2323 W LOY LANE 90041
Certificate Information: 2323 W LOY LANE 90041
- Application / Permit
- 20014-20000-04772
- Plan Check / Job No.
- B20VN14131
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 15'-10"x 11'-4" (197.3 SF) ADDITION TO (E) SINGLE FAMILY DWELLING W/ ATT. GARAGE AND INTERIOR REMODEL; ALL WORK PER ENGINEERING DESIGN
- Permit Issued
- Issued on 4/19/2021
- Issuing Office
- Current Status
- CofO Issued on 8/26/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/28/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/29/2020 | SEAN SHAHMIRI |
| Corrections Issued | 11/4/2020 | SEAN SHAHMIRI |
| Quality Review Completed | 11/4/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 11/5/2020 | APPLICANT |
| Applicant returned to address corrections | 1/5/2021 | SEAN SHAHMIRI |
| Plan Check Approved | 3/23/2021 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 3/25/2021 | SEAN SHAHMIRI |
| Issued | 4/19/2021 | APPLICANT |
| CofO in Progress | 8/24/2022 | CHARLES BOGHOSKHAN |
| CofO Issued | 8/26/2022 | DEROLD HAUFF |
| Permit Finaled | 8/26/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/3/2020 | ROSA SILVA |
| Roof/Waste drainage to street | Cleared | 12/3/2020 | ROSA SILVA |
| Sewer availability | Cleared | 12/3/2020 | ROSA SILVA |
| Hydrant and Access approval | Cleared | 1/21/2021 | MATTHEW CRAIG |
Contact Information
| Architect | Brookman,, Alan; Lic. No.: C32503 | 200 S. VISTA BONITA AVENUE GLENDORA, CA 91741 |
| Contractor | Hartman Baldwin Inc; Lic. No.: 653340-B | 100 WEST FOOTHILL BLVD CLAREMONT, CA 91711 |
| Engineer | Mutka,, Jason Richard; Lic. No.: C72255 | PO BOX 77144 CORONA, CA 92877 |
| Geologist | Cugno,, Giuseppe; Lic. No.: EG1804 | 1461 E CHEVY CHASE DR 200 BYER GEOTECHNICAL, INC. GLENDALE, CA 91206 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/15/2021 | No Access for Inspection | CRAIG VAUGHAN |
| METHANE-Barrier | 7/15/2021 | No Access for Inspection | CRAIG VAUGHAN |
| METHANE-Subgrade | 7/15/2021 | No Access for Inspection | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 7/21/2021 | Corrections Issued | CRAIG VAUGHAN |
| METHANE-Barrier | 7/21/2021 | No Access for Inspection | CRAIG VAUGHAN |
| METHANE-Subgrade | 7/21/2021 | No Access for Inspection | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 7/26/2021 | Approved | CRAIG VAUGHAN |
| METHANE-Barrier | 7/26/2021 | Approved | CRAIG VAUGHAN |
| METHANE-Subgrade | 7/26/2021 | Approved | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/2/2021 | Corrections Issued | CRAIG VAUGHAN |
| PLUMBING-Rough | 8/2/2021 | Corrections Issued | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 8/4/2021 | Partial Approval | CRAIG VAUGHAN |
| PLUMBING-Rough | 8/4/2021 | Partial Approval | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 10/1/2021 | Approved | CRAIG VAUGHAN |
| HVAC-Rough | 10/1/2021 | Corrections Issued | CRAIG VAUGHAN |
| PLUMBING-Rough | 10/1/2021 | Approved | CRAIG VAUGHAN |
| Wood Frame | 10/1/2021 | Corrections Issued | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 10/27/2021 | Approved | CRAIG VAUGHAN |
| Green Building Rough | 10/27/2021 | Approved | CRAIG VAUGHAN |
| HVAC-Rough | 10/27/2021 | Approved | CRAIG VAUGHAN |
| METHANE-Rough | 10/27/2021 | Approved | CRAIG VAUGHAN |
| Drywall Nailing | 11/3/2021 | Approved | CHARLES BOGHOSKHAN |
| Interior/Exterior Lathing | 11/9/2021 | Approved | CHARLES BOGHOSKHAN |
| Final | 5/10/2022 | Corrections Issued | CRAIG VAUGHAN |
| Green Building Final | 5/10/2022 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 5/10/2022 | SGSOV Approved | CRAIG VAUGHAN |
| Smoke Detectors | 5/10/2022 | Approved | CRAIG VAUGHAN |
| Final | 8/23/2022 | OK to Issue CofO | CHARLES BOGHOSKHAN |