8022 N WILKINSON AVE 91605

Certificate Information: 8022 N WILKINSON AVE 91605

Application / Permit
20014-20000-04767
Plan Check / Job No.
B20VN14123
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT THE (E) 18' x 20' GARAGE INTO A (N) ACCESSORY DWELLING UNIT AND 31' x 25' ADDITION PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 6/27/2022
Issuing Office
Current Status
CofO Issued on 4/25/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/28/2020 APPLICANT
Assigned to Plan Check Engineer 11/6/2020 JEFFREY TANGONAN
Corrections Issued 11/8/2020 JEFFREY TANGONAN
Applicant returned to address corrections 6/17/2022 JEFFREY TANGONAN
Issued 6/27/2022 APPLICANT
Building Plans Picked Up 6/28/2022 APPLICANT
CofO in Progress 4/25/2023 MATTHEW NELSON
CofO Issued 4/25/2023 MICHAEL SMITH
Permit Finaled 4/25/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 1/19/2021 JOHN TRIANTAFYLLOS
Permit Cleared 1/19/2021 JOHN TRIANTAFYLLOS
Construction near power lines Cleared 2/10/2021 RIDWAN HARDY
Low Impact Development Cleared 5/19/2022 ROGELIO CORTES
Sewer availability Cleared 6/1/2022 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 6/23/2022 JOSE DUARTE-DIAZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MATTHEW NELSON, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/29/2022 Corrections Issued WILLIAM WREN
PLUMBING-Rough 9/2/2022 Partial Approval CHRISTOPHER DELLEFIELD
Footing/Foundation/Slab 9/12/2022 Corrections Issued DEANDRE HOFFMAN
Excavation/Setback/Form/Re-Bar 9/16/2022 Approved WILLIAM WREN
Footing/Foundation/Slab 9/16/2022 Approved WILLIAM WREN
BUILDING-Rough-Frame 10/3/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 10/3/2022 Approved CHRISTOPHER DELLEFIELD
Wood Frame 10/3/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
PLUMBING-Rough 10/21/2022 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 11/9/2022 Corrections Issued CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 11/14/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 11/14/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
HVAC-Rough 11/14/2022 Corrections Issued CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 11/17/2022 Conditional Approval CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 11/17/2022 Partial Approval CHRISTOPHER DELLEFIELD
Green Building Rough 11/17/2022 Approved CHRISTOPHER DELLEFIELD
Insulation 11/17/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Insulation 11/30/2022 Approved MATTHEW NELSON
Drywall Nailing 12/9/2022 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 12/9/2022 Partial Approval JENNIFER RABUCHIN
Shower Pan 12/27/2022 Approved MATTHEW NELSON
Sewer 1/24/2023 Approved MATTHEW NELSON
Underground Mechanical 2/3/2023 Approved JOHN COLEMAN
Service/Power Release 2/28/2023 Not Ready for Inspection MATTHEW NELSON
BUILDING-Rough-Frame 4/19/2023 Approved MATTHEW NELSON
Final 4/19/2023 Corrections Issued MATTHEW NELSON
Green Building Final 4/19/2023 Approved MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 4/19/2023 SGSOV Approved MATTHEW NELSON
Service/Power Release 4/19/2023 Not Ready for Inspection MATTHEW NELSON
Smoke Detectors 4/19/2023 Approved MATTHEW NELSON
ELECTRICAL-Final 4/24/2023 Approved MATTHEW NELSON
Final 4/24/2023 OK to Issue CofO MATTHEW NELSON
HVAC-Final 4/24/2023 Approved MATTHEW NELSON
PLUMBING-Final 4/24/2023 Approved MATTHEW NELSON