920 N KAGAWA ST 90272
Certificate Information: 920 N KAGAWA ST 90272
- Application / Permit
- 20014-20000-04755
- Plan Check / Job No.
- B20VN14104
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2-STORY ADDITION & MAJOR REMODEL TO (E) 2-STORY SFD W/ ATTACHED GARAGE (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
- Permit Issued
- Issued on 6/5/2021
- Issuing Office
- Current Status
- Issued on 6/5/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/28/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/24/2020 | NILOOFAR MEHRAIN |
| Corrections Issued | 12/8/2020 | NILOOFAR MEHRAIN |
| Quality Review Completed | 12/10/2020 | CHON CHIO KUO |
| Building Plans Picked Up | 12/11/2020 | APPLICANT |
| Applicant returned to address corrections | 2/4/2021 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 3/11/2021 | NILOOFAR MEHRAIN |
| Plan Check Approved | 4/27/2021 | NILOOFAR MEHRAIN |
| Issued | 6/5/2021 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/6/2021 | RAYMOND MUGAMBWA |
| GPI Written Notices | Cleared | 3/11/2021 | NILOOFAR MEHRAIN |
| Grading Pre-Inspection | Cleared | 3/11/2021 | NILOOFAR MEHRAIN |
| Hydrant and Access approval | Cleared | 3/23/2021 | JOHN CONNEALLY |
| Sewer availability | Cleared | 4/14/2021 | DINAH GARIN |
| Low Impact Development | Cleared | 4/21/2021 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 4/28/2021 | HISASHI KOBAYAKAWA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Kim,, Taewon; Lic. No.: C80632 | 2800 PLAZA DEL AMO UNIT 161 TORRANCE, CA 90503 |
Inspector Information
| TEMISTOCLES CAAL, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
| JESUS PINEDA, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/8/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 9/24/2021 | Partial Approval | JUAN VALENZUELA |
| Green Building Rough | 9/24/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| Deputy Wood Construction | 9/27/2021 | Approved | DANIEL ORRANTE |
| Deputy Wood Construction | 10/18/2021 | Partial Approval | JOHN KIDWELL |
| Wood Frame | 10/18/2021 | Partial Inspection | JOHN KIDWELL |
| Deputy Drilled-In Anchors | 11/3/2021 | Approved | JOHN KIDWELL |
| Footing/Foundation/Slab | 11/3/2021 | Partial Approval | JOHN KIDWELL |
| Wood Frame | 11/3/2021 | Not Ready for Inspection | JOHN KIDWELL |
| Footing/Foundation/Slab | 11/12/2021 | Approved | JOHN KIDWELL |
| PLUMBING-Rough | 12/3/2021 | Approved | JOHN KIDWELL |
| BUILDING-Rough-Frame | 12/7/2021 | Not Ready for Inspection | JOHN KIDWELL |
| Green Building Rough | 12/7/2021 | Not Ready for Inspection | JOHN KIDWELL |
| HVAC-Rough | 12/7/2021 | Approved | JOHN KIDWELL |
| Deputy Wood Construction | 12/8/2021 | Partial Approval | JOHN KIDWELL |
| ELECTRICAL-Rough | 12/10/2021 | Corrections Issued | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 12/14/2021 | Partial Approval | JOHN KIDWELL |
| ELECTRICAL-Rough | 12/14/2021 | Approved | JOHN KIDWELL |
| Green Building Rough | 12/14/2021 | Approved | JOHN KIDWELL |
| PLUMBING-Rough | 12/14/2021 | Approved | JOHN KIDWELL |
| Insulation | 12/16/2021 | Conditional Approval | JOHN KIDWELL |
| Drywall Nailing | 12/21/2021 | Approved | JOHN KIDWELL |
| Underground Mechanical | 2/22/2022 | Approved | JOHN KIDWELL |
| Gas Test | 3/24/2022 | Approved | JOHN KIDWELL |
| PLUMBING-Final | 3/24/2022 | Partial Approval | JOHN KIDWELL |
| BUILDING-Rough-Frame | 5/10/2022 | Approved | JOHN KIDWELL |
| Final | 5/10/2022 | Corrections Issued | JOHN KIDWELL |
| Green Building Final | 5/10/2022 | Approved | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 5/10/2022 | SGSOV Approved | JOHN KIDWELL |
| Smoke Detectors | 5/10/2022 | Approved | JOHN KIDWELL |