024 | Partial Approval | CRAIG VAUGHAN |
| Sewer | 5/7/2024 | Approved | CRAIG VAUGHAN |
| Underground Mechanical | 5/7/2024 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 8/8/2024 | Partial Approval | CRAIG VAUGHAN |
| Rough-Elec/Plmb/HVAC | 12/26/2024 | Corrections Issued | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 4/2/2025 | Approved | DAVID WILLIAMS |
| ELECTRICAL-Rough | 4/2/2025 | Approved | DAVID WILLIAMS |
| Green Building Rough | 4/2/2025 | Approved | DAVID WILLIAMS |
| HVAC-Rough | 4/2/2025 | Approved | DAVID WILLIAMS |
| PLUMBING-Rough | 4/2/2025 | Approved | DAVID WILLIAMS |
| Interior/Exterior Lathing | 5/1/2025 | Partial Approval | BRENDAN MORELLI |
| Service/Power Release | 5/1/2025 | Not Ready for Inspection | BRENDAN MORELLI |
| Insulation | 7/2/2025 | Approved | DAVID WILLIAMS |
| Drywall Nailing | 7/31/2025 | Approved | DAVID WILLIAMS |
| Shower Pan | 9/4/2025 | Approved | GEM DE OCAMPO |
| Interior/Exterior Lathing | 9/19/2025 | Approved | JOSH MEISTER |
| Final | 6/1/2026 | OK to Issue CofO | RONNIE MEDINA |
| Green Building Final | 6/1/2026 | Approved | RONNIE MEDINA |
| SGSOV-Seismic Gas S/O Valve | 6/1/2026 | SGSOV Approved | RONNIE MEDINA |
| Smoke Detectors | 6/1/2026 | Approved | RONNIE MEDINA |