6124-6126 N ALCOVE AVE 91606

Certificate Information: 6124-6126 N ALCOVE AVE 91606

Application / Permit
20014-20000-04769
Plan Check / Job No.
B20VN14126
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD (18'-7"x 23'-3") 2nd FLOOR AND CONVERT (E) (18'-7"x 20'-3") ATT. GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) and (e), ADD/EXPAND (13'-2"x 5'-5") (E) BEDROOM & INT REMODEL TO (E) SFD. WORK PER ENGINEER.
Permit Issued
Issued on 8/19/2022
Issuing Office
Valley
Current Status
CofO Issued on 8/16/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/30/2020 APPLICANT
Assigned to Plan Check Engineer 11/5/2020 TROY DEGUZMAN
Corrections Issued 11/12/2020 TROY DEGUZMAN
Quality Review Completed 11/12/2020 CHON CHIO KUO
Building Plans Picked Up 11/16/2020 APPLICANT
Plan Check Approved 7/8/2021 TROY DEGUZMAN
Issued 8/19/2022 APPLICANT
CofO in Progress 8/14/2024 JUAN VALENZUELA
Permit Finaled 8/16/2024 DANIEL ORRANTE
CofO Issued 8/16/2024 DANIEL ORRANTE
Permit Finaled 8/16/2024 DANIEL ORRANTE

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 12/29/2020 MARKOS PEREZ-BRAN
Sewer availability Cleared 12/29/2020 MARKOS PEREZ-BRAN
Eng Process Fee Ord 176,300 Cleared 12/30/2020 MARKOS PEREZ-BRAN
Low Impact Development Cleared 6/10/2021 MITESH PATEL
Address approval Cleared 6/16/2021 GABRIEL ROBLES
Address approval Cleared 6/16/2021 GABRIEL ROBLES
Green Code Cleared 7/8/2021 TROY DEGUZMAN

Contact Information

Contractor L A Home Contractor Inc; Lic. No.: 1027193-B 14103 BURBANK BLVD      SHERMAN OAKS, CA 91401
Engineer Maalouf,, Sami; Lic. No.: C53210 15445 VENTURA BLVD STE 367      SHERMAN OAKS, CA 91403

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/15/2023 Conditional Approval KIRK SANDERS
Footing/Foundation/Slab 2/16/2023 Approved KIRK SANDERS
BUILDING-Rough-Frame 2/22/2023 Corrections Issued KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 2/22/2023 Partial Approval KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 3/7/2023 Not Ready for Inspection KIRK SANDERS
Insulation 3/7/2023 Partial Approval KIRK SANDERS
Drywall Nailing 3/8/2023 Not Ready for Inspection KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 3/8/2023 Partial Approval KIRK SANDERS
Green Building Rough 3/8/2023 Not Ready for Inspection KIRK SANDERS
Deputy Wood Construction 5/11/2023 Conditional Approval JUAN VALENZUELA
ELECTRICAL-Rough 5/31/2023 Partial Approval KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 5/31/2023 Corrections Issued KIRK SANDERS
HVAC-Rough 5/31/2023 Partial Approval KIRK SANDERS
PLUMBING-Rough 5/31/2023 Corrections Issued KIRK SANDERS
Interior/Exterior Lathing 6/14/2023 Partial Approval KIRK SANDERS
PLUMBING-Rough 6/14/2023 Partial Approval KIRK SANDERS
BUILDING-Rough-Frame 6/21/2023 Partial Approval KIRK SANDERS
Green Building Rough 6/21/2023 Partial Approval KIRK SANDERS
Insulation 6/21/2023 Not Ready for Inspection KIRK SANDERS
Interior/Exterior Lathing 6/21/2023 Not Ready for Inspection KIRK SANDERS
Shower Pan 6/21/2023 Partial Approval KIRK SANDERS
Insulation 7/24/2023 Partial Approval JUAN VALENZUELA
Drywall Nailing 8/2/2023 Partial Approval KIRK SANDERS
Green Building Rough 8/2/2023 Partial Approval KIRK SANDERS
Interior/Exterior Lathing 8/2/2023 Partial Approval KIRK SANDERS
BUILDING-Rough-Frame 11/28/2023 Corrections Issued KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 8/6/2024 SGSOV Approved OGANES TARAKHCHYAN
Smoke Detectors 8/6/2024 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 8/14/2024 Approved JUAN VALENZUELA
Drywall Nailing 8/14/2024 Approved JUAN VALENZUELA
Final 8/14/2024 OK to Issue CofO JUAN VALENZUELA
Green Building Final 8/14/2024 Approved JUAN VALENZUELA
Green Building Rough 8/14/2024 Approved JUAN VALENZUELA