920 N KAGAWA ST 90272

Certificate Information: 920 N KAGAWA ST 90272

Application / Permit
20014-20000-04755
Plan Check / Job No.
B20VN14104
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2-STORY ADDITION & MAJOR REMODEL TO (E) 2-STORY SFD W/ ATTACHED GARAGE (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
Permit Issued
Issued on 6/5/2021
Issuing Office
Current Status
Issued on 6/5/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/28/2020 APPLICANT
Assigned to Plan Check Engineer 11/24/2020 NILOOFAR MEHRAIN
Corrections Issued 12/8/2020 NILOOFAR MEHRAIN
Quality Review Completed 12/10/2020 CHON CHIO KUO
Building Plans Picked Up 12/11/2020 APPLICANT
Applicant returned to address corrections 2/4/2021 NILOOFAR MEHRAIN
Applicant returned to address corrections 3/11/2021 NILOOFAR MEHRAIN
Plan Check Approved 4/27/2021 NILOOFAR MEHRAIN
Issued 6/5/2021 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/6/2021 RAYMOND MUGAMBWA
GPI Written Notices Cleared 3/11/2021 NILOOFAR MEHRAIN
Grading Pre-Inspection Cleared 3/11/2021 NILOOFAR MEHRAIN
Hydrant and Access approval Cleared 3/23/2021 JOHN CONNEALLY
Sewer availability Cleared 4/14/2021 DINAH GARIN
Low Impact Development Cleared 4/21/2021 SUNG JOON WON
Roof/Waste drainage to street Cleared 4/28/2021 HISASHI KOBAYAKAWA

Contact Information

Contractor Owner-Builder       ,
Engineer Kim,, Taewon; Lic. No.: C80632 2800 PLAZA DEL AMO UNIT 161      TORRANCE, CA 90503

Inspector Information

TEMISTOCLES CAAL, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI
JESUS PINEDA, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/8/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 9/24/2021 Partial Approval JUAN VALENZUELA
Green Building Rough 9/24/2021 Not Ready for Inspection JUAN VALENZUELA
Deputy Wood Construction 9/27/2021 Approved DANIEL ORRANTE
Deputy Wood Construction 10/18/2021 Partial Approval JOHN KIDWELL
Wood Frame 10/18/2021 Partial Inspection JOHN KIDWELL
Deputy Drilled-In Anchors 11/3/2021 Approved JOHN KIDWELL
Footing/Foundation/Slab 11/3/2021 Partial Approval JOHN KIDWELL
Wood Frame 11/3/2021 Not Ready for Inspection JOHN KIDWELL
Footing/Foundation/Slab 11/12/2021 Approved JOHN KIDWELL
PLUMBING-Rough 12/3/2021 Approved JOHN KIDWELL
BUILDING-Rough-Frame 12/7/2021 Not Ready for Inspection JOHN KIDWELL
Green Building Rough 12/7/2021 Not Ready for Inspection JOHN KIDWELL
HVAC-Rough 12/7/2021 Approved JOHN KIDWELL
Deputy Wood Construction 12/8/2021 Partial Approval JOHN KIDWELL
ELECTRICAL-Rough 12/10/2021 Corrections Issued JUAN VALENZUELA
BUILDING-Rough-Frame 12/14/2021 Partial Approval JOHN KIDWELL
ELECTRICAL-Rough 12/14/2021 Approved JOHN KIDWELL
Green Building Rough 12/14/2021 Approved JOHN KIDWELL
PLUMBING-Rough 12/14/2021 Approved JOHN KIDWELL
Insulation 12/16/2021 Conditional Approval JOHN KIDWELL
Drywall Nailing 12/21/2021 Approved JOHN KIDWELL
Underground Mechanical 2/22/2022 Approved JOHN KIDWELL
Gas Test 3/24/2022 Approved JOHN KIDWELL
PLUMBING-Final 3/24/2022 Partial Approval JOHN KIDWELL
BUILDING-Rough-Frame 5/10/2022 Approved JOHN KIDWELL
Final 5/10/2022 Corrections Issued JOHN KIDWELL
Green Building Final 5/10/2022 Approved JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 5/10/2022 SGSOV Approved JOHN KIDWELL
Smoke Detectors 5/10/2022 Approved JOHN KIDWELL