6530 S 4TH AVE 90043

Certificate Information: 6530 S 4TH AVE 90043

Application / Permit
20014-20000-04773
Plan Check / Job No.
B20VN14138
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 23' X 15'6" IRREGULAR SHAPED ADDITION TO (E) SFD FOR A NEW BEDROOM, BATHROOM, HALLWAY ,INTERIOR REMODEL TO (E) SFD TO REMODEL (1) BEDROOM , REMOVE (1) BATHROOM , CREATE HALLWAY , ALL WORK PER ENGINEERING
Permit Issued
Issued on 12/31/2020
Issuing Office
Current Status
CofO Issued on 6/17/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/28/2020 APPLICANT
Assigned to Plan Check Engineer 11/6/2020 RARES BODEA
Corrections Issued 11/6/2020 RARES BODEA
Building Plans Picked Up 11/10/2020 APPLICANT
Plan Check Approved 12/21/2020 RARES BODEA
Issued 12/31/2020 APPLICANT
CofO in Progress 6/10/2021 FREDDIE RIVERA
Permit Finaled 6/17/2021 DEROLD HAUFF
CofO Issued 6/17/2021 DEROLD HAUFF
Permit Finaled 6/17/2021 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/10/2020 RENZ SORIANO
Roof/Waste drainage to street Cleared 12/10/2020 RENZ SORIANO
Sewer availability Cleared 12/14/2020 RENZ SORIANO

Contact Information

Contractor Verdugo Construction Inc; Lic. No.: 447014-B 411 E HUNTINGTON DR PMB 234      ARCADIA, CA 91006
Engineer Manesh,, Behnam Abraham; Lic. No.: C38454 17337 VENTURA BLVD STE 112      ENCINO, CA 91316

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/15/2021 Corrections Issued FREDDIE RIVERA
Deputy Drilled-In Anchors 1/20/2021 No Access for Inspection ELMER BLAND
Footing/Foundation/Slab 1/20/2021 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 2/3/2021 Partial Approval FREDDIE RIVERA
Insulation 2/3/2021 Partial Approval FREDDIE RIVERA
PLUMBING-Rough 2/3/2021 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 2/22/2021 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 3/15/2021 Approved FREDDIE RIVERA
ELECTRICAL-Rough 3/15/2021 Approved FREDDIE RIVERA
Green Building Rough 3/15/2021 Approved FREDDIE RIVERA
HVAC-Rough 3/15/2021 Approved FREDDIE RIVERA
PLUMBING-Rough 3/15/2021 Approved FREDDIE RIVERA
Insulation 3/24/2021 Approved FREDDIE RIVERA
Interior/Exterior Lathing 3/24/2021 Approved FREDDIE RIVERA
Drywall Nailing 4/8/2021 Approved SABAS ALONSO
ELECTRICAL-Final 5/19/2021 Approved DAVID FEILER
Final 5/19/2021 Not Ready for Inspection DAVID FEILER
Green Building Final 5/19/2021 Approved DAVID FEILER
HVAC-Final 5/19/2021 Corrections Issued DAVID FEILER
PLUMBING-Final 5/19/2021 Approved DAVID FEILER
SGSOV-Seismic Gas S/O Valve 5/19/2021 SGSOV Approved DAVID FEILER
Smoke Detectors 5/19/2021 Approved DAVID FEILER
Final 6/10/2021 OK to Issue CofO FREDDIE RIVERA