6124-6126 N ALCOVE AVE 91606
Certificate Information: 6124-6126 N ALCOVE AVE 91606
- Application / Permit
- 20014-20000-04769
- Plan Check / Job No.
- B20VN14126
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD (18'-7"x 23'-3") 2nd FLOOR AND CONVERT (E) (18'-7"x 20'-3") ATT. GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) and (e), ADD/EXPAND (13'-2"x 5'-5") (E) BEDROOM & INT REMODEL TO (E) SFD. WORK PER ENGINEER.
- Permit Issued
- Issued on 8/19/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/16/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/30/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/5/2020 | TROY DEGUZMAN |
| Corrections Issued | 11/12/2020 | TROY DEGUZMAN |
| Quality Review Completed | 11/12/2020 | CHON CHIO KUO |
| Building Plans Picked Up | 11/16/2020 | APPLICANT |
| Plan Check Approved | 7/8/2021 | TROY DEGUZMAN |
| Issued | 8/19/2022 | APPLICANT |
| CofO in Progress | 8/14/2024 | JUAN VALENZUELA |
| Permit Finaled | 8/16/2024 | DANIEL ORRANTE |
| CofO Issued | 8/16/2024 | DANIEL ORRANTE |
| Permit Finaled | 8/16/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 12/29/2020 | MARKOS PEREZ-BRAN |
| Sewer availability | Cleared | 12/29/2020 | MARKOS PEREZ-BRAN |
| Eng Process Fee Ord 176,300 | Cleared | 12/30/2020 | MARKOS PEREZ-BRAN |
| Low Impact Development | Cleared | 6/10/2021 | MITESH PATEL |
| Address approval | Cleared | 6/16/2021 | GABRIEL ROBLES |
| Address approval | Cleared | 6/16/2021 | GABRIEL ROBLES |
| Green Code | Cleared | 7/8/2021 | TROY DEGUZMAN |
Contact Information
| Contractor | L A Home Contractor Inc; Lic. No.: 1027193-B | 14103 BURBANK BLVD SHERMAN OAKS, CA 91401 |
| Engineer | Maalouf,, Sami; Lic. No.: C53210 | 15445 VENTURA BLVD STE 367 SHERMAN OAKS, CA 91403 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/15/2023 | Conditional Approval | KIRK SANDERS |
| Footing/Foundation/Slab | 2/16/2023 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 2/22/2023 | Corrections Issued | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 2/22/2023 | Partial Approval | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 3/7/2023 | Not Ready for Inspection | KIRK SANDERS |
| Insulation | 3/7/2023 | Partial Approval | KIRK SANDERS |
| Drywall Nailing | 3/8/2023 | Not Ready for Inspection | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 3/8/2023 | Partial Approval | KIRK SANDERS |
| Green Building Rough | 3/8/2023 | Not Ready for Inspection | KIRK SANDERS |
| Deputy Wood Construction | 5/11/2023 | Conditional Approval | JUAN VALENZUELA |
| ELECTRICAL-Rough | 5/31/2023 | Partial Approval | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 5/31/2023 | Corrections Issued | KIRK SANDERS |
| HVAC-Rough | 5/31/2023 | Partial Approval | KIRK SANDERS |
| PLUMBING-Rough | 5/31/2023 | Corrections Issued | KIRK SANDERS |
| Interior/Exterior Lathing | 6/14/2023 | Partial Approval | KIRK SANDERS |
| PLUMBING-Rough | 6/14/2023 | Partial Approval | KIRK SANDERS |
| BUILDING-Rough-Frame | 6/21/2023 | Partial Approval | KIRK SANDERS |
| Green Building Rough | 6/21/2023 | Partial Approval | KIRK SANDERS |
| Insulation | 6/21/2023 | Not Ready for Inspection | KIRK SANDERS |
| Interior/Exterior Lathing | 6/21/2023 | Not Ready for Inspection | KIRK SANDERS |
| Shower Pan | 6/21/2023 | Partial Approval | KIRK SANDERS |
| Insulation | 7/24/2023 | Partial Approval | JUAN VALENZUELA |
| Drywall Nailing | 8/2/2023 | Partial Approval | KIRK SANDERS |
| Green Building Rough | 8/2/2023 | Partial Approval | KIRK SANDERS |
| Interior/Exterior Lathing | 8/2/2023 | Partial Approval | KIRK SANDERS |
| BUILDING-Rough-Frame | 11/28/2023 | Corrections Issued | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 8/6/2024 | SGSOV Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 8/6/2024 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 8/14/2024 | Approved | JUAN VALENZUELA |
| Drywall Nailing | 8/14/2024 | Approved | JUAN VALENZUELA |
| Final | 8/14/2024 | OK to Issue CofO | JUAN VALENZUELA |
| Green Building Final | 8/14/2024 | Approved | JUAN VALENZUELA |
| Green Building Rough | 8/14/2024 | Approved | JUAN VALENZUELA |